12739 N ADELPHIA AVE 91340
Certificate Information: 12739 N ADELPHIA AVE 91340
- Application / Permit
- 24014-20000-01452
- Plan Check / Job No.
- B24VN04722
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DETACHED GARAGE AND STORAGE AND (N) ADDITION TO (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d). "COMPLY WITH DEPARTMENT ORDER effective date 10/16/2023. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
- Permit Issued
- Issued on 3/25/2025
- Issuing Office
- Current Status
- CofO Issued on 5/19/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/13/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 4/17/2024 | ISIS ARGUETA |
| Corrections Issued | 4/18/2024 | ISIS ARGUETA |
| Applicant returned to address corrections | 10/10/2024 | KAMYAR EMAMI |
| Applicant returned to address corrections | 12/26/2024 | ALEC MOUSAKHANIAN |
| Plan Check Approved | 3/5/2025 | ALEC MOUSAKHANIAN |
| Issued | 3/25/2025 | APPLICANT |
| Permit Finaled | 5/19/2026 | DAVID JAMES |
| CofO Issued | 5/19/2026 | DAVID JAMES |
| Permit Finaled | 5/19/2026 | DAVID JAMES |
Permit Application Clearance Information
| Address approval | Cleared | 8/20/2024 | BIAINA HARITUNIAN |
| Roof/Waste drainage to street | Cleared | 8/20/2024 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 8/22/2024 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 8/22/2024 | BIAINA HARITUNIAN |
| Hold | Cleared | 4/29/2025 | MARIA VENDIVIL |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| ARA SINANIAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| HASANTHA WEERASEKARA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| SCOTT SHUSTER, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOEL GUARDADO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARIYA MIHALEVA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOSE RUBIO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| DAVID JAMES, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| DAVID HICKMAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN HAMILTON, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN STEPHENS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| PIERRE VEGA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARK VAN SLOOTEN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MICKEY YAMASHITA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| RICHARD ROBLES, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| HAGOP BADOSSIAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| KIM BEAUCHAMP, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARK DOVICO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| THOMAS WOODS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAUL VASQUEZ, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| AUGUSTUS ALBAS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| FELIPE PENICHE, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| LEO MILBAUER, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 6/2/2025 | Approved | RAUL VASQUEZ |
| Footing/Foundation/Slab | 6/2/2025 | Approved | RAUL VASQUEZ |
| Pre-Inspection | 6/2/2025 | Approved | RAUL VASQUEZ |
| Underground Mechanical | 6/2/2025 | Approved | RAUL VASQUEZ |
| BUILDING-Rough-Frame | 7/10/2025 | Not Ready for Inspection | RAUL VASQUEZ |
| Green Building Rough | 7/10/2025 | Not Ready for Inspection | RAUL VASQUEZ |
| MERV13>=Rough | 7/10/2025 | Not Ready for Inspection | RAUL VASQUEZ |
| BUILDING-Rough-Frame | 7/30/2025 | Corrections Issued | RAUL VASQUEZ |
| ELECTRICAL-Rough | 7/30/2025 | Approved | RAUL VASQUEZ |
| Green Building Rough | 7/30/2025 | Approved | RAUL VASQUEZ |
| MERV13>=Rough | 7/30/2025 | Not Ready for Inspection | RAUL VASQUEZ |
| BUILDING-Rough-Frame | 8/6/2025 | Not Ready for Inspection | RAUL VASQUEZ |
| HVAC-Rough | 8/6/2025 | Corrections Issued | RAUL VASQUEZ |
| MERV13>=Rough | 8/6/2025 | Approved | RAUL VASQUEZ |
| Interior/Exterior Lathing | 9/9/2025 | Approved | RAUL VASQUEZ |
| PLUMBING-Rough | 9/9/2025 | Approved | RAUL VASQUEZ |
| Insulation | 9/12/2025 | Approved | RAUL VASQUEZ |
| Drywall Nailing | 9/24/2025 | Approved | RAUL VASQUEZ |
| Interior/Exterior Lathing | 11/12/2025 | Approved | RAUL VASQUEZ |
| Shower Pan | 11/12/2025 | Approved | RAUL VASQUEZ |
| BUILDING-Rough-Frame | 1/13/2026 | Approved | RAUL VASQUEZ |
| Final | 1/13/2026 | Corrections Issued | RAUL VASQUEZ |
| Green Building Final | 1/13/2026 | Approved | RAUL VASQUEZ |
| MERV13>=Final | 1/13/2026 | Not Ready for Inspection | RAUL VASQUEZ |
| SGSOV-Seismic Gas S/O Valve | 1/13/2026 | SGSOV Not Ready | RAUL VASQUEZ |
| Smoke Detectors | 1/13/2026 | Approved | RAUL VASQUEZ |
| Final | 2/18/2026 | Not Ready for Inspection | RAUL VASQUEZ |
| MERV13>=Final | 2/18/2026 | Not Ready for Inspection | RAUL VASQUEZ |
| SGSOV-Seismic Gas S/O Valve | 2/18/2026 | SGSOV Approved | RAUL VASQUEZ |
| Final | 2/23/2026 | Conditional Approval | RAUL VASQUEZ |
| MERV13>=Final | 2/23/2026 | Approved | RAUL VASQUEZ |
| SGSOV-Seismic Gas S/O Valve | 2/23/2026 | SGSOV Approved | RAUL VASQUEZ |