22125-22127 W LANARK ST 91304

Certificate Information: 22125-22127 W LANARK ST 91304

Application / Permit
24014-20000-01453
Plan Check / Job No.
B24VN04728
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan. Addition and conversion of portion of SFD w./ att. garage to ADU per LAMC 12.22.A.33(c) AND (e) and remodel the house
Permit Issued
Issued on 1/13/2025
Issuing Office
Current Status
Issued on 1/13/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 4/27/2024 APPLICANT
Assigned to Plan Check Engineer 5/1/2024 MADISON ODELL
Corrections Issued 5/1/2024 MADISON ODELL
Applicant returned to address corrections 8/31/2024 MADISON ODELL
Applicant returned to address corrections 10/30/2024 MADISON ODELL
Applicant returned to address corrections 12/3/2024 REZA HAGHIGHAT
Plan Check Approved 12/6/2024 REZA HAGHIGHAT
Issued 1/13/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 8/27/2024 RYAN CASTRO
Roof/Waste drainage to street Cleared 8/27/2024 RYAN CASTRO
Construction near power lines Cleared 9/10/2024 RIDWAN HARDY
Construction within easement Cleared 9/10/2024 RIDWAN HARDY
Eng Process Fee Ord 176,300 Cleared 10/18/2024 RYAN CASTRO
Sewer availability Cleared 10/18/2024 RYAN CASTRO
ZA Case Cleared 10/29/2024 JASON CHAN

Contact Information

Contractor Owner-Builder       ,
Engineer Luisoni,, Antonio Stefano; Lic. No.: S1781 12757 DEON PLACE      GRANADA HILLS, CA 91344

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 4/10/2025 Partial Approval JEFFREY HARTLINE
ELECTRICAL-Rough 4/10/2025 Partial Approval JEFFREY HARTLINE
PLUMBING-Rough 4/10/2025 Partial Approval JEFFREY HARTLINE
Pre-Inspection 4/10/2025 Partial Approval JEFFREY HARTLINE
Drywall Nailing 4/15/2025 Partial Approval JEFFREY HARTLINE
Interior/Exterior Lathing 4/15/2025 Partial Approval JEFFREY HARTLINE
BUILDING-Rough-Frame 4/29/2025 Not Ready for Inspection CHRIS CHRISTENSEN
Final 4/29/2025 Not Ready for Inspection CHRIS CHRISTENSEN
Footing/Foundation/Slab 4/29/2025 Not Ready for Inspection CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 4/29/2025 SGSOV Not Ready CHRIS CHRISTENSEN
Smoke Detectors 4/29/2025 Not Ready for Inspection CHRIS CHRISTENSEN
Deputy Drilled-In Anchors 5/9/2025 Conditional Approval CHRIS CHRISTENSEN
Excavation/Setback/Form/Re-Bar 5/12/2025 Approved JEFFREY HARTLINE
Footing/Foundation/Slab 5/12/2025 Approved JEFFREY HARTLINE
BUILDING-Rough-Frame 5/19/2025 Not Ready for Inspection JEFFREY HARTLINE
BUILDING-Rough-Frame 5/22/2025 Partial Approval CHRIS CHRISTENSEN
Sewer 5/22/2025 Approved CHRIS CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 5/27/2025 Partial Approval JEFFREY HARTLINE
Insulation 5/27/2025 Partial Approval JEFFREY HARTLINE
Wood Frame 6/17/2025 Not Ready for Inspection JEFFREY HARTLINE
Rough-Elec/Plmb/HVAC 7/8/2025 Approved CHRIS CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 7/10/2025 Partial Approval TROY SANDERS
Rough-Elec/Plmb/HVAC 7/10/2025 Approved TROY SANDERS
BUILDING-Rough-Frame 7/17/2025 Approved CHRIS CHRISTENSEN
Green Building Rough 7/17/2025 Approved CHRIS CHRISTENSEN
Insulation 7/17/2025 Approved CHRIS CHRISTENSEN
Interior/Exterior Lathing 7/17/2025 Partial Approval CHRIS CHRISTENSEN
Drywall Nailing 8/4/2025 Approved GEVORK IPCHYAN
Interior/Exterior Lathing 8/4/2025 Partial Approval GEVORK IPCHYAN
Shower Pan 8/4/2025 Approved GEVORK IPCHYAN
ELECTRICAL-Final 10/8/2025 Not Ready for Inspection CHRIS CHRISTENSEN
ELECTRICAL-Rough 10/8/2025 Not Ready for Inspection CHRIS CHRISTENSEN
Service/Power Release 3/3/2026 Corrections Issued CHRIS CHRISTENSEN
ELECTRICAL-Final 3/26/2026 Corrections Issued CHRIS CHRISTENSEN