11979 W NEENACH ST 91352
Certificate Information: 11979 W NEENACH ST 91352
- Application / Permit
- 24014-20000-01514
- Plan Check / Job No.
- B24VN04948
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 15'-3" X 23' ADDITION TO AND CONVERT (E) DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22.A.33(c) AND (d).
- Permit Issued
- Issued on 11/4/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 2/14/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/12/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 4/19/2024 | MADISON ODELL |
| Corrections Issued | 4/19/2024 | MADISON ODELL |
| Building Plans Picked Up | 4/22/2024 | APPLICANT |
| Applicant returned to address corrections | 5/13/2024 | ANGELICA DAVE |
| Applicant returned to address corrections | 10/22/2024 | GIOVANNY CHAVEZ |
| Plan Check Approved | 10/29/2024 | JEROME MAGAT PALMA |
| Issued | 11/4/2024 | APPLICANT |
| CofO in Progress | 9/2/2025 | MATTHEW NELSON |
| Permit Finaled | 2/14/2026 | MICHAEL PELHAM |
| CofO Issued | 2/14/2026 | MICHAEL PELHAM |
| Permit Finaled | 2/14/2026 | MICHAEL PELHAM |
Permit Application Clearance Information
| Address approval | Cleared | 4/29/2024 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 4/29/2024 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 5/6/2024 | CARLOS AGUILERA |
| Sewer availability | Cleared | 5/6/2024 | CARLOS AGUILERA |
| Construction near power lines | Cleared | 8/12/2024 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Lao,, Arturo Begino; Lic. No.: C56687 | 16348 MIDWOOD DR GRANADA HILLS, CA 91344 |
Inspector Information
| WILLIAM WREN, (818) 374-1170 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/31/2024 | Corrections Issued | MATTHEW NELSON |
| Footing/Foundation/Slab | 1/22/2025 | Partial Approval | MATTHEW NELSON |
| Footing/Foundation/Slab | 1/31/2025 | Approved | MATTHEW NELSON |
| BUILDING-Rough-Frame | 3/4/2025 | Partial Approval | MATTHEW NELSON |
| Green Building Rough | 3/4/2025 | Not Ready for Inspection | MATTHEW NELSON |
| MERV13>=Rough | 3/4/2025 | Not Ready for Inspection | MATTHEW NELSON |
| PLUMBING-Rough | 3/4/2025 | Partial Approval | MATTHEW NELSON |
| BUILDING-Rough-Frame | 3/26/2025 | Not Ready for Inspection | MATTHEW NELSON |
| ELECTRICAL-Rough | 3/26/2025 | Approved | MATTHEW NELSON |
| Green Building Rough | 3/26/2025 | Not Ready for Inspection | MATTHEW NELSON |
| MERV13>=Rough | 3/26/2025 | Not Ready for Inspection | MATTHEW NELSON |
| PLUMBING-Rough | 3/26/2025 | Corrections Issued | MATTHEW NELSON |
| BUILDING-Rough-Frame | 4/9/2025 | Approved | MATTHEW NELSON |
| Green Building Rough | 4/9/2025 | Approved | MATTHEW NELSON |
| HVAC-Rough | 4/9/2025 | Approved | MATTHEW NELSON |
| MERV13>=Rough | 4/9/2025 | Approved | MATTHEW NELSON |
| PLUMBING-Rough | 4/9/2025 | Approved | MATTHEW NELSON |
| Shower Pan | 4/9/2025 | Approved | MATTHEW NELSON |
| Insulation | 4/11/2025 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 4/11/2025 | Approved | MATTHEW NELSON |
| Shower Pan | 4/11/2025 | Approved | MATTHEW NELSON |
| Drywall Nailing | 4/24/2025 | Approved | NICHOLAS TROWBRIDGE |
| Final | 7/17/2025 | Corrections Issued | MATTHEW NELSON |
| Green Building Final | 7/17/2025 | Corrections Issued | MATTHEW NELSON |
| MERV13>=Final | 7/17/2025 | Approved | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 7/17/2025 | SGSOV Approved | MATTHEW NELSON |
| Smoke Detectors | 7/17/2025 | Approved | MATTHEW NELSON |
| Final | 8/5/2025 | Corrections Issued | MATTHEW NELSON |
| Green Building Final | 8/5/2025 | Corrections Issued | MATTHEW NELSON |
| Final | 8/29/2025 | OK to Issue CofO | MATTHEW NELSON |
| Green Building Final | 8/29/2025 | Approved | MATTHEW NELSON |
| Service/Power Release | 8/29/2025 | Approved | MATTHEW NELSON |