8435 N RINCON AVE 91352

Certificate Information: 8435 N RINCON AVE 91352

Application / Permit
24014-20000-01194
Plan Check / Job No.
B24VN04051
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Eplan. NEW 18'-0" x 20'-9" PATIO COVER ADDITION TO THE (E) SINGLE FAMILY DWELLING PER ENGINEERING. INTERIOR REMODEL TO REMOVE INTERIOR WALLS IN KITCHEN AND LIVING AREA.
Permit Issued
Issued on 9/9/2024
Issuing Office
Current Status
CofO Issued on 11/14/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/27/2024 APPLICANT
Assigned to Plan Check Engineer 4/1/2024 GIOVANNY CHAVEZ
Corrections Issued 4/2/2024 GIOVANNY CHAVEZ
Applicant returned to address corrections 8/8/2024 GIOVANNY CHAVEZ
Plan Check Approved 9/5/2024 GIOVANNY CHAVEZ
Issued 9/9/2024 APPLICANT
CofO in Progress 10/8/2025 MATTHEW NELSON
CofO Issued 11/14/2025 RUBEN SALAS
Permit Finaled 11/14/2025 RUBEN SALAS

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 4/22/2024 BIAINA HARITUNIAN
Clean Up Green Up Cleared 5/28/2024 BRENNEN OBETO
Eng Process Fee Ord 176,300 Cleared 7/25/2024 BIAINA HARITUNIAN
Low Impact Development (LID) Cleared 8/7/2024 LUIS LUVANO

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 3625 BEVERLY RIDGE DRIVE      SHERMAN OAKS, CA 91423

Inspector Information

MATTHEW NELSON, (818) 374-1170 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/19/2024 Corrections Issued MATTHEW NELSON
Footing/Foundation/Slab 12/10/2024 Approved MICHEL ABAJAN
Wood Frame 12/12/2024 Corrections Issued MATTHEW NELSON
Wood Frame 12/19/2024 Corrections Issued MATTHEW NELSON
Wood Frame 12/23/2024 Approved MATTHEW NELSON
Drywall Nailing 12/27/2024 Approved CHRISTOPHER ROJAS
ELECTRICAL-Rough 12/31/2024 Approved MATTHEW NELSON
HVAC-Rough 12/31/2024 Approved MATTHEW NELSON
PLUMBING-Rough 12/31/2024 Approved MATTHEW NELSON
BUILDING-Rough-Frame 1/13/2025 Approved MATTHEW NELSON
Final 1/13/2025 Not Ready for Inspection MATTHEW NELSON
Green Building Final 1/13/2025 Not Ready for Inspection MATTHEW NELSON
Green Building Rough 1/13/2025 Approved MATTHEW NELSON
Smoke Detectors 1/13/2025 Not Ready for Inspection MATTHEW NELSON
ELECTRICAL-Final 2/14/2025 Corrections Issued MATTHEW NELSON
Final 10/7/2025 OK to Issue CofO MATTHEW NELSON
Green Building Final 10/7/2025 Approved MATTHEW NELSON
Smoke Detectors 10/7/2025 Approved MATTHEW NELSON