10859 W NETTLETON ST 91352

Certificate Information: 10859 W NETTLETON ST 91352

Application / Permit
24014-20000-01178
Plan Check / Job No.
B24VN03987
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
43'-2" X 20'-4"ADDITION TO & CONVERT (E) 366 SF GARAGE TO (N) 1190 SF ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(D) AND LAMC 12.22 A.33(c)(d) AND (g). ALL WORK PER WFPP.
Permit Issued
Issued on 5/7/2024
Issuing Office
Current Status
CofO Issued on 9/11/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/26/2024 APPLICANT
Assigned to Plan Check Engineer 3/29/2024 JESSE ARELLANO
Corrections Issued 3/29/2024 JESSE ARELLANO
Building Plans Picked Up 4/1/2024 APPLICANT
Plan Check Approved 5/6/2024 LUISANGEL VALENZUELA
Issued 5/7/2024 APPLICANT
CofO in Progress 8/15/2025 DAVID ANDERSON
Permit Finaled 9/11/2025 RUBEN SALAS
CofO Issued 9/11/2025 RUBEN SALAS
Permit Finaled 9/11/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 4/3/2024 LEE GUILBEAUX
Clean Up Green Up Cleared 4/3/2024 BRENNEN OBETO
Eng Process Fee Ord 176,300 Cleared 4/3/2024 LEE GUILBEAUX
Sewer availability Cleared 4/3/2024 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 4/3/2024 LEE GUILBEAUX
Low Impact Development (LID) Cleared 5/1/2024 ERNEST TSE
Roof/Waste drainage to street Cleared 5/1/2024 LEE GUILBEAUX

Contact Information

Contractor Owner-Builder       ,

Inspector Information

DAVID ANDERSON, (818) 374-1168 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 8/22/2024 Approved VINCENT HANLEY
Footing/Foundation/Slab 8/22/2024 Approved VINCENT HANLEY
PLUMBING-Rough 8/22/2024 Partial Approval VINCENT HANLEY
BUILDING-Rough-Frame 9/9/2024 Corrections Issued DAVID ANDERSON
Green Building Rough 9/9/2024 Not Ready for Inspection DAVID ANDERSON
MERV13>=Rough 9/9/2024 Approved DAVID ANDERSON
Interior/Exterior Lathing 1/14/2025 Partial Approval DAVID ANDERSON
ELECTRICAL-Rough 2/12/2025 Approved DAVID ANDERSON
HVAC-Rough 2/12/2025 Approved DAVID ANDERSON
PLUMBING-Rough 2/12/2025 Approved DAVID ANDERSON
Sewer 2/12/2025 Approved DAVID ANDERSON
BUILDING-Rough-Frame 2/20/2025 Corrections Issued DAVID ANDERSON
Green Building Rough 2/20/2025 Approved DAVID ANDERSON
Underground Mechanical 2/20/2025 Approved DAVID ANDERSON
BUILDING-Rough-Frame 3/10/2025 Approved DAVID ANDERSON
Wood Frame 3/10/2025 Approved DAVID ANDERSON
Insulation 3/13/2025 Approved DAVID ANDERSON
Shower Pan 4/3/2025 Approved DAVID ANDERSON
Interior/Exterior Lathing 4/16/2025 Approved DAVID ANDERSON
Drywall Nailing 8/14/2025 Approved DAVID ANDERSON
Final 8/14/2025 OK to Issue CofO DAVID ANDERSON
Green Building Final 8/14/2025 Approved DAVID ANDERSON
MERV13>=Final 8/14/2025 Approved DAVID ANDERSON
SGSOV-Seismic Gas S/O Valve 8/14/2025 SGSOV Approved DAVID ANDERSON
Smoke Detectors 8/14/2025 Approved DAVID ANDERSON