20445 W STRATHERN ST 91306

Certificate Information: 20445 W STRATHERN ST 91306

Application / Permit
24014-20000-01459
Plan Check / Job No.
B24VN04748
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN: 489 IRREGULAR SHAPED ADDITION TO (E) SINGLE FAMILY RESIDENCE. WORK PER ENGINEERED DESIGN.
Permit Issued
Issued on 5/29/2024
Issuing Office
Current Status
CofO Issued on 1/28/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/9/2024 APPLICANT
Assigned to Plan Check Engineer 4/12/2024 OMAR GARNICA
Corrections Issued 4/13/2024 OMAR GARNICA
Plan Check Approved 5/22/2024 OMAR GARNICA
Issued 5/29/2024 APPLICANT
CofO in Progress 10/29/2024 ALEXANDER HANDY
Permit Finaled 1/28/2025 JOHN JANSON
CofO Issued 1/28/2025 JOHN JANSON

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 5/15/2024 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 5/20/2024 CARLOS AGUILERA
Sewer availability Cleared 5/20/2024 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Li,, Dacheng D; Lic. No.: NA58075       ,

Inspector Information

DAVID FASTIGGI, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI
ALEXANDER HANDY, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 6/20/2024 Conditional Approval ALEXANDER HANDY
Excavation/Setback/Form/Re-Bar 6/25/2024 Approved ALEXANDER HANDY
BUILDING-Rough-Frame 7/3/2024 Partial Approval ALEXANDER HANDY
Insulation 7/3/2024 Partial Approval ALEXANDER HANDY
Deputy Wood Construction 7/25/2024 Conditional Approval ALEXANDER HANDY
Floor/Roof Diaphrgm/Shear Wall 7/29/2024 Approved ALEXANDER HANDY
BUILDING-Rough-Frame 8/12/2024 Approved ALEXANDER HANDY
Green Building Rough 8/12/2024 Approved ALEXANDER HANDY
Interior/Exterior Lathing 8/12/2024 Partial Approval ALEXANDER HANDY
Rough-Elec/Plmb/HVAC 8/12/2024 Approved ALEXANDER HANDY
Insulation 8/15/2024 Approved ALEXANDER HANDY
Interior/Exterior Lathing 8/15/2024 Approved ALEXANDER HANDY
Shower Pan 8/15/2024 Approved ALEXANDER HANDY
Drywall Nailing 8/19/2024 Approved ALEXANDER HANDY
Final 10/23/2024 Corrections Issued ALEXANDER HANDY
Footing/Foundation/Slab 10/23/2024 Approved ALEXANDER HANDY
Green Building Final 10/23/2024 Not Ready for Inspection ALEXANDER HANDY
SGSOV-Seismic Gas S/O Valve 10/23/2024 SGSOV Approved ALEXANDER HANDY
Smoke Detectors 10/23/2024 Approved ALEXANDER HANDY
ELECTRICAL-Final 10/28/2024 Approved ALEXANDER HANDY
Final 10/28/2024 OK to Issue CofO ALEXANDER HANDY
Green Building Final 10/28/2024 Approved ALEXANDER HANDY
HVAC-Final 10/28/2024 Approved ALEXANDER HANDY
PLUMBING-Final 10/28/2024 Approved ALEXANDER HANDY