23732 W LADRILLO ST 91367

Certificate Information: 23732 W LADRILLO ST 91367

Application / Permit
24014-20000-01325
Plan Check / Job No.
B24VN04366
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION OF 36'-8" x 17'-0" TO CREATE NEW BEDROOM, AND 8'-0" x 36'-6" TRELLIS ADDITION AND REMODEL THROUGHOUT (E) SFD W/ ATTACHED GARAGE.
Permit Issued
Issued on 4/22/2024
Issuing Office
Valley
Current Status
CofO Issued on 9/16/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/3/2024 APPLICANT
Assigned to Plan Check Engineer 4/8/2024 JEROME MAGAT PALMA
Corrections Issued 4/10/2024 JEROME MAGAT PALMA
Building Plans Picked Up 4/15/2024 APPLICANT
Issued 4/22/2024 APPLICANT
CofO in Progress 9/12/2024 GEVORK IPCHYAN
Permit Finaled 9/16/2024 DANIEL ORRANTE
CofO Issued 9/16/2024 DANIEL ORRANTE
Permit Finaled 9/16/2024 DANIEL ORRANTE

Permit Application Clearance Information

GPI Written Notices Cleared 4/10/2024 JEROME MAGAT PALMA
Grading Pre-Inspection Cleared 4/10/2024 JEROME MAGAT PALMA
Eng Process Fee Ord 176,300 Cleared 4/11/2024 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 4/11/2024 CARLOS AGUILERA
Sewer availability Cleared 4/11/2024 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Standley,, Craig Erick; Lic. No.: C87675 60 VIA CARATAMA      SAN CLEMENTE, CA 92673

Inspector Information

GEVORK IPCHYAN, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI
TROY SANDERS, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 4/24/2024 Not Ready for Inspection GEVORK IPCHYAN
Footing/Foundation/Slab 4/24/2024 Not Ready for Inspection GEVORK IPCHYAN
Sewer 4/24/2024 Corrections Issued GEVORK IPCHYAN
Sewer 4/25/2024 Approved GEVORK IPCHYAN
Footing/Foundation/Slab 4/30/2024 Corrections Issued GEVORK IPCHYAN
Footing/Foundation/Slab 5/3/2024 Approved GEVORK IPCHYAN
BUILDING-Rough-Frame 5/22/2024 Partial Approval TROY SANDERS
Floor/Roof Diaphrgm/Shear Wall 5/22/2024 Partial Approval TROY SANDERS
BUILDING-Rough-Frame 5/23/2024 Partial Approval GEVORK IPCHYAN
Green Building Rough 5/23/2024 Not Ready for Inspection GEVORK IPCHYAN
PLUMBING-Rough 5/23/2024 Partial Approval GEVORK IPCHYAN
ELECTRICAL-Rough 6/3/2024 Approved GEVORK IPCHYAN
HVAC-Rough 6/3/2024 Approved GEVORK IPCHYAN
PLUMBING-Rough 6/3/2024 Approved GEVORK IPCHYAN
Rough-Elec/Plmb/HVAC 6/3/2024 Approved GEVORK IPCHYAN
Shower Pan 6/3/2024 Approved GEVORK IPCHYAN
Interior/Exterior Lathing 6/6/2024 Partial Approval ARUTYUN MADATYAN
Insulation 6/7/2024 Approved ARUTYUN MADATYAN
Drywall Nailing 6/14/2024 Approved GEVORK IPCHYAN
BUILDING-Rough-Frame 9/6/2024 Approved GEVORK IPCHYAN
Final 9/6/2024 Not Ready for Inspection GEVORK IPCHYAN
Green Building Final 9/6/2024 Not Ready for Inspection GEVORK IPCHYAN
Green Building Rough 9/6/2024 Approved GEVORK IPCHYAN
SGSOV-Seismic Gas S/O Valve 9/6/2024 SGSOV Approved GEVORK IPCHYAN
Smoke Detectors 9/6/2024 Approved GEVORK IPCHYAN
ELECTRICAL-Final 9/11/2024 Approved GEVORK IPCHYAN
Final 9/11/2024 OK to Issue CofO GEVORK IPCHYAN
Green Building Final 9/11/2024 Approved GEVORK IPCHYAN
HVAC-Final 9/11/2024 Approved GEVORK IPCHYAN
PLUMBING-Final 9/11/2024 Approved GEVORK IPCHYAN
Service/Power Release 9/11/2024 Approved GEVORK IPCHYAN