22925 W CALVERT ST 91367
Certificate Information: 22925 W CALVERT ST 91367
- Application / Permit
- 24014-20000-01369
- Plan Check / Job No.
- B24VN04491
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Accessory Living Quarters
- Work Description
- ADDITION TO EX. ACCESSORY LIVING QUARTERS. WORK PER ENGINEER.
- Permit Issued
- Issued on 5/2/2024
- Issuing Office
- Current Status
- Issued on 5/2/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 4/4/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 4/10/2024 | ARTIN ZARUKIAN |
| Corrections Issued | 4/13/2024 | ARTIN ZARUKIAN |
| Building Plans Picked Up | 4/15/2024 | APPLICANT |
| Plan Check Approved | 5/2/2024 | ROSENDO MEDINA |
| Issued | 5/2/2024 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 4/15/2024 | CARLOS RAMIREZ |
| Roof/Waste drainage to street | Cleared | 4/15/2024 | CARLOS RAMIREZ |
| Grading Pre-Inspection | Cleared | 4/16/2024 | CHARLES POWELL |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Helou,, Dawn Renee; Lic. No.: C52361 | 22701 ERWIN ST WOODLAND HILLS, CA 91367 |
Inspector Information
| GEVORK IPCHYAN, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
| TROY SANDERS, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 5/13/2024 | Conditional Approval | GEVORK IPCHYAN |
| Footing/Foundation/Slab | 5/16/2024 | Approved | TROY SANDERS |
| Deputy Reinf. Concrete | 5/17/2024 | Conditional Approval | GEVORK IPCHYAN |
| ELECTRICAL-Rough | 6/13/2024 | Not Ready for Inspection | TROY SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 6/13/2024 | Partial Approval | TROY SANDERS |
| HVAC-Rough | 6/13/2024 | Not Ready for Inspection | TROY SANDERS |
| ELECTRICAL-Rough | 6/18/2024 | Approved | GEVORK IPCHYAN |
| HVAC-Rough | 6/18/2024 | Partial Approval | GEVORK IPCHYAN |
| Insulation | 6/25/2024 | Approved | ARUTYUN MADATYAN |
| Interior/Exterior Lathing | 6/25/2024 | Partial Approval | ARUTYUN MADATYAN |
| Drywall Nailing | 7/1/2024 | Approved | ALEXANDER HANDY |
| Green Building Rough | 7/1/2024 | Approved | ALEXANDER HANDY |
| BUILDING-Rough-Frame | 8/14/2024 | Approved | TROY SANDERS |
| Final | 8/14/2024 | Not Ready for Inspection | TROY SANDERS |
| Green Building Final | 8/14/2024 | Approved | TROY SANDERS |
| SGSOV-Seismic Gas S/O Valve | 8/14/2024 | SGSOV Approved | TROY SANDERS |
| Smoke Detectors | 8/14/2024 | Approved | TROY SANDERS |