4145 N CAMELLIA AVE 91604

Certificate Information: 4145 N CAMELLIA AVE 91604

Application / Permit
24014-20000-01399
Plan Check / Job No.
B24VN04572
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 554 SQFT ADDITION TO 2ND FLOOR AND NEW ATTACHED COVERED PORCH (58 SQFT) W/NEW ATTACHED 2-CAR GARAGE ( 436 SQFT) TO EXISTING 2-STORY SINGLE FAMILY DWELLING
Permit Issued
Issued on 7/18/2024
Issuing Office
Current Status
CofO Issued on 6/20/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/5/2024 APPLICANT
Assigned to Plan Check Engineer 4/18/2024 PETER MOSESIAN
Corrections Issued 4/27/2024 PETER MOSESIAN
Quality Review Completed 5/3/2024 OMID HEDAYAT
Applicant returned to address corrections 6/11/2024 PETER MOSESIAN
Plan Check Approved 7/16/2024 PETER MOSESIAN
Issued 7/18/2024 APPLICANT
CofO in Progress 6/3/2025 JAVIER RAMOS JR
Permit Finaled 6/20/2025 RUBEN SALAS
Permit Finaled 6/20/2025 RUBEN SALAS
CofO Issued 6/20/2025 RUBEN SALAS

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 5/24/2024 BIAINA HARITUNIAN
Roof/Waste drainage to street Cleared 5/24/2024 BIAINA HARITUNIAN
Sewer availability Cleared 5/24/2024 BIAINA HARITUNIAN
ZI Cleared 6/12/2024 JASON CHAN
Trees in Parkway Cleared 7/8/2024 ADALBERTO VERA
Permit Cleared 7/9/2024 BRYAN GODINEZ

Contact Information

Contractor Alloi Inc; Lic. No.: 924675-B       ,
Engineer Andrada,, Aprile; Lic. No.: C81097 27240 TURNBERRY LANE      VALENCIA, CA 91355
Engineer Chikhale,, Jonathan; Lic. No.: C78893 2820 MILITARY AVENUE      LOS ANGELES, CA 90064

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Other (see comments) 8/15/2024 Conditional Approval JUAN VALENZUELA
Excavation/Setback/Form/Re-Bar 8/16/2024 Approved CHRISTOPHER ROJAS
Footing/Foundation/Slab 8/16/2024 Partial Approval CHRISTOPHER ROJAS
BUILDING-Rough-Frame 9/10/2024 Not Ready for Inspection SALVADOR MARTINEZ
Floor/Roof Diaphrgm/Shear Wall 9/10/2024 Partial Approval SALVADOR MARTINEZ
Wood Frame 9/10/2024 Not Ready for Inspection SALVADOR MARTINEZ
Floor/Roof Diaphrgm/Shear Wall 10/3/2024 Corrections Issued CHRISTOPHER ROJAS
Footing/Foundation/Slab 10/29/2024 Approved CHRISTOPHER ROJAS
Reinforced Concrete Frame 10/29/2024 Approved CHRISTOPHER ROJAS
ELECTRICAL-Rough 11/14/2024 Corrections Issued CHRISTOPHER ROJAS
ELECTRICAL-Rough 11/27/2024 Approved CHRISTOPHER ROJAS
BUILDING-Rough-Frame 12/12/2024 Corrections Issued CHRISTOPHER ROJAS
PLUMBING-Rough 12/12/2024 Partial Inspection CHRISTOPHER ROJAS
BUILDING-Rough-Frame 12/24/2024 Approved CHRISTOPHER ROJAS
PLUMBING-Rough 12/24/2024 Approved CHRISTOPHER ROJAS
Insulation 12/31/2024 Approved CHRISTOPHER ROJAS
Drywall Nailing 1/15/2025 Approved CHRISTOPHER ROJAS
ELECTRICAL-Final 5/21/2025 Approved JAVIER RAMOS JR
Final 5/21/2025 Corrections Issued JAVIER RAMOS JR
Green Building Final 5/21/2025 Approved JAVIER RAMOS JR
HVAC-Final 5/21/2025 Approved JAVIER RAMOS JR
PLUMBING-Final 5/21/2025 Approved JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 5/21/2025 SGSOV Approved JAVIER RAMOS JR
Smoke Detectors 5/21/2025 Approved JAVIER RAMOS JR
Final 6/3/2025 OK to Issue CofO JAVIER RAMOS JR