9702 N LEMONA AVE 91343

Certificate Information: 9702 N LEMONA AVE 91343

Application / Permit
24014-20000-01348
Plan Check / Job No.
B24VN04419
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN (E) Detached Garage conversion and addition to ADU per Ordinance
Permit Issued
Issued on 6/19/2024
Issuing Office
Current Status
CofO Issued on 4/2/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/3/2024 APPLICANT
Assigned to Plan Check Engineer 4/8/2024 LUKE GONZALES
Corrections Issued 4/9/2024 LUKE GONZALES
Applicant returned to address corrections 5/9/2024 LUKE GONZALES
Plan Check Approved 6/2/2024 ZAW HAN
Issued 6/19/2024 APPLICANT
CofO in Progress 3/28/2026 JOSE AVILA
Permit Finaled 4/2/2026 RUBEN SALAS
CofO Issued 4/2/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 4/22/2024 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 4/25/2024 BIAINA HARITUNIAN
Sewer availability Cleared 4/25/2024 BIAINA HARITUNIAN
Roof/Waste drainage to street Cleared 5/21/2024 BIAINA HARITUNIAN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 10/7/2024 Partial Approval JENNIFER RABUCHIN
Deputy Drilled-In Anchors 10/10/2024 Conditional Approval ROBERT GOLD
Footing/Foundation/Slab 10/11/2024 Approved JENNIFER RABUCHIN
ELECTRICAL-Rough 10/23/2024 Partial Inspection JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 10/24/2024 Partial Approval JENNIFER RABUCHIN
BUILDING-Rough-Frame 1/14/2025 Approved JENNIFER RABUCHIN
ELECTRICAL-Rough 1/14/2025 Corrections Issued JENNIFER RABUCHIN
Green Building Rough 1/14/2025 Not Ready for Inspection JENNIFER RABUCHIN
HVAC-Rough 1/14/2025 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Rough 1/14/2025 Approved JENNIFER RABUCHIN
ELECTRICAL-Rough 1/30/2025 Approved JENNIFER RABUCHIN
HVAC-Rough 1/30/2025 Approved JENNIFER RABUCHIN
Insulation 3/13/2025 Corrections Issued DAVID ANDERSON
Interior/Exterior Lathing 3/13/2025 Partial Approval DAVID ANDERSON
Insulation 4/4/2025 Approved JENNIFER RABUCHIN
Drywall Nailing 4/11/2025 Approved JENNIFER RABUCHIN
Green Building Rough 4/11/2025 Approved JENNIFER RABUCHIN
Shower Pan 4/23/2025 Corrections Issued KEVIN BERBERYAN
Shower Pan 4/29/2025 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 5/21/2025 Approved JENNIFER RABUCHIN
Sewer 5/29/2025 Approved JENNIFER RABUCHIN
Underground Mechanical 5/29/2025 Partial Approval JENNIFER RABUCHIN
ELECTRICAL-Rough 6/16/2025 Corrections Issued JENNIFER RABUCHIN
ELECTRICAL-Rough 6/26/2025 Partial Approval JENNIFER RABUCHIN
Final 12/1/2025 Corrections Issued KEVIN BERBERYAN
Green Building Final 12/1/2025 Approved KEVIN BERBERYAN
SGSOV-Seismic Gas S/O Valve 12/1/2025 SGSOV Approved KEVIN BERBERYAN
Smoke Detectors 12/1/2025 Not Ready for Inspection KEVIN BERBERYAN
Final 12/9/2025 Corrections Issued JENNIFER RABUCHIN
Smoke Detectors 12/9/2025 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 12/30/2025 Corrections Issued JENNIFER RABUCHIN
ELECTRICAL-Final 1/15/2026 Approved JENNIFER RABUCHIN
Service/Power Release 1/15/2026 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 2/17/2026 Approved JENNIFER RABUCHIN
Final 3/6/2026 OK to Issue CofO JENNIFER RABUCHIN