12508 W MIRANDA ST 91607

Certificate Information: 12508 W MIRANDA ST 91607

Application / Permit
24014-20000-01355
Plan Check / Job No.
B24VN04442
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADDITION TO AND CONVERT EX. GARAGE INTO DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c) and (d).
Permit Issued
Issued on 8/29/2024
Issuing Office
Current Status
CofO Issued on 10/15/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/5/2024 APPLICANT
Assigned to Plan Check Engineer 4/10/2024 ROSENDO MEDINA
Corrections Issued 4/11/2024 ROSENDO MEDINA
Plan Check Approved 6/6/2024 ROSENDO MEDINA
Issued 8/29/2024 APPLICANT
CofO in Progress 5/27/2025 OGANES TARAKHCHYAN
Permit Finaled 10/15/2025 RUBEN SALAS
CofO Issued 10/15/2025 RUBEN SALAS
Permit Finaled 10/15/2025 RUBEN SALAS

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 4/24/2024 EDGAR ALCARAZ
Sewer availability Cleared 4/24/2024 EDGAR ALCARAZ
Address approval Cleared 4/30/2024 EDGAR ALCARAZ
Eng Process Fee Ord 176,300 Cleared 5/14/2024 EDGAR ALCARAZ

Contact Information

Architect Sobhani,, Jamsheed Madadkar; Lic. No.: NA29736       ,
Contractor Owner-Builder       ,
Engineer Chiu,, Ivan Wai-Kuen; Lic. No.: NA44672       ,

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 10/4/2024 Conditional Approval RAUL OLAGI
Excavation/Setback/Form/Re-Bar 10/7/2024 Corrections Issued OGANES TARAKHCHYAN
Footing/Foundation/Slab 10/7/2024 Corrections Issued OGANES TARAKHCHYAN
Sewer 10/7/2024 Approved OGANES TARAKHCHYAN
Underground Mechanical 10/7/2024 Corrections Issued OGANES TARAKHCHYAN
Footing/Foundation/Slab 10/10/2024 Not Ready for Inspection OGANES TARAKHCHYAN
Underground Mechanical 10/10/2024 Not Ready for Inspection OGANES TARAKHCHYAN
Underground Mechanical 10/11/2024 Not Ready for Inspection OGANES TARAKHCHYAN
Footing/Foundation/Slab 10/17/2024 Partial Approval OGANES TARAKHCHYAN
Deputy Drilled-In Anchors 10/23/2024 Conditional Approval RAUL OLAGI
Footing/Foundation/Slab 10/24/2024 Approved GAREN HAYRAPETYAN
ELECTRICAL-Rough 12/4/2024 Not Ready for Inspection OGANES TARAKHCHYAN
HVAC-Rough 12/4/2024 Not Ready for Inspection OGANES TARAKHCHYAN
PLUMBING-Rough 12/4/2024 Not Ready for Inspection OGANES TARAKHCHYAN
Wood Frame 12/4/2024 Partial Approval OGANES TARAKHCHYAN
ELECTRICAL-Rough 12/16/2024 Not Ready for Inspection GAREN HAYRAPETYAN
HVAC-Rough 12/16/2024 Corrections Issued GAREN HAYRAPETYAN
PLUMBING-Rough 12/16/2024 Approved GAREN HAYRAPETYAN
Interior/Exterior Lathing 1/15/2025 Partial Approval OGANES TARAKHCHYAN
ELECTRICAL-Rough 1/17/2025 Approved OGANES TARAKHCHYAN
HVAC-Rough 1/17/2025 Approved OGANES TARAKHCHYAN
PLUMBING-Rough 1/17/2025 Approved OGANES TARAKHCHYAN
BUILDING-Rough-Frame 1/21/2025 Approved OGANES TARAKHCHYAN
Green Building Rough 1/21/2025 Approved OGANES TARAKHCHYAN
Insulation 1/23/2025 Approved OGANES TARAKHCHYAN
Drywall Nailing 1/30/2025 Approved MICHAEL CORTEZ
Shower Pan 2/3/2025 Approved OGANES TARAKHCHYAN
Interior/Exterior Lathing 2/7/2025 Partial Approval OGANES TARAKHCHYAN
Final 5/9/2025 Corrections Issued GAREN HAYRAPETYAN
Green Building Final 5/9/2025 Not Ready for Inspection GAREN HAYRAPETYAN
SGSOV-Seismic Gas S/O Valve 5/9/2025 SGSOV Not Ready GAREN HAYRAPETYAN
Smoke Detectors 5/9/2025 Approved GAREN HAYRAPETYAN
Final 5/21/2025 OK to Issue CofO OGANES TARAKHCHYAN
Green Building Final 5/21/2025 Approved OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 5/21/2025 SGSOV Approved OGANES TARAKHCHYAN