6911 N JAMIESON AVE 91335

Certificate Information: 6911 N JAMIESON AVE 91335

Application / Permit
24014-20000-01410
Plan Check / Job No.
B24VN04600
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 19'-9" x 25'-0" ADDITION TO AND CONVERT DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d).
Permit Issued
Issued on 7/26/2024
Issuing Office
Current Status
CofO Issued on 9/6/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/7/2024 APPLICANT
Assigned to Plan Check Engineer 4/12/2024 JEROME MAGAT PALMA
Corrections Issued 4/13/2024 JEROME MAGAT PALMA
Building Plans Picked Up 4/17/2024 APPLICANT
Applicant returned to address corrections 7/19/2024 MIROOSH KHACHATOORIAN
Plan Check Approved 7/19/2024 GIOVANNY CHAVEZ
Issued 7/26/2024 APPLICANT
CofO in Progress 6/18/2025 JUAN ALVARADO
Permit Finaled 9/6/2025 MICHAEL PELHAM
CofO Issued 9/6/2025 MICHAEL PELHAM
Permit Finaled 9/6/2025 MICHAEL PELHAM

Permit Application Clearance Information

Address approval Cleared 4/17/2024 BIAINA HARITUNIAN
Roof/Waste drainage to street Cleared 4/17/2024 BIAINA HARITUNIAN
Sewer availability Cleared 4/18/2024 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 7/5/2024 BIAINA HARITUNIAN
Construction within easement Cleared 7/16/2024 WALTER RAMIREZ

Contact Information

Contractor Owner-Builder       ,
Engineer Khatchadourian,, Vicken; Lic. No.: S3141 1221 N CEDAR ST      GLENDALE, CA 92107

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 10/1/2024 Partial Approval JEFFREY BULL
Pre-Inspection 10/1/2024 Approved JEFFREY BULL
Deputy Drilled-In Anchors 10/7/2024 Conditional Approval JEFFREY BULL
Footing/Foundation/Slab 10/7/2024 Approved JEFFREY BULL
Floor/Roof Diaphrgm/Shear Wall 11/13/2024 Approved ARUTYUN MADATYAN
Green Building Rough 11/13/2024 Not Ready for Inspection ARUTYUN MADATYAN
BUILDING-Rough-Frame 1/13/2025 Corrections Issued ARUTYUN MADATYAN
ELECTRICAL-Rough 1/13/2025 Approved ARUTYUN MADATYAN
Green Building Rough 1/13/2025 Approved ARUTYUN MADATYAN
HVAC-Rough 1/13/2025 Approved ARUTYUN MADATYAN
PLUMBING-Rough 1/13/2025 Approved ARUTYUN MADATYAN
BUILDING-Rough-Frame 1/22/2025 Approved ARUTYUN MADATYAN
Insulation 1/22/2025 Approved ARUTYUN MADATYAN
Drywall Nailing 1/28/2025 Approved SCOTT SOBEL
Interior/Exterior Lathing 1/28/2025 Partial Approval SCOTT SOBEL
ELECTRICAL-Rough 2/28/2025 Partial Approval JEFFREY PARD
Sewer 2/28/2025 Approved JEFFREY PARD
Shower Pan 2/28/2025 Approved JEFFREY PARD
Gas Test 3/4/2025 Approved MORRIS JACKSON
Interior/Exterior Lathing 3/4/2025 Approved MORRIS JACKSON
Final 5/27/2025 Corrections Issued JUAN ALVARADO
Green Building Final 5/27/2025 Approved JUAN ALVARADO
SGSOV-Seismic Gas S/O Valve 5/27/2025 SGSOV Approved JUAN ALVARADO
Smoke Detectors 5/27/2025 Approved JUAN ALVARADO
ELECTRICAL-Final 6/12/2025 Not Ready for Inspection JUAN ALVARADO
Final 6/12/2025 Not Ready for Inspection JUAN ALVARADO
PLUMBING-Final 6/12/2025 Approved JUAN ALVARADO
ELECTRICAL-Final 6/17/2025 Approved JUAN ALVARADO
Final 6/17/2025 OK to Issue CofO JUAN ALVARADO
HVAC-Final 6/17/2025 Approved JUAN ALVARADO
Service/Power Release 6/17/2025 Approved JUAN ALVARADO