22412 W BESSEMER ST 91367
Certificate Information: 22412 W BESSEMER ST 91367
- Application / Permit
- 24014-20000-01419
- Plan Check / Job No.
- B24VN04621
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMODEL, (N) 7'-11" X 7'-11" ADDITON ON FIRST FLOOR AND (N) 32'-5" X 20'-8" SECOND STORY ADDITION TO (E) SINGLE FAMILY DWELLING ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 10/30/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 6/27/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/8/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 4/11/2024 | SEWADA ZADOORIAN MILAGARDI |
| Corrections Issued | 4/17/2024 | SEWADA ZADOORIAN MILAGARDI |
| Quality Review Completed | 4/19/2024 | STEVEN KIM |
| Building Plans Picked Up | 5/30/2024 | APPLICANT |
| Plan Check Approved | 9/6/2024 | SEWADA ZADOORAN MILAGARDI |
| Issued | 10/30/2024 | APPLICANT |
| CofO in Progress | 6/25/2025 | TROY SANDERS |
| Permit Finaled | 6/27/2025 | JOHN JANSON |
| CofO Issued | 6/27/2025 | JOHN JANSON |
| Permit Finaled | 6/27/2025 | JOHN JANSON |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 6/4/2024 | BIAINA HARITUNIAN |
| Roof/Waste drainage to street | Cleared | 6/4/2024 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 6/4/2024 | BIAINA HARITUNIAN |
| Miscellaneous | Cleared | 6/13/2024 | NATHAN ROMINE |
| GPI Written Notices | Cleared | 9/6/2024 | SEWADA ZADOORAN MILAGARDI |
| Grading Pre-Inspection | Cleared | 9/6/2024 | SEWADA ZADOORAN MILAGARDI |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Castillo,, Margarito; Lic. No.: S4808 | 1205 PINE AVE SUITE 201 LONG BEACH, CA 90813 |
Inspector Information
| GEVORK IPCHYAN, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
| TROY SANDERS, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 11/21/2024 | Not Ready for Inspection | GEVORK IPCHYAN |
| Footing/Foundation/Slab | 11/26/2024 | Approved | GEVORK IPCHYAN |
| Underground Mechanical | 11/26/2024 | Approved | GEVORK IPCHYAN |
| Deputy Reinf. Concrete | 12/2/2024 | Conditional Approval | TROY SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 12/31/2024 | Partial Approval | TROY SANDERS |
| Green Building Rough | 12/31/2024 | Not Ready for Inspection | TROY SANDERS |
| BUILDING-Rough-Frame | 1/15/2025 | Not Ready for Inspection | GEVORK IPCHYAN |
| Green Building Rough | 1/15/2025 | Not Ready for Inspection | GEVORK IPCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/27/2025 | Corrections Issued | GEVORK IPCHYAN |
| Green Building Rough | 1/27/2025 | Not Ready for Inspection | GEVORK IPCHYAN |
| ELECTRICAL-Rough | 2/14/2025 | Approved | TROY SANDERS |
| BUILDING-Rough-Frame | 2/24/2025 | Partial Approval | GEVORK IPCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/24/2025 | Partial Approval | GEVORK IPCHYAN |
| HVAC-Rough | 2/24/2025 | Approved | GEVORK IPCHYAN |
| PLUMBING-Rough | 2/24/2025 | Approved | GEVORK IPCHYAN |
| Interior/Exterior Lathing | 3/5/2025 | Partial Approval | GEVORK IPCHYAN |
| BUILDING-Rough-Frame | 4/1/2025 | Approved | GEVORK IPCHYAN |
| Green Building Rough | 4/1/2025 | Approved | GEVORK IPCHYAN |
| Insulation | 4/1/2025 | Approved | GEVORK IPCHYAN |
| Interior/Exterior Lathing | 4/1/2025 | Partial Approval | GEVORK IPCHYAN |
| Shower Pan | 4/1/2025 | Approved | GEVORK IPCHYAN |
| Drywall Nailing | 4/21/2025 | Approved | GEVORK IPCHYAN |
| ELECTRICAL-Final | 6/13/2025 | Not Ready for Inspection | GEVORK IPCHYAN |
| Final | 6/13/2025 | Not Ready for Inspection | GEVORK IPCHYAN |
| Green Building Final | 6/13/2025 | Not Ready for Inspection | GEVORK IPCHYAN |
| HVAC-Final | 6/13/2025 | Not Ready for Inspection | GEVORK IPCHYAN |
| PLUMBING-Final | 6/13/2025 | Not Ready for Inspection | GEVORK IPCHYAN |
| SGSOV-Seismic Gas S/O Valve | 6/13/2025 | SGSOV Not Ready | GEVORK IPCHYAN |
| Smoke Detectors | 6/13/2025 | Not Ready for Inspection | GEVORK IPCHYAN |
| Final | 6/24/2025 | OK to Issue CofO | TROY SANDERS |
| Green Building Final | 6/24/2025 | Approved | TROY SANDERS |
| SGSOV-Seismic Gas S/O Valve | 6/24/2025 | SGSOV Approved | TROY SANDERS |
| Smoke Detectors | 6/24/2025 | Approved | TROY SANDERS |