PROPOSED ADDITION TO THE (E) SINGLE FAMILY DWELLING AT REAR.
Permit Issued
Issued on 4/30/2025
Issuing Office
Current Status
Issued on 4/30/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 4/9/2024 APPLICANT
Assigned to Plan Check Engineer 4/12/2024 KAMYAR EMAMI
Corrections Issued 4/15/2024 KAMYAR EMAMI
Applicant returned to address corrections 3/6/2025 SARKIS HARABEDIAN
Plan Check Approved 4/1/2025 GIOVANNY CHAVEZ
Issued 4/30/2025 APPLICANT

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 11/22/2024 CARLOS AGUILERA
BHO/Hillside ordinance Cleared 11/22/2024 CARLOS AGUILERA
BHO/Hillside ordinance Cleared 11/22/2024 CARLOS AGUILERA
BHO/Hillside ordinance Cleared 11/22/2024 CARLOS AGUILERA
BHO/Hillside ordinance Cleared 11/22/2024 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 11/22/2024 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 11/22/2024 CARLOS AGUILERA
Sewer availability Cleared 11/22/2024 CARLOS AGUILERA
GPI Written Notices Cleared 3/8/2025 KAMYAR EMAMI
Grading Pre-Inspection Cleared 3/8/2025 KAMYAR EMAMI
Hydrant and Access approval Cleared 3/27/2025 PATRICK PEREZ

Contact Information

Contractor Owner-Builder       ,
Engineer Li,, Dacheng D; Lic. No.: C58075 1400 N KRAEMER BLVD #712      PLACENTIA, CA 92781

Inspector Information

DAVID ANDERSON, (818) 374-1168 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 8/29/2025 Not Ready for Inspection DAVID MATSON
PLUMBING-Rough 8/29/2025 Not Ready for Inspection DAVID MATSON
Deputy Drilled-In Anchors 5/22/2026 Conditional Approval DAVID MATSON
Footing/Foundation/Slab 5/26/2026 Approved DAVID ANDERSON
Floor/Roof Diaphrgm/Shear Wall 6/2/2026 Partial Approval DAVID ANDERSON
PLUMBING-Rough 6/2/2026 Partial Approval DAVID ANDERSON
Floor/Roof Diaphrgm/Shear Wall 6/4/2026 Partial Approval DAVID ANDERSON