807-809 S CURSON AVE 90036

Certificate Information: 807-809 S CURSON AVE 90036

Application / Permit
24014-20000-01197
Plan Check / Job No.
B24VN04056
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
(N) ATTACHED 6'-2"X7'-4 1/2" PATIO COVER ON FIRST FLOOR WITH DECK ON SECOND FLOOR, ENLARGE (E) BALCONY BY 5'-0"X9'-7 1/2" AND INTERIOR REMODEL. **1 OF 2 TV= $50,000 BPV= $49,500
Permit Issued
Issued on 9/10/2024
Issuing Office
Valley
Current Status
CofO Issued on 9/10/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/27/2024 APPLICANT
Assigned to Plan Check Engineer 4/1/2024 JESSE ARELLANO
Corrections Issued 4/2/2024 JESSE ARELLANO
Building Plans Picked Up 4/10/2024 APPLICANT
Issued 9/10/2024 APPLICANT
CofO in Progress 9/9/2025 RONNIE MINDANAO
Permit Finaled 9/10/2025 DEROLD HAUFF
CofO Issued 9/10/2025 DEROLD HAUFF
Permit Finaled 9/10/2025 DEROLD HAUFF

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 4/24/2024 JUSTIN BICOL
Sewer availability Cleared 4/24/2024 JUSTIN BICOL
Eng Process Fee Ord 176,300 Cleared 4/29/2024 JUSTIN BICOL
HPOZ Cleared 7/11/2024 ERIK VAN BREENE

Contact Information

Contractor Los Angeles Retrofit & Construction Inc; Lic. No.: 1023060-B 18075 VENTURA BLVD STE #101      ENCINO, CA 91316

Inspector Information

RONNIE MINDANAO, (213) 202-3252 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/11/2024 Partial Approval RONNIE MINDANAO
METHANE-Barrier 12/11/2024 Approved RONNIE MINDANAO
METHANE-Subgrade 12/11/2024 Approved RONNIE MINDANAO
Wood Frame 12/20/2024 Approved RONNIE MINDANAO
PLUMBING-Rough 2/19/2025 Approved JOSE MACIAS
Sewer 2/19/2025 Approved JOSE MACIAS
ELECTRICAL-Rough 2/20/2025 Approved ENRIQUE MIRELES
HVAC-Rough 2/21/2025 Approved ENRIQUE MIRELES
Wood Frame 3/11/2025 Approved ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 3/24/2025 Approved RONNIE MINDANAO
Interior/Exterior Lathing 3/24/2025 Partial Approval RONNIE MINDANAO
Insulation 3/28/2025 Approved RONNIE MINDANAO
Floor/Roof Diaphrgm/Shear Wall 4/2/2025 Approved RONNIE MINDANAO
Special/Order Compliance 4/15/2025 No Access for Inspection RONNIE MINDANAO
Drywall Nailing 4/24/2025 Approved ALIZAH MAYAGOITIA
Interior/Exterior Lathing 4/24/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
Shower Pan 4/24/2025 Approved ALIZAH MAYAGOITIA
Interior/Exterior Lathing 4/30/2025 Approved RONNIE MINDANAO
Gas Test 8/5/2025 Approved RONNIE MINDANAO
BUILDING-Rough-Frame 8/8/2025 Approved RONNIE MINDANAO
Final 8/8/2025 Corrections Issued RONNIE MINDANAO
Footing/Foundation/Slab 8/8/2025 Approved RONNIE MINDANAO
Green Building Final 8/8/2025 Approved RONNIE MINDANAO
Green Building Rough 8/8/2025 Approved RONNIE MINDANAO
METHANE-Final 8/8/2025 Approved RONNIE MINDANAO
METHANE-Rough 8/8/2025 Approved RONNIE MINDANAO
SGSOV-Seismic Gas S/O Valve 8/8/2025 SGSOV Approved RONNIE MINDANAO
Smoke Detectors 8/8/2025 Partial Approval RONNIE MINDANAO
Final 8/28/2025 Corrections Issued RONNIE MINDANAO
Smoke Detectors 8/28/2025 Approved RONNIE MINDANAO
Final 9/4/2025 Corrections Issued RONNIE MINDANAO
Final 9/8/2025 OK to Issue CofO RONNIE MINDANAO