12512 N COMETA AVE 91340

Certificate Information: 12512 N COMETA AVE 91340

Application / Permit
24014-20000-01386
Plan Check / Job No.
B24VN04543
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan: Enlarge existing detached A.D.U. by converting attached garage and adding an addition per LAMC 12.22 A.33 (c)-(d). ***1 of 2***
Permit Issued
Issued on 10/9/2024
Issuing Office
Current Status
CofO Issued on 12/18/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/10/2024 APPLICANT
Assigned to Plan Check Engineer 4/12/2024 CAROLEAN BASMA
Corrections Issued 4/13/2024 CAROLEAN BASMA
Applicant returned to address corrections 7/26/2024 CAROLEAN BASMA
Applicant returned to address corrections 8/20/2024 CAROLEAN BASMA
Plan Check Approved 9/23/2024 CAROLEAN BASMA
Issued 10/9/2024 APPLICANT
CofO in Progress 12/1/2025 KEVIN BERBERYAN
CofO Issued 12/18/2025 RUBEN SALAS
Permit Finaled 12/18/2025 RUBEN SALAS

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 8/22/2024 MARKOS PEREZ-BRAN
Eng Process Fee Ord 176,300 Cleared 8/27/2024 MARKOS PEREZ-BRAN
Sewer availability Cleared 8/27/2024 MARKOS PEREZ-BRAN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

KEVIN BERBERYAN, (818) 374-9931 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 12/11/2024 Corrections Issued KEVIN BERBERYAN
PLUMBING-Rough 3/21/2025 Corrections Issued KEVIN BERBERYAN
PLUMBING-Rough 3/25/2025 Approved KEVIN BERBERYAN
Deputy Drilled-In Anchors 3/28/2025 Conditional Approval RAUL OLAGI
Footing/Foundation/Slab 4/3/2025 Approved KEVIN BERBERYAN
BUILDING-Rough-Frame 5/13/2025 Corrections Issued KEVIN BERBERYAN
ELECTRICAL-Rough 5/13/2025 Corrections Issued KEVIN BERBERYAN
Green Building Rough 5/13/2025 Not Ready for Inspection KEVIN BERBERYAN
PLUMBING-Rough 5/13/2025 Corrections Issued KEVIN BERBERYAN
BUILDING-Rough-Frame 5/15/2025 Partial Inspection KEVIN BERBERYAN
ELECTRICAL-Rough 5/15/2025 Not Ready for Inspection KEVIN BERBERYAN
Green Building Rough 5/15/2025 Not Ready for Inspection KEVIN BERBERYAN
PLUMBING-Rough 5/15/2025 Approved KEVIN BERBERYAN
BUILDING-Rough-Frame 5/20/2025 Corrections Issued KEVIN BERBERYAN
ELECTRICAL-Rough 5/20/2025 Not Ready for Inspection KEVIN BERBERYAN
Floor/Roof Diaphrgm/Shear Wall 5/20/2025 Approved KEVIN BERBERYAN
Green Building Rough 5/20/2025 Not Ready for Inspection KEVIN BERBERYAN
Insulation 5/20/2025 Not Ready for Inspection KEVIN BERBERYAN
Insulation 5/27/2025 Corrections Issued KEVIN BERBERYAN
Insulation 5/29/2025 Corrections Issued KEVIN BERBERYAN
Insulation 6/13/2025 Not Ready for Inspection KEVIN BERBERYAN
Interior/Exterior Lathing 6/13/2025 Not Ready for Inspection KEVIN BERBERYAN
BUILDING-Rough-Frame 6/17/2025 Corrections Issued KEVIN BERBERYAN
Insulation 6/17/2025 Approved KEVIN BERBERYAN
Interior/Exterior Lathing 6/17/2025 Approved KEVIN BERBERYAN
Rough-Elec/Plmb/HVAC 6/17/2025 Approved KEVIN BERBERYAN
Drywall Nailing 7/1/2025 Not Ready for Inspection MICHAEL CORTEZ
Shower Pan 7/1/2025 Approved MICHAEL CORTEZ
Drywall Nailing 7/11/2025 Corrections Issued MICHAEL CORTEZ
BUILDING-Rough-Frame 9/11/2025 Not Ready for Inspection KEVIN BERBERYAN
Final 9/11/2025 Corrections Issued KEVIN BERBERYAN
Green Building Final 9/11/2025 Not Ready for Inspection KEVIN BERBERYAN
Green Building Rough 9/11/2025 Approved KEVIN BERBERYAN
SGSOV-Seismic Gas S/O Valve 9/11/2025 SGSOV Approved KEVIN BERBERYAN
Smoke Detectors 9/11/2025 Approved KEVIN BERBERYAN
BUILDING-Rough-Frame 10/14/2025 Approved KEVIN BERBERYAN
Final 10/14/2025 Corrections Issued KEVIN BERBERYAN
Green Building Final 10/14/2025 Approved KEVIN BERBERYAN
Final 10/17/2025 OK to Issue CofO KEVIN BERBERYAN