11013 W KLING ST 91602
Certificate Information: 11013 W KLING ST 91602
- Application / Permit
- 24014-20000-01409
- Plan Check / Job No.
- B24VN04599
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Addition of 513 sf ADU, 48 sf storage, 15 sf pool shower room addition to (E) detached garage per state law
- Permit Issued
- Issued on 1/29/2025
- Issuing Office
- Current Status
- CofO Issued on 12/26/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/8/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 4/10/2024 | KHUONG TRUONG |
| Corrections Issued | 4/10/2024 | KHUONG TRUONG |
| Applicant returned to address corrections | 7/9/2024 | AUNG SOE |
| Plan Check Approved | 11/3/2024 | SHANGQIN XIE |
| Issued | 1/29/2025 | APPLICANT |
| CofO in Progress | 11/13/2025 | JAVIER RAMOS JR |
| Permit Finaled | 12/26/2025 | RUBEN SALAS |
| CofO Issued | 12/26/2025 | RUBEN SALAS |
| Permit Finaled | 12/26/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 7/15/2024 | CARLOS RAMIREZ |
| Roof/Waste drainage to street | Cleared | 7/15/2024 | CARLOS RAMIREZ |
| Sewer availability | Cleared | 7/15/2024 | CARLOS RAMIREZ |
| Eng Process Fee Ord 176,300 | Cleared | 7/17/2024 | CARLOS RAMIREZ |
| Construction near power lines | Cleared | 10/31/2024 | TINA MIRANDA |
Contact Information
| Contractor | D T Development; Lic. No.: 1126267-B | , |
| Engineer | Arutyunyan,, Vladimir; Lic. No.: C92714 | 331 ARDEN AVE SUIT 201 GLENDALE, CA 91203 |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 4/4/2025 | Approved | JAVIER RAMOS JR |
| Excavation/Setback/Form/Re-Bar | 4/4/2025 | Corrections Issued | JAVIER RAMOS JR |
| Footing/Foundation/Slab | 4/4/2025 | Partial Approval | JAVIER RAMOS JR |
| PLUMBING-Rough | 4/4/2025 | Partial Approval | JAVIER RAMOS JR |
| Sewer | 4/4/2025 | Approved | JAVIER RAMOS JR |
| Underground Mechanical | 4/4/2025 | Approved | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 4/21/2025 | Partial Approval | JAVIER RAMOS JR |
| Excavation/Setback/Form/Re-Bar | 4/21/2025 | Approved | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 4/21/2025 | Approved | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 5/13/2025 | Approved | JAVIER RAMOS JR |
| HVAC-Rough | 5/13/2025 | Corrections Issued | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 5/13/2025 | Approved | JAVIER RAMOS JR |
| PLUMBING-Rough | 5/13/2025 | Corrections Issued | JAVIER RAMOS JR |
| Shower Pan | 5/13/2025 | Approved | JAVIER RAMOS JR |
| HVAC-Rough | 5/15/2025 | Approved | JAVIER RAMOS JR |
| PLUMBING-Rough | 5/15/2025 | Approved | JAVIER RAMOS JR |
| Drywall Nailing | 8/28/2025 | Partial Inspection | JAVIER RAMOS JR |
| Insulation | 8/28/2025 | Corrections Issued | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 9/9/2025 | Approved | JAVIER RAMOS JR |
| Drywall Nailing | 9/9/2025 | Partial Approval | JAVIER RAMOS JR |
| ELECTRICAL-Final | 9/9/2025 | Approved | JAVIER RAMOS JR |
| Final | 9/9/2025 | Corrections Issued | JAVIER RAMOS JR |
| Footing/Foundation/Slab | 9/9/2025 | Approved | JAVIER RAMOS JR |
| Green Building Final | 9/9/2025 | Approved | JAVIER RAMOS JR |
| Green Building Rough | 9/9/2025 | Approved | JAVIER RAMOS JR |
| HVAC-Final | 9/9/2025 | Approved | JAVIER RAMOS JR |
| Insulation | 9/9/2025 | Corrections Issued | JAVIER RAMOS JR |
| MERV13>=Final | 9/9/2025 | Approved | JAVIER RAMOS JR |
| MERV13>=Rough | 9/9/2025 | Approved | JAVIER RAMOS JR |
| PLUMBING-Final | 9/9/2025 | Approved | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 9/9/2025 | SGSOV Approved | JAVIER RAMOS JR |
| Smoke Detectors | 9/9/2025 | Approved | JAVIER RAMOS JR |
| Final | 11/12/2025 | OK to Issue CofO | JAVIER RAMOS JR |
| Insulation | 11/12/2025 | Approved | JAVIER RAMOS JR |