18616 W NORDHOFF ST 91324

Certificate Information: 18616 W NORDHOFF ST 91324

Application / Permit
24014-20000-01341
Plan Check / Job No.
B24VN04403
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
14'-5 1/8" X 7'-0" ADDITION TO (E) SFD.
Permit Issued
Issued on 6/11/2024
Issuing Office
Valley
Current Status
Issued on 6/11/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 4/3/2024 APPLICANT
Assigned to Plan Check Engineer 4/8/2024 ARTIN ZARUKIAN
Corrections Issued 4/8/2024 ARTIN ZARUKIAN
Building Plans Picked Up 5/21/2024 APPLICANT
Plan Check Approved 6/11/2024 ALEC MOUSAKHANIAN
Issued 6/11/2024 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 6/7/2024 CARLOS RAMIREZ
Roof/Waste drainage to street Cleared 6/7/2024 CARLOS RAMIREZ

Contact Information

Contractor Zhao Construction; Lic. No.: 1095386-B 3633 JADE COURT      WEST COVINA, CA 91792
Engineer Wong,, George Voon; Lic. No.: C49894 516 N MOORE AVE E      MONTEREY PARK, CA 91754

Inspector Information

JACK KARGODORIAN, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI
KRISTEN CAUSEY, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 7/11/2024 Approved KRISTEN CAUSEY
Green Building Rough 7/16/2024 Not Ready for Inspection KRISTEN CAUSEY
Excavation/Setback/Form/Re-Bar 7/18/2024 Approved DAVID SCANTLIN
BUILDING-Rough-Frame 8/15/2024 Not Ready for Inspection DAVID SCANTLIN
ELECTRICAL-Rough 8/15/2024 Approved DAVID SCANTLIN
Floor/Roof Diaphrgm/Shear Wall 8/15/2024 Approved DAVID SCANTLIN
Green Building Rough 8/15/2024 Not Ready for Inspection DAVID SCANTLIN
HVAC-Rough 8/15/2024 Approved DAVID SCANTLIN
PLUMBING-Rough 8/15/2024 Approved DAVID SCANTLIN
Sewer 8/15/2024 Approved DAVID SCANTLIN
Wood Frame 8/15/2024 Not Ready for Inspection DAVID SCANTLIN
Insulation 8/20/2024 No Access for Inspection KRISTEN CAUSEY
BUILDING-Rough-Frame 8/21/2024 Approved KRISTEN CAUSEY
Green Building Rough 8/21/2024 Approved KRISTEN CAUSEY
Insulation 8/21/2024 Approved KRISTEN CAUSEY
Drywall Nailing 8/29/2024 Approved KRISTEN CAUSEY
Interior/Exterior Lathing 8/29/2024 Approved KRISTEN CAUSEY
Shower Pan 8/29/2024 Approved KRISTEN CAUSEY
Underground Mechanical 9/23/2024 Approved KRISTEN CAUSEY
Smoke Detectors 10/2/2024 Not Ready for Inspection KRISTEN CAUSEY
Footing/Foundation/Slab 10/10/2024 Approved KRISTEN CAUSEY
Green Building Final 10/10/2024 Approved KRISTEN CAUSEY
Smoke Detectors 10/10/2024 Approved KRISTEN CAUSEY
Service/Power Release 11/5/2024 Approved KRISTEN CAUSEY