7514 N FORBES AVE 91406

Certificate Information: 7514 N FORBES AVE 91406

Application / Permit
24014-20000-01480
Plan Check / Job No.
B24VN04820
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Addition and convert (E) detached garage to ADU PER LAMC 12.22 A.33 (c)-(d)
Permit Issued
Issued on 10/3/2024
Issuing Office
Current Status
CofO Issued on 9/23/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/23/2024 APPLICANT
Assigned to Plan Check Engineer 4/26/2024 NGHI SU
Corrections Issued 4/27/2024 NGHI SU
Plan Check Approved 10/2/2024 SHANGQIN XIE
Issued 10/3/2024 APPLICANT
CofO in Progress 9/19/2025 GAREN HAYRAPETYAN
CofO Issued 9/23/2025 RUBEN SALAS
Permit Finaled 9/23/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 5/11/2024 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 5/11/2024 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 5/13/2024 CARLOS AGUILERA
Sewer availability Cleared 5/14/2024 CARLOS AGUILERA
Construction near power lines Cleared 9/24/2024 RIDWAN HARDY
Construction within easement Cleared 9/24/2024 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Yeghiayan,, Armond; Lic. No.: C69935 16873 MCKEEVER ST      GRANADA HILLS, CA 91344

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM WREN, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 11/13/2024 Approved GAREN HAYRAPETYAN
Footing/Foundation/Slab 11/30/2024 Not Ready for Inspection RYAN SALAZAR
PLUMBING-Rough 11/30/2024 Partial Approval RYAN SALAZAR
Footing/Foundation/Slab 12/11/2024 Corrections Issued SALVADOR MARTINEZ
Excavation/Setback/Form/Re-Bar 12/18/2024 Approved RAUL OLAGI
Footing/Foundation/Slab 12/18/2024 Approved RAUL OLAGI
Footing/Foundation/Slab 12/20/2024 Partial Inspection SALVADOR MARTINEZ
Floor/Roof Diaphrgm/Shear Wall 3/3/2025 Corrections Issued SALVADOR MARTINEZ
Floor/Roof Diaphrgm/Shear Wall 3/13/2025 Corrections Issued SALVADOR MARTINEZ
Floor/Roof Diaphrgm/Shear Wall 4/7/2025 Approved OGANES TARAKHCHYAN
Special/Order Compliance 4/7/2025 Corrections Issued OGANES TARAKHCHYAN
Underground Mechanical 4/7/2025 Approved OGANES TARAKHCHYAN
Interior/Exterior Lathing 5/5/2025 Corrections Issued WILLIAM WREN
BUILDING-Rough-Frame 5/8/2025 Not Ready for Inspection SALVADOR MARTINEZ
ELECTRICAL-Rough 5/8/2025 Not Ready for Inspection SALVADOR MARTINEZ
Green Building Rough 5/8/2025 Not Ready for Inspection SALVADOR MARTINEZ
HVAC-Rough 5/8/2025 Corrections Issued SALVADOR MARTINEZ
Interior/Exterior Lathing 5/8/2025 Not Ready for Inspection SALVADOR MARTINEZ
BUILDING-Rough-Frame 5/19/2025 Approved KEVIN BERBERYAN
ELECTRICAL-Rough 5/19/2025 Approved KEVIN BERBERYAN
Green Building Rough 5/19/2025 Approved KEVIN BERBERYAN
HVAC-Rough 5/19/2025 Approved KEVIN BERBERYAN
Interior/Exterior Lathing 5/19/2025 Approved KEVIN BERBERYAN
Insulation 5/27/2025 Approved GAREN HAYRAPETYAN
Interior/Exterior Lathing 6/3/2025 Not Ready for Inspection OGANES TARAKHCHYAN
Drywall Nailing 6/10/2025 Approved JACK KARGODORIAN
Interior/Exterior Lathing 6/16/2025 Approved SALVADOR MARTINEZ
Shower Pan 6/17/2025 Approved MICHAEL CORTEZ
Final 9/2/2025 Corrections Issued GAREN HAYRAPETYAN
Footing/Foundation/Slab 9/2/2025 Approved GAREN HAYRAPETYAN
Green Building Final 9/2/2025 Approved GAREN HAYRAPETYAN
SGSOV-Seismic Gas S/O Valve 9/2/2025 SGSOV Approved GAREN HAYRAPETYAN
Smoke Detectors 9/2/2025 Approved GAREN HAYRAPETYAN
Final 9/18/2025 OK to Issue CofO GAREN HAYRAPETYAN