1549 S WESTGATE AVE 1-9 90025

Certificate Information: 1549 S WESTGATE AVE 1-9 90025

Application / Permit
24014-20000-01289
Plan Check / Job No.
B24VN04294
Group
Building
Type
Bldg-Addition
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
ADDITION OF (2) ATTACHED REC ROOMS ON 2ND FLOOR ABOVE (E) CARPORT ALL WORK PER ENGINEERING
Permit Issued
Issued on 6/24/2025
Issuing Office
South Los Angeles
Current Status
CofO Issued on 5/1/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/2/2024 APPLICANT
Assigned to Plan Check Engineer 4/4/2024 SEWADA ZADOORIAN MILAGARDI
Assigned to Zoning Architect 4/4/2024 NEVRIK NAVASARTIAN
Corrections Issued 4/11/2024 SEWADA ZADOORIAN MILAGARDI
Quality Review Completed 4/11/2024 STEVEN KIM
Building Plans Picked Up 4/12/2024 APPLICANT
Green Plans Picked Up 4/12/2024 APPLICANT
Plan Check Approved 12/2/2024 SEWADA ZADOORAN MILAGARDI
Issued 6/24/2025 APPLICANT
CofO in Progress 4/28/2026 CASIMIR BRITTON
Permit Finaled 5/1/2026 VASIL MIHALEV
CofO Issued 5/1/2026 VASIL MIHALEV
Permit Finaled 5/1/2026 VASIL MIHALEV

Permit Application Clearance Information

"Q" conditions Cleared 4/17/2024 ALEX VELA
CPC Cleared 4/17/2024 ALEX VELA
ZI Cleared 4/17/2024 ALEX VELA
Specific Plan Cleared 4/29/2024 MOHAMMAD HASAN
Eng Process Fee Ord 176,300 Cleared 9/13/2024 KIMBERLY HERNANDEZ
Highway dedication Cleared 9/13/2024 KIMBERLY HERNANDEZ
Roof/Waste drainage to street Cleared 11/12/2024 VLADIMIR ARUTYUNYAN
Tenant Habitability Plan Cleared 11/12/2024 HUGO GARRIDO GARZA
Green Code Cleared 11/13/2024 MICHAEL AYERS

Contact Information

Architect Nigosian,, Michael Nickolas; Lic. No.: C35308 75-572 PAINTED DESERT DRIVE      INDIAN WELLS, CA 92210
Contractor Sergio'S & Ivan General Construction Inc; Lic. No.: 985967-B 4318 S HARVARD BLVD      LOS ANGELES, CA 90062

Inspector Information

CASIMIR BRITTON, (310) 914-3913 Office Hours: 7:00-8:00 AM MON-FRI
SHAVONNE ESPINOZA, (310) 914-3913 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/18/2025 Corrections Issued CASIMIR BRITTON
Footing/Foundation/Slab 7/29/2025 Partial Approval CASIMIR BRITTON
Footing/Foundation/Slab 8/20/2025 Approved CASIMIR BRITTON
Green Building Rough 11/21/2025 Not Ready for Inspection CASIMIR BRITTON
Wood Frame 11/21/2025 Corrections Issued CASIMIR BRITTON
Green Building Rough 12/1/2025 Not Ready for Inspection CASIMIR BRITTON
Wood Frame 12/1/2025 Not Ready for Inspection CASIMIR BRITTON
Green Building Rough 12/5/2025 Approved CASIMIR BRITTON
Wood Frame 12/5/2025 Conditional Approval CASIMIR BRITTON
Pre-Inspection 12/15/2025 Partial Inspection CASIMIR BRITTON
Interior/Exterior Lathing 12/22/2025 Partial Approval PAUL DAVIDSON
Insulation 12/24/2025 Approved DANIEL VARNUM
Drywall Nailing 12/31/2025 Corrections Issued CASIMIR BRITTON
Floor/Roof Diaphrgm/Shear Wall 12/31/2025 Conditional Approval CASIMIR BRITTON
Floor/Roof Diaphrgm/Shear Wall 1/6/2026 Approved CASIMIR BRITTON
Interior/Exterior Lathing 1/12/2026 Approved CASIMIR BRITTON
Interior/Exterior Lathing 1/12/2026 Partial Inspection ROGELIO REYNA
Drywall Nailing 3/16/2026 Not Ready for Inspection CASIMIR BRITTON
Final 3/16/2026 Not Ready for Inspection CASIMIR BRITTON
Green Building Final 3/16/2026 Approved CASIMIR BRITTON
SGSOV-Seismic Gas S/O Valve 3/16/2026 SGSOV Approved CASIMIR BRITTON
Smoke Detectors 3/16/2026 Approved CASIMIR BRITTON
Wood Frame 3/16/2026 Not Ready for Inspection CASIMIR BRITTON
Drywall Nailing 4/9/2026 Approved CASIMIR BRITTON
Final 4/9/2026 Not Ready for Inspection CASIMIR BRITTON
Wood Frame 4/9/2026 Approved CASIMIR BRITTON
Final 4/28/2026 OK to Issue CofO CASIMIR BRITTON