7734-7736 N ETIWANDA AVE 91335
Certificate Information: 7734-7736 N ETIWANDA AVE 91335
- Application / Permit
- 24014-20000-01346
- Plan Check / Job No.
- B24VN04413
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- Convert existing 20' x 18' garage and addition of 8' 6" x 20' 4" to new single family dwellingper SB9 Two-Unit Development Ca Govt Code 65852.21creating new Duplex, NFPA 13D sprinkler required through out. All work done per engineer.
- Permit Issued
- Issued on 4/22/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 11/22/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/3/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 4/4/2024 | NAREG ATARIAN |
| Corrections Issued | 4/7/2024 | NAREG ATARIAN |
| Quality Review Completed | 4/8/2024 | OMID HEDAYAT |
| Building Plans Picked Up | 4/10/2024 | APPLICANT |
| Plan Check Approved | 4/22/2024 | NAREG ATARIAN |
| Issued | 4/22/2024 | APPLICANT |
| CofO in Progress | 11/15/2024 | ARUTYUN MADATYAN |
| CofO Issued | 11/22/2024 | JOHN JANSON |
| Permit Finaled | 11/22/2024 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 4/9/2024 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 4/9/2024 | LEE GUILBEAUX |
| Roof/Waste drainage to street | Cleared | 4/9/2024 | LEE GUILBEAUX |
| Sewer availability | Cleared | 4/9/2024 | LEE GUILBEAUX |
| Senate Bill 9 | Cleared | 4/11/2024 | BRENNEN OBETO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Mejia,, Fernando Finuliar; Lic. No.: C54382 | 8305 DUCOR AVE WEST HILLS, CA 91304 |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 5/20/2024 | Partial Approval | JEFFREY BULL |
| Deputy Drilled-In Anchors | 5/28/2024 | Conditional Approval | JEFFREY BULL |
| Footing/Foundation/Slab | 5/29/2024 | Approved | JEFFREY BULL |
| ELECTRICAL-Rough | 7/5/2024 | Approved | JEFFREY BULL |
| Floor/Roof Diaphrgm/Shear Wall | 7/5/2024 | Approved | JEFFREY BULL |
| HVAC-Rough | 7/5/2024 | Approved | JEFFREY BULL |
| PLUMBING-Rough | 7/5/2024 | Approved | JEFFREY BULL |
| Wood Frame | 7/5/2024 | Not Ready for Inspection | JEFFREY BULL |
| BUILDING-Rough-Frame | 7/9/2024 | Not Ready for Inspection | JEFFREY BULL |
| Green Building Rough | 7/9/2024 | Not Ready for Inspection | JEFFREY BULL |
| Insulation | 7/9/2024 | Partial Approval | JEFFREY BULL |
| Wood Frame | 7/9/2024 | Approved | JEFFREY BULL |
| Interior/Exterior Lathing | 7/18/2024 | Partial Approval | JEFFREY BULL |
| Insulation | 7/23/2024 | Approved | JEFFREY BULL |
| Drywall Nailing | 7/31/2024 | Approved | JEFFREY BULL |
| Green Building Rough | 7/31/2024 | Approved | JEFFREY BULL |
| Shower Pan | 7/31/2024 | Approved | JEFFREY BULL |
| BUILDING-Rough-Frame | 10/23/2024 | Approved | JEFFREY BULL |
| Final | 10/23/2024 | Corrections Issued | JEFFREY BULL |
| Green Building Final | 10/23/2024 | Approved | JEFFREY BULL |
| SGSOV-Seismic Gas S/O Valve | 10/23/2024 | SGSOV Approved | JEFFREY BULL |
| Smoke Detectors | 10/23/2024 | Approved | JEFFREY BULL |
| Final | 11/12/2024 | Not Ready for Inspection | ARUTYUN MADATYAN |
| ELECTRICAL-Final | 11/15/2024 | Approved | ARUTYUN MADATYAN |
| Final | 11/15/2024 | OK to Issue CofO | ARUTYUN MADATYAN |
| HVAC-Final | 11/15/2024 | Approved | ARUTYUN MADATYAN |
| PLUMBING-Final | 11/15/2024 | Approved | ARUTYUN MADATYAN |
| Service/Power Release | 11/15/2024 | Approved | ARUTYUN MADATYAN |