7734-7736 N ETIWANDA AVE 91335

Certificate Information: 7734-7736 N ETIWANDA AVE 91335

Application / Permit
24014-20000-01346
Plan Check / Job No.
B24VN04413
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
Convert existing 20' x 18' garage and addition of 8' 6" x 20' 4" to new single family dwellingper SB9 Two-Unit Development Ca Govt Code 65852.21creating new Duplex, NFPA 13D sprinkler required through out. All work done per engineer.
Permit Issued
Issued on 4/22/2024
Issuing Office
Valley
Current Status
CofO Issued on 11/22/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/3/2024 APPLICANT
Assigned to Plan Check Engineer 4/4/2024 NAREG ATARIAN
Corrections Issued 4/7/2024 NAREG ATARIAN
Quality Review Completed 4/8/2024 OMID HEDAYAT
Building Plans Picked Up 4/10/2024 APPLICANT
Plan Check Approved 4/22/2024 NAREG ATARIAN
Issued 4/22/2024 APPLICANT
CofO in Progress 11/15/2024 ARUTYUN MADATYAN
CofO Issued 11/22/2024 JOHN JANSON
Permit Finaled 11/22/2024 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 4/9/2024 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 4/9/2024 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 4/9/2024 LEE GUILBEAUX
Sewer availability Cleared 4/9/2024 LEE GUILBEAUX
Senate Bill 9 Cleared 4/11/2024 BRENNEN OBETO

Contact Information

Contractor Owner-Builder       ,
Engineer Mejia,, Fernando Finuliar; Lic. No.: C54382 8305 DUCOR AVE      WEST HILLS, CA 91304

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 5/20/2024 Partial Approval JEFFREY BULL
Deputy Drilled-In Anchors 5/28/2024 Conditional Approval JEFFREY BULL
Footing/Foundation/Slab 5/29/2024 Approved JEFFREY BULL
ELECTRICAL-Rough 7/5/2024 Approved JEFFREY BULL
Floor/Roof Diaphrgm/Shear Wall 7/5/2024 Approved JEFFREY BULL
HVAC-Rough 7/5/2024 Approved JEFFREY BULL
PLUMBING-Rough 7/5/2024 Approved JEFFREY BULL
Wood Frame 7/5/2024 Not Ready for Inspection JEFFREY BULL
BUILDING-Rough-Frame 7/9/2024 Not Ready for Inspection JEFFREY BULL
Green Building Rough 7/9/2024 Not Ready for Inspection JEFFREY BULL
Insulation 7/9/2024 Partial Approval JEFFREY BULL
Wood Frame 7/9/2024 Approved JEFFREY BULL
Interior/Exterior Lathing 7/18/2024 Partial Approval JEFFREY BULL
Insulation 7/23/2024 Approved JEFFREY BULL
Drywall Nailing 7/31/2024 Approved JEFFREY BULL
Green Building Rough 7/31/2024 Approved JEFFREY BULL
Shower Pan 7/31/2024 Approved JEFFREY BULL
BUILDING-Rough-Frame 10/23/2024 Approved JEFFREY BULL
Final 10/23/2024 Corrections Issued JEFFREY BULL
Green Building Final 10/23/2024 Approved JEFFREY BULL
SGSOV-Seismic Gas S/O Valve 10/23/2024 SGSOV Approved JEFFREY BULL
Smoke Detectors 10/23/2024 Approved JEFFREY BULL
Final 11/12/2024 Not Ready for Inspection ARUTYUN MADATYAN
ELECTRICAL-Final 11/15/2024 Approved ARUTYUN MADATYAN
Final 11/15/2024 OK to Issue CofO ARUTYUN MADATYAN
HVAC-Final 11/15/2024 Approved ARUTYUN MADATYAN
PLUMBING-Final 11/15/2024 Approved ARUTYUN MADATYAN
Service/Power Release 11/15/2024 Approved ARUTYUN MADATYAN