12508 W MIRANDA ST 91607
Certificate Information: 12508 W MIRANDA ST 91607
- Application / Permit
- 24014-20000-01355
- Plan Check / Job No.
- B24VN04442
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADDITION TO AND CONVERT EX. GARAGE INTO DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c) and (d).
- Permit Issued
- Issued on 8/29/2024
- Issuing Office
- Current Status
- CofO Issued on 10/15/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/5/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 4/10/2024 | ROSENDO MEDINA |
| Corrections Issued | 4/11/2024 | ROSENDO MEDINA |
| Plan Check Approved | 6/6/2024 | ROSENDO MEDINA |
| Issued | 8/29/2024 | APPLICANT |
| CofO in Progress | 5/27/2025 | OGANES TARAKHCHYAN |
| Permit Finaled | 10/15/2025 | RUBEN SALAS |
| CofO Issued | 10/15/2025 | RUBEN SALAS |
| Permit Finaled | 10/15/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 4/24/2024 | EDGAR ALCARAZ |
| Sewer availability | Cleared | 4/24/2024 | EDGAR ALCARAZ |
| Address approval | Cleared | 4/30/2024 | EDGAR ALCARAZ |
| Eng Process Fee Ord 176,300 | Cleared | 5/14/2024 | EDGAR ALCARAZ |
Contact Information
| Architect | Sobhani,, Jamsheed Madadkar; Lic. No.: NA29736 | , |
| Contractor | Owner-Builder | , |
| Engineer | Chiu,, Ivan Wai-Kuen; Lic. No.: NA44672 | , |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 10/4/2024 | Conditional Approval | RAUL OLAGI |
| Excavation/Setback/Form/Re-Bar | 10/7/2024 | Corrections Issued | OGANES TARAKHCHYAN |
| Footing/Foundation/Slab | 10/7/2024 | Corrections Issued | OGANES TARAKHCHYAN |
| Sewer | 10/7/2024 | Approved | OGANES TARAKHCHYAN |
| Underground Mechanical | 10/7/2024 | Corrections Issued | OGANES TARAKHCHYAN |
| Footing/Foundation/Slab | 10/10/2024 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Underground Mechanical | 10/10/2024 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Underground Mechanical | 10/11/2024 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Footing/Foundation/Slab | 10/17/2024 | Partial Approval | OGANES TARAKHCHYAN |
| Deputy Drilled-In Anchors | 10/23/2024 | Conditional Approval | RAUL OLAGI |
| Footing/Foundation/Slab | 10/24/2024 | Approved | GAREN HAYRAPETYAN |
| ELECTRICAL-Rough | 12/4/2024 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| HVAC-Rough | 12/4/2024 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 12/4/2024 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Wood Frame | 12/4/2024 | Partial Approval | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 12/16/2024 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| HVAC-Rough | 12/16/2024 | Corrections Issued | GAREN HAYRAPETYAN |
| PLUMBING-Rough | 12/16/2024 | Approved | GAREN HAYRAPETYAN |
| Interior/Exterior Lathing | 1/15/2025 | Partial Approval | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 1/17/2025 | Approved | OGANES TARAKHCHYAN |
| HVAC-Rough | 1/17/2025 | Approved | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 1/17/2025 | Approved | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 1/21/2025 | Approved | OGANES TARAKHCHYAN |
| Green Building Rough | 1/21/2025 | Approved | OGANES TARAKHCHYAN |
| Insulation | 1/23/2025 | Approved | OGANES TARAKHCHYAN |
| Drywall Nailing | 1/30/2025 | Approved | MICHAEL CORTEZ |
| Shower Pan | 2/3/2025 | Approved | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 2/7/2025 | Partial Approval | OGANES TARAKHCHYAN |
| Final | 5/9/2025 | Corrections Issued | GAREN HAYRAPETYAN |
| Green Building Final | 5/9/2025 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| SGSOV-Seismic Gas S/O Valve | 5/9/2025 | SGSOV Not Ready | GAREN HAYRAPETYAN |
| Smoke Detectors | 5/9/2025 | Approved | GAREN HAYRAPETYAN |
| Final | 5/21/2025 | OK to Issue CofO | OGANES TARAKHCHYAN |
| Green Building Final | 5/21/2025 | Approved | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 5/21/2025 | SGSOV Approved | OGANES TARAKHCHYAN |