12739 N ADELPHIA AVE 91340

Certificate Information: 12739 N ADELPHIA AVE 91340

Application / Permit
24014-20000-01452
Plan Check / Job No.
B24VN04722
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) DETACHED GARAGE AND STORAGE AND (N) ADDITION TO (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d). "COMPLY WITH DEPARTMENT ORDER effective date 10/16/2023. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
Permit Issued
Issued on 3/25/2025
Issuing Office
Current Status
CofO Issued on 5/19/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/13/2024 APPLICANT
Assigned to Plan Check Engineer 4/17/2024 ISIS ARGUETA
Corrections Issued 4/18/2024 ISIS ARGUETA
Applicant returned to address corrections 10/10/2024 KAMYAR EMAMI
Applicant returned to address corrections 12/26/2024 ALEC MOUSAKHANIAN
Plan Check Approved 3/5/2025 ALEC MOUSAKHANIAN
Issued 3/25/2025 APPLICANT
Permit Finaled 5/19/2026 DAVID JAMES
CofO Issued 5/19/2026 DAVID JAMES
Permit Finaled 5/19/2026 DAVID JAMES

Permit Application Clearance Information

Address approval Cleared 8/20/2024 BIAINA HARITUNIAN
Roof/Waste drainage to street Cleared 8/20/2024 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 8/22/2024 BIAINA HARITUNIAN
Sewer availability Cleared 8/22/2024 BIAINA HARITUNIAN
Hold Cleared 4/29/2025 MARIA VENDIVIL

Contact Information

Contractor Owner-Builder       ,

Inspector Information

ARA SINANIAN, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
HASANTHA WEERASEKARA, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
SCOTT SHUSTER, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
JOEL GUARDADO, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MARIYA MIHALEVA, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
JOSE RUBIO, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
DAVID JAMES, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
DAVID HICKMAN, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
JOHN HAMILTON, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
JOHN STEPHENS, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
PIERRE VEGA, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MARK VAN SLOOTEN, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MICKEY YAMASHITA, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
RICHARD ROBLES, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
HAGOP BADOSSIAN, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
KIM BEAUCHAMP, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MARK DOVICO, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
THOMAS WOODS, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
RAUL VASQUEZ, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
AUGUSTUS ALBAS, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
FELIPE PENICHE, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
LEO MILBAUER, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 6/2/2025 Approved RAUL VASQUEZ
Footing/Foundation/Slab 6/2/2025 Approved RAUL VASQUEZ
Pre-Inspection 6/2/2025 Approved RAUL VASQUEZ
Underground Mechanical 6/2/2025 Approved RAUL VASQUEZ
BUILDING-Rough-Frame 7/10/2025 Not Ready for Inspection RAUL VASQUEZ
Green Building Rough 7/10/2025 Not Ready for Inspection RAUL VASQUEZ
MERV13>=Rough 7/10/2025 Not Ready for Inspection RAUL VASQUEZ
BUILDING-Rough-Frame 7/30/2025 Corrections Issued RAUL VASQUEZ
ELECTRICAL-Rough 7/30/2025 Approved RAUL VASQUEZ
Green Building Rough 7/30/2025 Approved RAUL VASQUEZ
MERV13>=Rough 7/30/2025 Not Ready for Inspection RAUL VASQUEZ
BUILDING-Rough-Frame 8/6/2025 Not Ready for Inspection RAUL VASQUEZ
HVAC-Rough 8/6/2025 Corrections Issued RAUL VASQUEZ
MERV13>=Rough 8/6/2025 Approved RAUL VASQUEZ
Interior/Exterior Lathing 9/9/2025 Approved RAUL VASQUEZ
PLUMBING-Rough 9/9/2025 Approved RAUL VASQUEZ
Insulation 9/12/2025 Approved RAUL VASQUEZ
Drywall Nailing 9/24/2025 Approved RAUL VASQUEZ
Interior/Exterior Lathing 11/12/2025 Approved RAUL VASQUEZ
Shower Pan 11/12/2025 Approved RAUL VASQUEZ
BUILDING-Rough-Frame 1/13/2026 Approved RAUL VASQUEZ
Final 1/13/2026 Corrections Issued RAUL VASQUEZ
Green Building Final 1/13/2026 Approved RAUL VASQUEZ
MERV13>=Final 1/13/2026 Not Ready for Inspection RAUL VASQUEZ
SGSOV-Seismic Gas S/O Valve 1/13/2026 SGSOV Not Ready RAUL VASQUEZ
Smoke Detectors 1/13/2026 Approved RAUL VASQUEZ
Final 2/18/2026 Not Ready for Inspection RAUL VASQUEZ
MERV13>=Final 2/18/2026 Not Ready for Inspection RAUL VASQUEZ
SGSOV-Seismic Gas S/O Valve 2/18/2026 SGSOV Approved RAUL VASQUEZ
Final 2/23/2026 Conditional Approval RAUL VASQUEZ
MERV13>=Final 2/23/2026 Approved RAUL VASQUEZ
SGSOV-Seismic Gas S/O Valve 2/23/2026 SGSOV Approved RAUL VASQUEZ