5445 N ENCINO AVE 91316
Certificate Information: 5445 N ENCINO AVE 91316
- Application / Permit
- 24014-20000-01198
- Plan Check / Job No.
- B24VN04062
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Interior/Exterior Remodel to existing 2-story Single Family Dwelling w/attached Garage, convert (19'-5" x 4'-9") patio cover to a trellis patio cover, 2-story (16'-7" x 15'-8") addition and a (26'-2" x 5'-4") addition to the second story with a (26'-2" x 11'-9") deck over the existing first story
- Permit Issued
- Issued on 5/14/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 7/18/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/27/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 3/28/2024 | VAHAN JIVALAGIAN |
| Corrections Issued | 3/31/2024 | VAHAN JIVALAGIAN |
| Quality Review Completed | 4/3/2024 | OMID HEDAYAT |
| Building Plans Picked Up | 4/5/2024 | APPLICANT |
| Applicant returned to address corrections | 5/6/2024 | VAHAN JIVALAGIAN |
| Plan Check Approved | 5/14/2024 | VAHAN JIVALAGIAN |
| Issued | 5/14/2024 | APPLICANT |
| CofO in Progress | 6/27/2025 | JON MCHUGH |
| Permit Finaled | 7/18/2025 | DANIEL ORRANTE |
| CofO Issued | 7/18/2025 | DANIEL ORRANTE |
| Permit Finaled | 7/18/2025 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 4/9/2024 | LEE GUILBEAUX |
| Sewer availability | Cleared | 4/9/2024 | LEE GUILBEAUX |
| Miscellaneous | Cleared | 4/10/2024 | ALEX VELA |
| ZA Case | Cleared | 4/10/2024 | ALEX VELA |
| ZA Case | Cleared | 4/10/2024 | ALEX VELA |
| Low Impact Development (LID) | Cleared | 5/9/2024 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 5/9/2024 | CARLOS AGUILERA |
Contact Information
| Contractor | G M C Construction; Lic. No.: 792508-B | 9279 KEWEN AVENUE SUN VALLEY, CA 91352 |
| Engineer | Abkarian,, Raffi; Lic. No.: C36027 | 18763 VINTAGE STREET NORTHRIDGE, CA 91324 |
| Engineer | Christiansen,, Scott; Lic. No.: C37989 | 1003 WILSHIRE BLVD 202 SANTA MONICA, CA 90401 |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/20/2024 | Corrections Issued | MORRIS JACKSON |
| Deputy Drilled-In Anchors | 5/21/2024 | Conditional Approval | JON MCHUGH |
| Footing/Foundation/Slab | 5/23/2024 | Approved | MORRIS JACKSON |
| Special/Order Compliance | 5/23/2024 | Corrections Issued | MORRIS JACKSON |
| Floor/Roof Diaphrgm/Shear Wall | 5/28/2024 | Partial Approval | JON MCHUGH |
| BUILDING-Rough-Frame | 6/17/2024 | Corrections Issued | JON MCHUGH |
| ELECTRICAL-Rough | 6/17/2024 | Corrections Issued | JON MCHUGH |
| Green Building Rough | 6/17/2024 | Not Ready for Inspection | JON MCHUGH |
| MERV13>=Rough | 6/17/2024 | Not Ready for Inspection | JON MCHUGH |
| PLUMBING-Rough | 6/17/2024 | Not Ready for Inspection | JON MCHUGH |
| HVAC-Rough | 6/21/2024 | No Access for Inspection | JON MCHUGH |
| HVAC-Rough | 6/25/2024 | Corrections Issued | JON MCHUGH |
| Deputy Steel/Welding | 7/2/2024 | Conditional Approval | JON MCHUGH |
| Deputy Wood Construction | 7/5/2024 | Conditional Approval | JON MCHUGH |
| Deputy Drilled-In Anchors | 7/9/2024 | Conditional Approval | MORRIS JACKSON |
| BUILDING-Rough-Frame | 7/15/2024 | Corrections Issued | JON MCHUGH |
| Deputy Steel/Welding | 7/15/2024 | Corrections Issued | JON MCHUGH |
| ELECTRICAL-Rough | 7/15/2024 | Not Ready for Inspection | JON MCHUGH |
| Floor/Roof Diaphrgm/Shear Wall | 7/15/2024 | Corrections Issued | JON MCHUGH |
| MERV13>=Rough | 7/15/2024 | Approved | JON MCHUGH |
| Shower Pan | 7/15/2024 | Approved | JON MCHUGH |
| ELECTRICAL-Rough | 7/18/2024 | Approved | JON MCHUGH |
| Floor/Roof Diaphrgm/Shear Wall | 7/18/2024 | Corrections Issued | JON MCHUGH |
| PLUMBING-Rough | 7/18/2024 | Corrections Issued | JON MCHUGH |
| PLUMBING-Rough | 7/22/2024 | Corrections Issued | JON MCHUGH |
| BUILDING-Rough-Frame | 7/24/2024 | Not Ready for Inspection | GEVORK IPCHYAN |
| Green Building Rough | 7/24/2024 | Approved | GEVORK IPCHYAN |
| PLUMBING-Rough | 7/24/2024 | Partial Approval | GEVORK IPCHYAN |
| BUILDING-Rough-Frame | 7/26/2024 | Corrections Issued | JON MCHUGH |
| Insulation | 7/26/2024 | Not Ready for Inspection | JON MCHUGH |
| Interior/Exterior Lathing | 7/26/2024 | Not Ready for Inspection | JON MCHUGH |
| BUILDING-Rough-Frame | 7/31/2024 | Corrections Issued | JON MCHUGH |
| HVAC-Rough | 8/7/2024 | Partial Approval | MORRIS JACKSON |
| Interior/Exterior Lathing | 8/7/2024 | Partial Approval | MORRIS JACKSON |
| PLUMBING-Rough | 8/7/2024 | Partial Approval | MORRIS JACKSON |
| Drywall Nailing | 8/19/2024 | Corrections Issued | MORRIS JACKSON |
| Interior/Exterior Lathing | 8/19/2024 | Partial Approval | MORRIS JACKSON |
| Drywall Nailing | 8/27/2024 | Not Ready for Inspection | JON MCHUGH |
| Interior/Exterior Lathing | 8/27/2024 | Approved | JON MCHUGH |
| BUILDING-Rough-Frame | 9/27/2024 | Approved | JON MCHUGH |
| Drywall Nailing | 9/27/2024 | Approved | JON MCHUGH |
| HVAC-Rough | 9/27/2024 | Approved | JON MCHUGH |
| Insulation | 9/27/2024 | Approved | JON MCHUGH |
| PLUMBING-Rough | 9/27/2024 | Approved | JON MCHUGH |
| Final | 3/20/2025 | Corrections Issued | JON MCHUGH |
| Green Building Final | 3/20/2025 | Not Ready for Inspection | JON MCHUGH |
| MERV13>=Final | 3/20/2025 | Not Ready for Inspection | JON MCHUGH |
| SGSOV-Seismic Gas S/O Valve | 3/20/2025 | SGSOV Approved | JON MCHUGH |
| Smoke Detectors | 3/20/2025 | Approved | JON MCHUGH |
| Final | 6/6/2025 | No Access for Inspection | JON MCHUGH |
| Green Building Final | 6/6/2025 | Not Ready for Inspection | JON MCHUGH |
| MERV13>=Final | 6/6/2025 | No Access for Inspection | JON MCHUGH |
| Final | 6/18/2025 | Not Ready for Inspection | JON MCHUGH |
| Green Building Final | 6/18/2025 | Approved | JON MCHUGH |
| MERV13>=Final | 6/18/2025 | Approved | JON MCHUGH |
| ELECTRICAL-Final | 6/26/2025 | Approved | JON MCHUGH |
| Final | 6/26/2025 | OK to Issue CofO | JON MCHUGH |
| HVAC-Final | 6/26/2025 | Approved | JON MCHUGH |
| PLUMBING-Final | 6/26/2025 | Approved | JON MCHUGH |