2649 S BARRY AVE 90064

Certificate Information: 2649 S BARRY AVE 90064

Application / Permit
24014-20000-01350
Plan Check / Job No.
B24VN04426
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Addition and Major Remodel to existing 1-story Single Family Dwelling, three portions of existing foundation, wall and ceiling joists to remain. Rebuild as 1-story (51'-9" x 40'-3" Irregular Shape) Single Family Dwelling. NFPA 13D Fire Sprinklers Throughout.
Permit Issued
Issued on 6/11/2024
Issuing Office
Valley
Current Status
CofO Issued on 3/11/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/3/2024 APPLICANT
Assigned to Plan Check Engineer 4/4/2024 VAHAN JIVALAGIAN
Corrections Issued 4/7/2024 VAHAN JIVALAGIAN
Quality Review Completed 4/8/2024 OMID HEDAYAT
Building Plans Picked Up 4/9/2024 APPLICANT
Applicant returned to address corrections 5/20/2024 VAHAN JIVALAGIAN
Plan Check Approved 6/11/2024 VAHAN JIVALAGIAN
Issued 6/11/2024 APPLICANT
CofO in Progress 3/10/2026 ARAM AVEDISIAN
Permit Finaled 3/11/2026 RICHARD STEINBACH
CofO Issued 3/11/2026 RICHARD STEINBACH
Permit Finaled 3/11/2026 RICHARD STEINBACH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 4/9/2024 DIANA RENTERIA
Sewer availability Cleared 4/9/2024 DIANA RENTERIA
Roof/Waste drainage to street Cleared 4/18/2024 DIANA RENTERIA
Specific Plan Cleared 5/6/2024 PEDRO AYALA

Contact Information

Contractor A 1 Construction & Designs Inc; Lic. No.: 1002697-B 2817 S ROBERTSON BLVD      LOS ANGELES, CA 90034
Engineer Telian,, Vartan; Lic. No.: C94330 11776 PIERCE ST      SYLMAR, CA 91342

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 7/10/2024 Partial Inspection JESUS PINEDA
Sewer 7/10/2024 Partial Inspection JESUS PINEDA
Special/Order Compliance 7/10/2024 Corrections Issued JESUS PINEDA
PLUMBING-Rough 7/25/2024 Not Ready for Inspection HERBERT GIRON
Underground Mechanical 7/25/2024 Not Ready for Inspection HERBERT GIRON
PLUMBING-Rough 8/20/2024 Partial Approval JESUS PINEDA
Sewer 8/20/2024 Approved JESUS PINEDA
Footing/Foundation/Slab 9/3/2024 Approved ARAM AVEDISIAN
Deputy Wood Construction 9/9/2024 Conditional Approval MICHAEL PELHAM
Floor/Roof Diaphrgm/Shear Wall 9/24/2024 Partial Approval DANIEL VERA
PLUMBING-Rough 12/3/2024 Approved DANIEL VERA
Shower Pan 12/3/2024 Approved DANIEL VERA
Deputy Drilled-In Anchors 12/16/2024 Conditional Approval DANIEL VERA
HVAC-Rough 12/26/2024 Partial Approval SEAN HAUPT
HVAC-Rough 1/13/2025 Not Ready for Inspection DANIEL VERA
ELECTRICAL-Rough 1/23/2025 Corrections Issued ARAM AVEDISIAN
HVAC-Rough 1/23/2025 Approved ARAM AVEDISIAN
BUILDING-Rough-Frame 2/4/2025 Approved JESUS RODRIGUEZ
ELECTRICAL-Rough 2/4/2025 Approved JESUS RODRIGUEZ
Green Building Rough 2/4/2025 Approved JESUS RODRIGUEZ
Interior/Exterior Lathing 2/4/2025 Approved JESUS RODRIGUEZ
Verify Sprinkler Sign Off 2/4/2025 Approved JESUS RODRIGUEZ
Insulation 2/12/2025 Approved DANIEL VERA
Drywall Nailing 2/20/2025 Approved BOBBY KEY
ELECTRICAL-Final 2/17/2026 Corrections Issued ANTHONY EGSON
Gas Test 2/17/2026 Approved ANTHONY EGSON
HVAC-Final 2/17/2026 Not Ready for Inspection ANTHONY EGSON
Service/Power Release 2/17/2026 Not Ready for Inspection ANTHONY EGSON
Final 3/2/2026 Corrections Issued ARAM AVEDISIAN
Green Building Final 3/2/2026 Approved ARAM AVEDISIAN
SGSOV-Seismic Gas S/O Valve 3/2/2026 SGSOV Approved ARAM AVEDISIAN
Service/Power Release 3/2/2026 Not Ready for Inspection ARAM AVEDISIAN
Smoke Detectors 3/2/2026 Approved ARAM AVEDISIAN
ELECTRICAL-Final 3/10/2026 Approved ARAM AVEDISIAN
Final 3/10/2026 OK to Issue CofO ARAM AVEDISIAN
HVAC-Final 3/10/2026 Approved ARAM AVEDISIAN
PLUMBING-Final 3/10/2026 Approved ARAM AVEDISIAN
Service/Power Release 3/10/2026 Approved ARAM AVEDISIAN