7943 N CLYBOURN AVE 91352
Certificate Information: 7943 N CLYBOURN AVE 91352
- Application / Permit
- 24014-20000-01413
- Plan Check / Job No.
- B24VN04193
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADD 15' X 16' REC ROOM AND 29'-1.5" X 34' IRREGUALR SHAPED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c)-(d) TO (E) DETACHED GARAGE. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 6/10/2024
- Issuing Office
- Current Status
- Issued on 6/10/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 4/2/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 4/4/2024 | RAPHAEL ROSAS |
| Corrections Issued | 4/9/2024 | RAPHAEL ROSAS |
| Quality Review Completed | 4/9/2024 | STEVEN KIM |
| Applicant returned to address corrections | 5/21/2024 | RAPHAEL ROSAS |
| Plan Check Approved | 6/6/2024 | RAPHAEL ROSAS |
| Plan Check Approved | 6/10/2024 | RAPHAEL ROSAS |
| Plan Check Approved | 6/10/2024 | RAPHAEL ROSAS |
| Issued | 6/10/2024 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 4/13/2024 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 4/13/2024 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 4/25/2024 | CARLOS AGUILERA |
| Sewer availability | Cleared | 4/25/2024 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MATTHEW NELSON, (818) 374-1170 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/17/2025 | Corrections Issued | MATTHEW NELSON |
| Underground Mechanical | 2/13/2025 | Approved | MATTHEW NELSON |
| Excavation/Setback/Form/Re-Bar | 2/18/2025 | Corrections Issued | MATTHEW NELSON |
| Footing/Foundation/Slab | 2/18/2025 | Corrections Issued | MATTHEW NELSON |
| Floor/Roof Diaphrgm/Shear Wall | 3/14/2025 | Partial Approval | MATTHEW NELSON |
| Floor/Roof Diaphrgm/Shear Wall | 4/3/2025 | Approved | MATTHEW NELSON |
| Footing/Foundation/Slab | 4/3/2025 | Approved | MATTHEW NELSON |
| ELECTRICAL-Rough | 4/10/2025 | Partial Approval | MATTHEW NELSON |
| HVAC-Rough | 4/10/2025 | Partial Approval | MATTHEW NELSON |
| Interior/Exterior Lathing | 4/10/2025 | Partial Approval | MATTHEW NELSON |
| PLUMBING-Rough | 4/10/2025 | Partial Approval | MATTHEW NELSON |
| Insulation | 4/14/2025 | Partial Approval | WILLIAM WREN |
| Drywall Nailing | 4/17/2025 | Approved | DAVID ANDERSON |
| BUILDING-Rough-Frame | 3/3/2026 | Approved | MATTHEW NELSON |
| Final | 3/3/2026 | Partial Approval | MATTHEW NELSON |
| Green Building Final | 3/3/2026 | Approved | MATTHEW NELSON |
| Green Building Rough | 3/3/2026 | Approved | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 3/3/2026 | SGSOV Approved | MATTHEW NELSON |
| Smoke Detectors | 3/3/2026 | Not Ready for Inspection | MATTHEW NELSON |