23732 W LADRILLO ST 91367
Certificate Information: 23732 W LADRILLO ST 91367
- Application / Permit
- 24014-20000-01325
- Plan Check / Job No.
- B24VN04366
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION OF 36'-8" x 17'-0" TO CREATE NEW BEDROOM, AND 8'-0" x 36'-6" TRELLIS ADDITION AND REMODEL THROUGHOUT (E) SFD W/ ATTACHED GARAGE.
- Permit Issued
- Issued on 4/22/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 9/16/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/3/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 4/8/2024 | JEROME MAGAT PALMA |
| Corrections Issued | 4/10/2024 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 4/15/2024 | APPLICANT |
| Issued | 4/22/2024 | APPLICANT |
| CofO in Progress | 9/12/2024 | GEVORK IPCHYAN |
| Permit Finaled | 9/16/2024 | DANIEL ORRANTE |
| CofO Issued | 9/16/2024 | DANIEL ORRANTE |
| Permit Finaled | 9/16/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| GPI Written Notices | Cleared | 4/10/2024 | JEROME MAGAT PALMA |
| Grading Pre-Inspection | Cleared | 4/10/2024 | JEROME MAGAT PALMA |
| Eng Process Fee Ord 176,300 | Cleared | 4/11/2024 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 4/11/2024 | CARLOS AGUILERA |
| Sewer availability | Cleared | 4/11/2024 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Standley,, Craig Erick; Lic. No.: C87675 | 60 VIA CARATAMA SAN CLEMENTE, CA 92673 |
Inspector Information
| GEVORK IPCHYAN, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
| TROY SANDERS, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/24/2024 | Not Ready for Inspection | GEVORK IPCHYAN |
| Footing/Foundation/Slab | 4/24/2024 | Not Ready for Inspection | GEVORK IPCHYAN |
| Sewer | 4/24/2024 | Corrections Issued | GEVORK IPCHYAN |
| Sewer | 4/25/2024 | Approved | GEVORK IPCHYAN |
| Footing/Foundation/Slab | 4/30/2024 | Corrections Issued | GEVORK IPCHYAN |
| Footing/Foundation/Slab | 5/3/2024 | Approved | GEVORK IPCHYAN |
| BUILDING-Rough-Frame | 5/22/2024 | Partial Approval | TROY SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 5/22/2024 | Partial Approval | TROY SANDERS |
| BUILDING-Rough-Frame | 5/23/2024 | Partial Approval | GEVORK IPCHYAN |
| Green Building Rough | 5/23/2024 | Not Ready for Inspection | GEVORK IPCHYAN |
| PLUMBING-Rough | 5/23/2024 | Partial Approval | GEVORK IPCHYAN |
| ELECTRICAL-Rough | 6/3/2024 | Approved | GEVORK IPCHYAN |
| HVAC-Rough | 6/3/2024 | Approved | GEVORK IPCHYAN |
| PLUMBING-Rough | 6/3/2024 | Approved | GEVORK IPCHYAN |
| Rough-Elec/Plmb/HVAC | 6/3/2024 | Approved | GEVORK IPCHYAN |
| Shower Pan | 6/3/2024 | Approved | GEVORK IPCHYAN |
| Interior/Exterior Lathing | 6/6/2024 | Partial Approval | ARUTYUN MADATYAN |
| Insulation | 6/7/2024 | Approved | ARUTYUN MADATYAN |
| Drywall Nailing | 6/14/2024 | Approved | GEVORK IPCHYAN |
| BUILDING-Rough-Frame | 9/6/2024 | Approved | GEVORK IPCHYAN |
| Final | 9/6/2024 | Not Ready for Inspection | GEVORK IPCHYAN |
| Green Building Final | 9/6/2024 | Not Ready for Inspection | GEVORK IPCHYAN |
| Green Building Rough | 9/6/2024 | Approved | GEVORK IPCHYAN |
| SGSOV-Seismic Gas S/O Valve | 9/6/2024 | SGSOV Approved | GEVORK IPCHYAN |
| Smoke Detectors | 9/6/2024 | Approved | GEVORK IPCHYAN |
| ELECTRICAL-Final | 9/11/2024 | Approved | GEVORK IPCHYAN |
| Final | 9/11/2024 | OK to Issue CofO | GEVORK IPCHYAN |
| Green Building Final | 9/11/2024 | Approved | GEVORK IPCHYAN |
| HVAC-Final | 9/11/2024 | Approved | GEVORK IPCHYAN |
| PLUMBING-Final | 9/11/2024 | Approved | GEVORK IPCHYAN |
| Service/Power Release | 9/11/2024 | Approved | GEVORK IPCHYAN |