807-809 S CURSON AVE 90036
Certificate Information: 807-809 S CURSON AVE 90036
- Application / Permit
- 24014-20000-01197
- Plan Check / Job No.
- B24VN04056
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- (N) ATTACHED 6'-2"X7'-4 1/2" PATIO COVER ON FIRST FLOOR WITH DECK ON SECOND FLOOR, ENLARGE (E) BALCONY BY 5'-0"X9'-7 1/2" AND INTERIOR REMODEL. **1 OF 2 TV= $50,000 BPV= $49,500
- Permit Issued
- Issued on 9/10/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 9/10/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/27/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 4/1/2024 | JESSE ARELLANO |
| Corrections Issued | 4/2/2024 | JESSE ARELLANO |
| Building Plans Picked Up | 4/10/2024 | APPLICANT |
| Issued | 9/10/2024 | APPLICANT |
| CofO in Progress | 9/9/2025 | RONNIE MINDANAO |
| Permit Finaled | 9/10/2025 | DEROLD HAUFF |
| CofO Issued | 9/10/2025 | DEROLD HAUFF |
| Permit Finaled | 9/10/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 4/24/2024 | JUSTIN BICOL |
| Sewer availability | Cleared | 4/24/2024 | JUSTIN BICOL |
| Eng Process Fee Ord 176,300 | Cleared | 4/29/2024 | JUSTIN BICOL |
| HPOZ | Cleared | 7/11/2024 | ERIK VAN BREENE |
Contact Information
| Contractor | Los Angeles Retrofit & Construction Inc; Lic. No.: 1023060-B | 18075 VENTURA BLVD STE #101 ENCINO, CA 91316 |
Inspector Information
| RONNIE MINDANAO, (213) 202-3252 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/11/2024 | Partial Approval | RONNIE MINDANAO |
| METHANE-Barrier | 12/11/2024 | Approved | RONNIE MINDANAO |
| METHANE-Subgrade | 12/11/2024 | Approved | RONNIE MINDANAO |
| Wood Frame | 12/20/2024 | Approved | RONNIE MINDANAO |
| PLUMBING-Rough | 2/19/2025 | Approved | JOSE MACIAS |
| Sewer | 2/19/2025 | Approved | JOSE MACIAS |
| ELECTRICAL-Rough | 2/20/2025 | Approved | ENRIQUE MIRELES |
| HVAC-Rough | 2/21/2025 | Approved | ENRIQUE MIRELES |
| Wood Frame | 3/11/2025 | Approved | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 3/24/2025 | Approved | RONNIE MINDANAO |
| Interior/Exterior Lathing | 3/24/2025 | Partial Approval | RONNIE MINDANAO |
| Insulation | 3/28/2025 | Approved | RONNIE MINDANAO |
| Floor/Roof Diaphrgm/Shear Wall | 4/2/2025 | Approved | RONNIE MINDANAO |
| Special/Order Compliance | 4/15/2025 | No Access for Inspection | RONNIE MINDANAO |
| Drywall Nailing | 4/24/2025 | Approved | ALIZAH MAYAGOITIA |
| Interior/Exterior Lathing | 4/24/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Shower Pan | 4/24/2025 | Approved | ALIZAH MAYAGOITIA |
| Interior/Exterior Lathing | 4/30/2025 | Approved | RONNIE MINDANAO |
| Gas Test | 8/5/2025 | Approved | RONNIE MINDANAO |
| BUILDING-Rough-Frame | 8/8/2025 | Approved | RONNIE MINDANAO |
| Final | 8/8/2025 | Corrections Issued | RONNIE MINDANAO |
| Footing/Foundation/Slab | 8/8/2025 | Approved | RONNIE MINDANAO |
| Green Building Final | 8/8/2025 | Approved | RONNIE MINDANAO |
| Green Building Rough | 8/8/2025 | Approved | RONNIE MINDANAO |
| METHANE-Final | 8/8/2025 | Approved | RONNIE MINDANAO |
| METHANE-Rough | 8/8/2025 | Approved | RONNIE MINDANAO |
| SGSOV-Seismic Gas S/O Valve | 8/8/2025 | SGSOV Approved | RONNIE MINDANAO |
| Smoke Detectors | 8/8/2025 | Partial Approval | RONNIE MINDANAO |
| Final | 8/28/2025 | Corrections Issued | RONNIE MINDANAO |
| Smoke Detectors | 8/28/2025 | Approved | RONNIE MINDANAO |
| Final | 9/4/2025 | Corrections Issued | RONNIE MINDANAO |
| Final | 9/8/2025 | OK to Issue CofO | RONNIE MINDANAO |