705 W MANCHESTER AVE 90044
Certificate Information: 705 W MANCHESTER AVE 90044
- Application / Permit
- 24014-20000-01405
- Plan Check / Job No.
- B24VN04589
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- DEMOLISH ENTIRE EXISTING GARAGE W/ STORAGE RM EXCEPT 4' PORTION OF EXISTING FOOTING & WALL TO REMAIN. AND RECONSTRUCT WITH ADDITION FOR NEW 40'X26' ACCESSORY DWELLING UNIT PER LAMC 12.22a.33(c) & (d). ALL WORK PER WFPP.
- Permit Issued
- Issued on 9/30/2024
- Issuing Office
- Valley
- Current Status
- Issued on 9/30/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 4/5/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 4/12/2024 | HAYATO TSUCHIYA |
| Corrections Issued | 4/13/2024 | HAYATO TSUCHIYA |
| Building Plans Picked Up | 4/18/2024 | APPLICANT |
| Plan Check Approved | 9/27/2024 | PINANK PATEL |
| Issued | 9/30/2024 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 6/25/2024 | JEANIE LAM |
| Roof/Waste drainage to street | Cleared | 6/25/2024 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 6/28/2024 | JEANIE LAM |
| Sewer availability | Cleared | 6/28/2024 | JEANIE LAM |
| Community Plan Implem. Overlay | Cleared | 7/8/2024 | MANERI ROMAN |
| Redevelopment Project Area | Cleared | 7/23/2024 | YASMINE BASHIRI |
| Construction near power lines | Cleared | 8/17/2024 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 10/21/2025 | Approved | JOHN QUINTANILLA |
| Deputy Drilled-In Anchors | 10/27/2025 | Conditional Approval | JOHN QUINTANILLA |
| Excavation/Setback/Form/Re-Bar | 11/5/2025 | Approved | JOHN QUINTANILLA |
| Floor/Roof Diaphrgm/Shear Wall | 1/9/2026 | Approved | JOHN QUINTANILLA |
| ELECTRICAL-Rough | 3/17/2026 | Approved | JOHN QUINTANILLA |
| Floor/Roof Diaphrgm/Shear Wall | 3/17/2026 | Partial Inspection | JOHN QUINTANILLA |
| HVAC-Rough | 3/17/2026 | Approved | JOHN QUINTANILLA |
| PLUMBING-Rough | 3/17/2026 | Corrections Issued | JOHN QUINTANILLA |
| Interior/Exterior Lathing | 3/20/2026 | Approved | JOHN QUINTANILLA |
| PLUMBING-Rough | 3/20/2026 | Approved | JOHN QUINTANILLA |
| Wood Frame | 3/20/2026 | Partial Inspection | JOHN QUINTANILLA |
| BUILDING-Rough-Frame | 3/24/2026 | Corrections Issued | BARRY HACHE |
| Green Building Rough | 3/24/2026 | Approved | BARRY HACHE |
| BUILDING-Rough-Frame | 3/26/2026 | Approved | JOHN QUINTANILLA |
| Insulation | 3/31/2026 | Approved | BARRY HACHE |
| Drywall Nailing | 4/15/2026 | Approved | ALEX COLIN |
| Shower Pan | 4/15/2026 | Approved | ALEX COLIN |
| Interior/Exterior Lathing | 5/29/2026 | Approved | RAUL BARAJAS |