4031 N CARTWRIGHT AVE 91604
Certificate Information: 4031 N CARTWRIGHT AVE 91604
- Application / Permit
- 24014-20000-01434
- Plan Check / Job No.
- B24VN04674
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION TO EX. SFD EXPAND LIVING ROOM AND NEW FRONT PORCH. REMODEL TO CREATE NEW BEDROOM, RELOCATE KITCHEN. REFRAME PORTION OF ROOF PER PLANS.
- Permit Issued
- Issued on 4/4/2025
- Issuing Office
- Current Status
- CofO in Progress on 4/10/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 4/10/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 4/12/2024 | ROSENDO MEDINA |
| Corrections Issued | 4/13/2024 | ROSENDO MEDINA |
| Plan Check Approved | 6/10/2024 | ROSENDO MEDINA |
| Issued | 4/4/2025 | APPLICANT |
| CofO in Progress | 4/10/2026 | JAVIER RAMOS JR |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 5/1/2024 | MARKOS PEREZ-BRAN |
| Eng Process Fee Ord 176,300 | Cleared | 5/6/2024 | MARKOS PEREZ-BRAN |
Contact Information
| Contractor | Build Method Construction Inc; Lic. No.: 1059684-B | , |
| Engineer | Tuchscher,, James; Lic. No.: C77649 | 5318 E 2ND ST., #539 LONG BEACH, CA 90803 |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/10/2025 | Partial Approval | JAVIER RAMOS JR |
| Footing/Foundation/Slab | 6/16/2025 | Partial Approval | JAVIER RAMOS JR |
| Deputy Wood Construction | 6/20/2025 | Conditional Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 6/30/2025 | Partial Approval | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 7/21/2025 | Corrections Issued | JAVIER RAMOS JR |
| PLUMBING-Rough | 8/14/2025 | Approved | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 9/2/2025 | Partial Approval | JAVIER RAMOS JR |
| HVAC-Rough | 9/2/2025 | Approved | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 9/10/2025 | Approved | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 9/11/2025 | Corrections Issued | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 9/11/2025 | Corrections Issued | JAVIER RAMOS JR |
| Green Building Rough | 9/11/2025 | Approved | JAVIER RAMOS JR |
| MERV13>=Rough | 9/11/2025 | Approved | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 9/26/2025 | Corrections Issued | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 9/26/2025 | Approved | JAVIER RAMOS JR |
| Footing/Foundation/Slab | 9/26/2025 | Approved | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 9/26/2025 | Approved | JAVIER RAMOS JR |
| Shower Pan | 9/26/2025 | Approved | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 10/14/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Insulation | 10/14/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Interior/Exterior Lathing | 10/14/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Drywall Nailing | 11/14/2025 | Approved | JAVIER RAMOS JR |
| ELECTRICAL-Final | 4/1/2026 | Approved | JAVIER RAMOS JR |
| Final | 4/1/2026 | Corrections Issued | JAVIER RAMOS JR |
| Green Building Final | 4/1/2026 | Approved | JAVIER RAMOS JR |
| HVAC-Final | 4/1/2026 | Approved | JAVIER RAMOS JR |
| MERV13>=Final | 4/1/2026 | Approved | JAVIER RAMOS JR |
| PLUMBING-Final | 4/1/2026 | Corrections Issued | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 4/1/2026 | SGSOV Approved | JAVIER RAMOS JR |
| Service/Power Release | 4/1/2026 | Approved | JAVIER RAMOS JR |
| Smoke Detectors | 4/1/2026 | Approved | JAVIER RAMOS JR |
| Final | 4/10/2026 | OK to Issue CofO | JAVIER RAMOS JR |
| PLUMBING-Final | 4/10/2026 | Approved | JAVIER RAMOS JR |