10512 W COLEBROOK ST 91040

Certificate Information: 10512 W COLEBROOK ST 91040

Application / Permit
24014-20000-01295
Plan Check / Job No.
B24VN04306
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION TO EX. SFD FOR NEW ENTRANCE AND PORCH. EXPAND DINING ROOM AND OPEN LATTICE ROOF TRELLIS PATIO COVER.
Permit Issued
Issued on 5/21/2025
Issuing Office
Valley
Current Status
CofO Issued on 2/12/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/2/2024 APPLICANT
Assigned to Plan Check Engineer 4/5/2024 ARTIN ZARUKIAN
Corrections Issued 4/6/2024 ARTIN ZARUKIAN
Building Plans Picked Up 4/9/2024 APPLICANT
Applicant returned to address corrections 4/23/2024 GIOVANNY CHAVEZ
Plan Check Approved 5/21/2025 ROSENDO MEDINA
Issued 5/21/2025 APPLICANT
CofO in Progress 1/26/2026 VINCENT HANLEY
Permit Finaled 2/12/2026 RUBEN SALAS
CofO Issued 2/12/2026 RUBEN SALAS
Permit Finaled 2/12/2026 RUBEN SALAS

Permit Application Clearance Information

Grading Pre-Inspection Cleared 6/26/2024 CHARLES POWELL
Roof/Waste drainage to street Cleared 7/5/2024 EDGAR ALCARAZ
Eng Process Fee Ord 176,300 Cleared 7/9/2024 EDGAR ALCARAZ
Specific Plan Cleared 5/20/2025 DORIAN AGUILAR

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 3625 BEVERLY RIDGE DRIVE      SHERMAN OAKS, CA 91423

Inspector Information

DAVID ANDERSON, (818) 374-1168 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 6/27/2025 Corrections Issued DAVID ANDERSON
Footing/Foundation/Slab 6/27/2025 Partial Approval DAVID ANDERSON
Footing/Foundation/Slab 8/27/2025 Approved DAVID ANDERSON
Deputy Wood Construction 10/21/2025 Conditional Approval JOAQUIN GREENOUGH
Floor/Roof Diaphrgm/Shear Wall 10/22/2025 Approved DAVID ANDERSON
Green Building Rough 10/22/2025 Not Ready for Inspection DAVID ANDERSON
BUILDING-Rough-Frame 11/3/2025 Approved DAVID ANDERSON
ELECTRICAL-Rough 11/3/2025 Approved DAVID ANDERSON
Green Building Rough 11/3/2025 Approved DAVID ANDERSON
Insulation 11/7/2025 Approved DAVID ANDERSON
Interior/Exterior Lathing 11/7/2025 Approved DAVID ANDERSON
Drywall Nailing 11/13/2025 Approved LOUIS ESCOTO
Final 1/9/2026 Corrections Issued VINCENT HANLEY
Green Building Final 1/9/2026 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 1/9/2026 SGSOV Approved VINCENT HANLEY
Smoke Detectors 1/9/2026 Approved VINCENT HANLEY
ELECTRICAL-Final 1/23/2026 Approved VINCENT HANLEY
Final 1/23/2026 OK to Issue CofO VINCENT HANLEY
HVAC-Final 1/23/2026 Approved VINCENT HANLEY
PLUMBING-Final 1/23/2026 Approved VINCENT HANLEY