20302 W OXNARD ST 91367
Certificate Information: 20302 W OXNARD ST 91367
- Application / Permit
- 24014-20000-01368
- Plan Check / Job No.
- B24VN04486
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan. (N) DETACHED ADU PER LAMC 12.22 A.33(c) AND (d)
- Permit Issued
- Issued on 11/19/2024
- Issuing Office
- Current Status
- CofO Issued on 2/24/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/10/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 4/18/2024 | YASHAR EMAMI |
| Corrections Issued | 4/24/2024 | YASHAR EMAMI |
| Re-Submittal Required | 5/7/2024 | CHIHARU SUZUKI |
| Re-Submitted | 5/7/2024 | YASHAR EMAMI |
| Corrections Issued 2 | 5/7/2024 | YASHAR EMAMI |
| Submitted for Second Quality Review | 5/7/2024 | YASHAR EMAMI |
| Quality Review Completed | 5/7/2024 | CHIHARU SUZUKI |
| Applicant returned to address corrections | 7/26/2024 | YASHAR EMAMI |
| Applicant returned to address corrections | 8/2/2024 | YASHAR EMAMI |
| Applicant returned to address corrections | 8/30/2024 | YASHAR EMAMI |
| Plan Check Approved | 9/23/2024 | YASHAR EMAMI |
| No Progress | 9/23/2024 | YASHAR EMAMI |
| Plan Check Approved | 9/23/2024 | YASHAR EMAMI |
| Issued | 11/19/2024 | APPLICANT |
| CofO in Progress | 11/10/2025 | ALEXANDER HANDY |
| Permit Finaled | 2/24/2026 | JOHN JANSON |
| CofO Issued | 2/24/2026 | JOHN JANSON |
| Permit Finaled | 2/24/2026 | JOHN JANSON |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 4/24/2024 | YASHAR EMAMI |
| Address approval | Cleared | 5/8/2024 | CARLOS RAMIREZ |
| Roof/Waste drainage to street | Cleared | 5/8/2024 | CARLOS RAMIREZ |
| Eng Process Fee Ord 176,300 | Cleared | 5/14/2024 | CARLOS RAMIREZ |
| Sewer availability | Cleared | 5/14/2024 | CARLOS RAMIREZ |
| ZA Case | Cleared | 6/18/2024 | NOAH MCCOY |
| Hydrant and Access approval | Cleared | 6/21/2024 | GILBERT URREA |
| GPI Written Notices | Cleared | 9/23/2024 | YASHAR EMAMI |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Endrawes,, George; Lic. No.: C91685 | 1140 PORTOFINO CT 103 CORONA, CA 92881 |
Inspector Information
| DAVID FASTIGGI, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
| ALEXANDER HANDY, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 12/31/2024 | Corrections Issued | ALEXANDER HANDY |
| PLUMBING-Rough | 1/8/2025 | Partial Approval | SCOTT SOBEL |
| Footing/Foundation/Slab | 1/31/2025 | Approved | ALEXANDER HANDY |
| PLUMBING-Rough | 1/31/2025 | Partial Approval | ALEXANDER HANDY |
| Wood Frame | 2/27/2025 | Partial Approval | ALEXANDER HANDY |
| Special/Order Compliance | 4/14/2025 | Corrections Issued | ALEXANDER HANDY |
| Floor/Roof Diaphrgm/Shear Wall | 6/25/2025 | Corrections Issued | KRISTEN CAUSEY |
| Floor/Roof Diaphrgm/Shear Wall | 6/30/2025 | Partial Approval | TROY SANDERS |
| Special/Order Compliance | 6/30/2025 | Corrections Issued | TROY SANDERS |
| BUILDING-Rough-Frame | 7/16/2025 | Corrections Issued | ALEXANDER HANDY |
| Interior/Exterior Lathing | 7/16/2025 | Partial Approval | ALEXANDER HANDY |
| Rough-Elec/Plmb/HVAC | 7/16/2025 | Corrections Issued | ALEXANDER HANDY |
| Rough-Elec/Plmb/HVAC | 7/23/2025 | Not Ready for Inspection | ALEXANDER HANDY |
| Wood Frame | 7/23/2025 | Not Ready for Inspection | ALEXANDER HANDY |
| BUILDING-Rough-Frame | 8/1/2025 | Corrections Issued | SCOTT SOBEL |
| ELECTRICAL-Rough | 8/1/2025 | Approved | SCOTT SOBEL |
| PLUMBING-Rough | 8/1/2025 | Not Ready for Inspection | SCOTT SOBEL |
| Shower Pan | 8/1/2025 | Approved | SCOTT SOBEL |
| ELECTRICAL-Rough | 8/4/2025 | Corrections Issued | SCOTT SOBEL |
| HVAC-Rough | 8/4/2025 | Corrections Issued | SCOTT SOBEL |
| PLUMBING-Rough | 8/4/2025 | Corrections Issued | SCOTT SOBEL |
| BUILDING-Rough-Frame | 8/12/2025 | Approved | ALEXANDER HANDY |
| ELECTRICAL-Rough | 8/12/2025 | Approved | ALEXANDER HANDY |
| Final | 8/12/2025 | Corrections Issued | ALEXANDER HANDY |
| HVAC-Rough | 8/12/2025 | Approved | ALEXANDER HANDY |
| PLUMBING-Rough | 8/12/2025 | Approved | ALEXANDER HANDY |
| Insulation | 8/21/2025 | Approved | ALEXANDER HANDY |
| Underground Mechanical | 8/21/2025 | Approved | ALEXANDER HANDY |
| Drywall Nailing | 9/2/2025 | Approved | ALEXANDER HANDY |
| Final | 10/29/2025 | Corrections Issued | ALEXANDER HANDY |
| SGSOV-Seismic Gas S/O Valve | 10/29/2025 | SGSOV No Gas | ALEXANDER HANDY |
| Service/Power Release | 10/29/2025 | Approved | ALEXANDER HANDY |
| Smoke Detectors | 10/29/2025 | Approved | ALEXANDER HANDY |
| ELECTRICAL-Final | 11/4/2025 | Approved | ALEXANDER HANDY |
| Final | 11/4/2025 | OK to Issue CofO | ALEXANDER HANDY |
| HVAC-Final | 11/4/2025 | Approved | ALEXANDER HANDY |
| PLUMBING-Final | 11/4/2025 | Approved | ALEXANDER HANDY |