5375 N VANALDEN AVE 91356
Certificate Information: 5375 N VANALDEN AVE 91356
- Application / Permit
- 24014-20000-01361
- Plan Check / Job No.
- B24VN04469
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- REMOVE ALL (E) WALLS EXCEPT FOR A PORTION OF AN EXT. WALL AND ERECT AN IRR SHAPED 30'-2" x 63'-2" DET. ACCESSORY DWELLING UNIT [PER LAMC 12.22 A.33 (c)-(d)] W/ AN ATT. 2-CAR GARAGE
- Permit Issued
- Issued on 7/3/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 3/7/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/4/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 4/11/2024 | SEAN SHAHMIRI |
| Corrections Issued | 4/18/2024 | SEAN SHAHMIRI |
| Quality Review Completed | 4/19/2024 | STEVEN KIM |
| Building Plans Picked Up | 4/22/2024 | APPLICANT |
| Applicant returned to address corrections | 6/5/2024 | NAREG ATARIAN |
| Plan Check Approved | 7/3/2024 | NAREG ATARIAN |
| Plan Check Approved | 7/3/2024 | NAREG ATARIAN |
| Issued | 7/3/2024 | APPLICANT |
| CofO in Progress | 2/11/2025 | JOHN KIDWELL |
| CofO Issued | 3/7/2025 | JOHN JANSON |
| Permit Finaled | 3/7/2025 | JOHN JANSON |
Permit Application Clearance Information
| Miscellaneous | Cleared | 4/23/2024 | NATHAN ROMINE |
| ZA Case | Cleared | 4/23/2024 | NATHAN ROMINE |
| ZA Case | Cleared | 4/23/2024 | NATHAN ROMINE |
| ZI | Cleared | 4/23/2024 | NATHAN ROMINE |
| Address approval | Cleared | 4/24/2024 | EDGAR ALCARAZ |
| Eng Process Fee Ord 176,300 | Cleared | 4/24/2024 | EDGAR ALCARAZ |
| Roof/Waste drainage to street | Cleared | 4/24/2024 | EDGAR ALCARAZ |
| Sewer availability | Cleared | 4/25/2024 | EDGAR ALCARAZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Standley,, Craig Erick; Lic. No.: C87675 | 60 VIA CARATAMA SAN CLEMENTE, CA 92673 |
Inspector Information
| JOHN KIDWELL, (818) 774-4314 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/26/2024 | Partial Inspection | MORRIS JACKSON |
| PLUMBING-Rough | 9/6/2024 | Partial Approval | JOHN KIDWELL |
| Footing/Foundation/Slab | 9/11/2024 | Approved | JOHN KIDWELL |
| Excavation/Setback/Form/Re-Bar | 9/30/2024 | Approved | JOHN KIDWELL |
| Floor/Roof Diaphrgm/Shear Wall | 10/18/2024 | Partial Approval | JOHN KIDWELL |
| Deputy Wood Construction | 10/28/2024 | Partial Approval | JOHN KIDWELL |
| PLUMBING-Rough | 10/31/2024 | Approved | JOHN KIDWELL |
| HVAC-Rough | 11/7/2024 | Approved | JOHN KIDWELL |
| Shower Pan | 11/7/2024 | Approved | JOHN KIDWELL |
| BUILDING-Rough-Frame | 11/14/2024 | Approved | JOHN KIDWELL |
| ELECTRICAL-Rough | 11/14/2024 | Approved | JOHN KIDWELL |
| Green Building Rough | 11/14/2024 | Approved | JOHN KIDWELL |
| Interior/Exterior Lathing | 11/14/2024 | Approved | JOHN KIDWELL |
| Insulation | 11/22/2024 | Approved | JOHN KIDWELL |
| Drywall Nailing | 12/2/2024 | Approved | JOHN KIDWELL |
| Gas Test | 12/24/2024 | Partial Inspection | JOHN KIDWELL |
| ELECTRICAL-Final | 1/8/2025 | Approved | JOHN KIDWELL |
| HVAC-Final | 1/8/2025 | Conditional Approval | JOHN KIDWELL |
| PLUMBING-Final | 1/8/2025 | Approved | JOHN KIDWELL |
| Final | 1/9/2025 | Corrections Issued | JOHN KIDWELL |
| Green Building Final | 1/9/2025 | Not Ready for Inspection | JOHN KIDWELL |
| SGSOV-Seismic Gas S/O Valve | 1/9/2025 | SGSOV Not Required | JOHN KIDWELL |
| Smoke Detectors | 1/9/2025 | Approved | JOHN KIDWELL |
| Final | 2/11/2025 | OK to Issue CofO | JOHN KIDWELL |
| Green Building Final | 2/11/2025 | Approved | JOHN KIDWELL |