5824 N MAMMOTH AVE 91401

Certificate Information: 5824 N MAMMOTH AVE 91401

Application / Permit
24014-20000-01395
Plan Check / Job No.
B24VN04568
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED ADDITION TO ENLARGE EX KITCHEN & DINING ROOM. REMOVE EXISTING EXTERIOR WINDOWS & DOORS FOR NEW FOLDING GLASS DOORS PER PLAN. CONSTRUCTION DESIGN PER ENGR.
Permit Issued
Issued on 5/17/2024
Issuing Office
West Los Angeles
Current Status
CofO Issued on 5/15/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/5/2024 APPLICANT
Assigned to Plan Check Engineer 4/11/2024 HAYATO TSUCHIYA
Corrections Issued 4/11/2024 HAYATO TSUCHIYA
Building Plans Picked Up 4/16/2024 APPLICANT
Plan Check Approved 4/23/2024 YAQUB MIRZA
Issued 5/17/2024 APPLICANT
CofO in Progress 5/8/2025 RYAN SALAZAR
Permit Finaled 5/15/2025 RUBEN SALAS
CofO Issued 5/15/2025 RUBEN SALAS
Permit Finaled 5/15/2025 RUBEN SALAS

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 4/22/2024 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 4/22/2024 CARLOS AGUILERA

Contact Information

Contractor Dezign Construction Inc; Lic. No.: 1107522-B 6230 MELBA AVE      WOODLAND HILLS, CA 91367
Engineer Sandoval,, Martin; Lic. No.: C56905 12761 DAIRY ST      EASTVALE, CA 92880

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/6/2024 Approved RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 6/11/2024 Partial Approval RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 7/3/2024 Approved RYAN SALAZAR
ELECTRICAL-Rough 7/16/2024 Approved RYAN SALAZAR
PLUMBING-Rough 7/16/2024 Approved RYAN SALAZAR
Insulation 7/18/2024 Approved RYAN SALAZAR
Drywall Nailing 7/22/2024 Approved RYAN SALAZAR
Green Building Rough 7/22/2024 Approved RYAN SALAZAR
BUILDING-Rough-Frame 4/30/2025 Corrections Issued RYAN SALAZAR
ELECTRICAL-Final 4/30/2025 Approved RYAN SALAZAR
Final 4/30/2025 Corrections Issued RYAN SALAZAR
Green Building Final 4/30/2025 Approved RYAN SALAZAR
HVAC-Final 4/30/2025 Approved RYAN SALAZAR
PLUMBING-Final 4/30/2025 Approved RYAN SALAZAR
SGSOV-Seismic Gas S/O Valve 4/30/2025 SGSOV Approved RYAN SALAZAR
Service/Power Release 4/30/2025 Approved RYAN SALAZAR
Smoke Detectors 4/30/2025 Approved RYAN SALAZAR
BUILDING-Rough-Frame 5/7/2025 Approved RYAN SALAZAR
ELECTRICAL-Final 5/7/2025 Approved RYAN SALAZAR
Final 5/7/2025 OK to Issue CofO RYAN SALAZAR
HVAC-Final 5/7/2025 Approved RYAN SALAZAR
PLUMBING-Final 5/7/2025 Approved RYAN SALAZAR
Service/Power Release 5/7/2025 Approved RYAN SALAZAR