22841-22843 W CANTLAY ST 91307

Certificate Information: 22841-22843 W CANTLAY ST 91307

Application / Permit
24014-20000-01371
Plan Check / Job No.
B24VN04494
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN. CONVERT (E) ATTACHED GARAGE TO A (N) ACCESSORY DWELLING UNIT AND 6'-7" x 11'-9" ADDITION PER LAMC 12.22 A.33(c) AND (e).
Permit Issued
Issued on 8/14/2024
Issuing Office
Current Status
CofO Issued on 1/27/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/4/2024 APPLICANT
Assigned to Plan Check Engineer 4/9/2024 GIOVANNY CHAVEZ
Corrections Issued 4/9/2024 GIOVANNY CHAVEZ
Plan Check Approved 8/14/2024 GIOVANNY CHAVEZ
Issued 8/14/2024 APPLICANT
CofO in Progress 1/22/2025 CHRIS CHRISTENSEN
Permit Finaled 1/27/2025 JOHN JANSON
CofO Issued 1/27/2025 JOHN JANSON
Permit Finaled 1/27/2025 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 4/15/2024 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 4/15/2024 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 4/15/2024 LEE GUILBEAUX
Sewer availability Cleared 4/15/2024 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 4/15/2024 LEE GUILBEAUX
Construction near power lines Cleared 8/5/2024 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Melchor,, Oscar Elias; Lic. No.: C76828 21243 VENTURA BLVD SUITE 119      WOODLAND HILLS, CA 91364

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 9/30/2024 Conditional Approval CHRIS CHRISTENSEN
Footing/Foundation/Slab 9/30/2024 Approved CHRIS CHRISTENSEN
PLUMBING-Rough 9/30/2024 Partial Approval CHRIS CHRISTENSEN
BUILDING-Rough-Frame 10/22/2024 Corrections Issued CHRIS CHRISTENSEN
ELECTRICAL-Rough 10/22/2024 Approved CHRIS CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 10/22/2024 Corrections Issued CHRIS CHRISTENSEN
Green Building Rough 10/22/2024 Not Ready for Inspection CHRIS CHRISTENSEN
HVAC-Rough 10/22/2024 Approved CHRIS CHRISTENSEN
PLUMBING-Rough 10/22/2024 Approved CHRIS CHRISTENSEN
ELECTRICAL-Rough 10/24/2024 Approved CHRIS CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 10/24/2024 Partial Approval CHRIS CHRISTENSEN
HVAC-Rough 10/24/2024 Approved CHRIS CHRISTENSEN
PLUMBING-Rough 10/24/2024 Approved CHRIS CHRISTENSEN
Wood Frame 10/24/2024 Partial Approval CHRIS CHRISTENSEN
BUILDING-Rough-Frame 10/28/2024 Approved CHRIS CHRISTENSEN
Green Building Rough 10/28/2024 Approved CHRIS CHRISTENSEN
Insulation 10/28/2024 Conditional Approval CHRIS CHRISTENSEN
Interior/Exterior Lathing 10/28/2024 Partial Approval CHRIS CHRISTENSEN
Drywall Nailing 10/30/2024 Approved CHRIS CHRISTENSEN
Interior/Exterior Lathing 10/30/2024 Approved CHRIS CHRISTENSEN
Final 1/10/2025 Corrections Issued CHRIS CHRISTENSEN
Green Building Final 1/10/2025 Not Ready for Inspection CHRIS CHRISTENSEN
HVAC-Final 1/10/2025 Approved CHRIS CHRISTENSEN
PLUMBING-Final 1/10/2025 Approved CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 1/10/2025 SGSOV Approved CHRIS CHRISTENSEN
Smoke Detectors 1/10/2025 Approved CHRIS CHRISTENSEN
Final 1/21/2025 OK to Issue CofO CHRIS CHRISTENSEN
Green Building Final 1/21/2025 Approved CHRIS CHRISTENSEN
Service/Power Release 1/21/2025 Approved CHRIS CHRISTENSEN