8000 N NAGLE AVE 91605
Certificate Information: 8000 N NAGLE AVE 91605
- Application / Permit
- 24014-20000-01428
- Plan Check / Job No.
- B24VN04654
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED MAJOR INTERIOR REMODEL WITH 23'5"X12'4" ADDITION AT REAR TO EXPAND EXISTING BEDROOMS WITH NEW BATHROOM. REFRAME EXISTING FRONT PORCH PER PLAN.
- Permit Issued
- Issued on 5/31/2024
- Issuing Office
- Current Status
- CofO Issued on 4/15/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/8/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 4/15/2024 | HAYATO TSUCHIYA |
| Corrections Issued | 4/15/2024 | HAYATO TSUCHIYA |
| Building Plans Picked Up | 4/16/2024 | APPLICANT |
| Plan Check Approved | 5/31/2024 | ALEC MOUSAKHANIAN |
| Issued | 5/31/2024 | APPLICANT |
| CofO in Progress | 4/7/2025 | VINCENT HANLEY |
| Permit Finaled | 4/15/2025 | RUBEN SALAS |
| CofO Issued | 4/15/2025 | RUBEN SALAS |
| Permit Finaled | 4/15/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 4/17/2024 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 5/20/2024 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Khatchadourian,, Vicken; Lic. No.: S3141 | 1221 N CEDAR ST GLENDALE, CA 92107 |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/10/2024 | Approved | VINCENT HANLEY |
| Deputy Drilled-In Anchors | 6/11/2024 | Conditional Approval | DAVID MATSON |
| PLUMBING-Rough | 7/1/2024 | Partial Approval | GREGG CUMMINGS |
| Floor/Roof Diaphrgm/Shear Wall | 7/3/2024 | Partial Approval | GREGG CUMMINGS |
| Excavation/Setback/Form/Re-Bar | 8/26/2024 | Corrections Issued | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 9/9/2024 | Partial Approval | VINCENT HANLEY |
| Deputy Drilled-In Anchors | 9/9/2024 | Approved | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 9/23/2024 | Partial Approval | GREGG CUMMINGS |
| PLUMBING-Rough | 9/23/2024 | Approved | GREGG CUMMINGS |
| ELECTRICAL-Rough | 10/7/2024 | Approved | DAVID MATSON |
| HVAC-Rough | 10/7/2024 | Conditional Approval | DAVID MATSON |
| ELECTRICAL-Rough | 10/24/2024 | Approved | GREGG CUMMINGS |
| Floor/Roof Diaphrgm/Shear Wall | 10/24/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 10/25/2024 | Corrections Issued | GREGG CUMMINGS |
| Green Building Rough | 10/25/2024 | Approved | GREGG CUMMINGS |
| Shower Pan | 11/1/2024 | Approved | GREGG CUMMINGS |
| HVAC-Rough | 11/5/2024 | Approved | GREGG CUMMINGS |
| Interior/Exterior Lathing | 11/5/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 11/12/2024 | Approved | GREGG CUMMINGS |
| Interior/Exterior Lathing | 11/12/2024 | Partial Approval | GREGG CUMMINGS |
| Insulation | 11/18/2024 | Approved | GREGG CUMMINGS |
| Drywall Nailing | 11/25/2024 | Approved | GREGG CUMMINGS |
| Interior/Exterior Lathing | 12/2/2024 | Partial Approval | GREGG CUMMINGS |
| ELECTRICAL-Final | 4/7/2025 | Approved | VINCENT HANLEY |
| Final | 4/7/2025 | OK to Issue CofO | VINCENT HANLEY |
| Green Building Final | 4/7/2025 | Approved | VINCENT HANLEY |
| HVAC-Final | 4/7/2025 | Approved | VINCENT HANLEY |
| PLUMBING-Final | 4/7/2025 | Approved | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 4/7/2025 | SGSOV Approved | VINCENT HANLEY |
| Smoke Detectors | 4/7/2025 | Approved | VINCENT HANLEY |