7818-7820 N RIVERTON AVE 91352

Certificate Information: 7818-7820 N RIVERTON AVE 91352

Application / Permit
24014-20000-01391
Plan Check / Job No.
B24VN04560
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMODEL, REMOVE ATTACHED GARAGE AND ADD (N) 8'-8" X 7' ATTACHED PATIO COVER AND (N) 21' X 27'-5" TWO STORY ACCESSORY PER LAMC 12.22 A.33(c) and (e) ALL WORK PER ENGINEERING
Permit Issued
Issued on 6/26/2024
Issuing Office
Valley
Current Status
Issued on 6/26/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 4/5/2024 APPLICANT
Assigned to Plan Check Engineer 4/11/2024 SEWADA ZADOORIAN MILAGARDI
Corrections Issued 4/15/2024 SEWADA ZADOORIAN MILAGARDI
Quality Review Completed 4/19/2024 STEVEN KIM
Building Plans Picked Up 4/22/2024 APPLICANT
Plan Check Approved 6/26/2024 SEWADA ZADOORAN MILAGARDI
Issued 6/26/2024 APPLICANT

Permit Application Clearance Information

Address approval Cleared 5/4/2024 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 5/4/2024 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 5/7/2024 CARLOS AGUILERA
Sewer availability Cleared 5/7/2024 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Abedian,, Vanik; Lic. No.: S5323 2906 JOLLEY DR      BURBANK, CA 91504

Inspector Information

MATTHEW NELSON, (818) 374-1170 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 10/31/2024 Partial Inspection MATTHEW NELSON
Excavation/Setback/Form/Re-Bar 11/19/2024 Partial Approval MATTHEW NELSON
Footing/Foundation/Slab 11/19/2024 Partial Approval MATTHEW NELSON
Footing/Foundation/Slab 12/9/2024 Partial Approval MICHEL ABAJAN
Sewer 12/27/2024 Partial Inspection CHRISTOPHER ROJAS
Underground Mechanical 12/27/2024 Partial Approval CHRISTOPHER ROJAS
Deputy Drilled-In Anchors 1/14/2025 Conditional Approval ROBERT GOLD
Footing/Foundation/Slab 1/15/2025 Partial Approval MATTHEW NELSON
Footing/Foundation/Slab 1/27/2025 Approved MATTHEW NELSON
Wood Frame 2/25/2025 Partial Approval MATTHEW NELSON
Interior/Exterior Lathing 3/11/2025 Not Ready for Inspection MATTHEW NELSON
Wood Frame 3/11/2025 Corrections Issued MATTHEW NELSON
Wood Frame 3/13/2025 Partial Approval WILLIAM WREN
Wood Frame 3/18/2025 Partial Approval VINCENT HANLEY
BUILDING-Rough-Frame 4/7/2025 Corrections Issued MATTHEW NELSON
Wood Frame 4/7/2025 Partial Approval MATTHEW NELSON
Interior/Exterior Lathing 4/9/2025 Partial Approval MATTHEW NELSON
Floor/Roof Diaphrgm/Shear Wall 4/30/2025 Corrections Issued NICHOLAS TROWBRIDGE
Deputy Wood Construction 5/5/2025 Conditional Approval DAVID MATSON
Floor/Roof Diaphrgm/Shear Wall 5/13/2025 Corrections Issued NICHOLAS TROWBRIDGE
Floor/Roof Diaphrgm/Shear Wall 5/20/2025 Approved NICHOLAS TROWBRIDGE
Gas Test 5/20/2025 Approved NICHOLAS TROWBRIDGE
PLUMBING-Rough 5/20/2025 Approved NICHOLAS TROWBRIDGE
Sewer 5/20/2025 Approved NICHOLAS TROWBRIDGE
HVAC-Rough 6/23/2025 Approved MATTHEW NELSON
Wood Frame 6/23/2025 Partial Approval MATTHEW NELSON
BUILDING-Rough-Frame 8/18/2025 Approved MATTHEW NELSON
ELECTRICAL-Rough 8/18/2025 Approved MATTHEW NELSON
Green Building Rough 8/18/2025 Approved MATTHEW NELSON
Interior/Exterior Lathing 8/18/2025 Partial Approval MATTHEW NELSON
Rough-Elec/Plmb/HVAC 8/18/2025 Approved MATTHEW NELSON
Insulation 9/3/2025 Corrections Issued MATTHEW NELSON
Insulation 9/8/2025 Approved MATTHEW NELSON
Drywall Nailing 9/16/2025 Approved MATTHEW NELSON
Shower Pan 10/2/2025 Approved MATTHEW NELSON
Interior/Exterior Lathing 10/7/2025 Approved MATTHEW NELSON