11254 W SHELDON ST 91352
Certificate Information: 11254 W SHELDON ST 91352
- Application / Permit
- 24014-20000-01173
- Plan Check / Job No.
- B24VN03966
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION TO REAR OF EXISTING SINGLE-FAMILY DWELLING WITH RE-FRAMING OF PORTION OF EXISTING ROOF
- Permit Issued
- Issued on 12/5/2024
- Issuing Office
- Current Status
- Issued on 12/5/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 3/26/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 3/29/2024 | ALEC MOUSAKHANIAN |
| Corrections Issued | 3/29/2024 | ALEC MOUSAKHANIAN |
| Applicant returned to address corrections | 4/27/2024 | ALEC MOUSAKHANIAN |
| Applicant returned to address corrections | 11/27/2024 | ALEC MOUSAKHANIAN |
| Plan Check Approved | 12/2/2024 | ALEC MOUSAKHANIAN |
| Issued | 12/5/2024 | APPLICANT |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 4/8/2024 | CARLOS RAMIREZ |
| Grading Pre-Inspection | Cleared | 5/3/2024 | CHARLES POWELL |
| Eng Process Fee Ord 176,300 | Cleared | 6/17/2024 | CARLOS RAMIREZ |
| Sewer availability | Cleared | 6/17/2024 | CARLOS RAMIREZ |
| HPOZ | Cleared | 6/20/2024 | NATHALY DE LA PAZ |
| Specific Plan | Cleared | 11/22/2024 | BRENNEN OBETO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| DAVID ANDERSON, (818) 374-1168 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/17/2025 | Corrections Issued | DAVID ANDERSON |
| BUILDING-Rough-Frame | 2/28/2025 | Not Ready for Inspection | DAVID ANDERSON |
| Floor/Roof Diaphrgm/Shear Wall | 2/28/2025 | Not Ready for Inspection | DAVID ANDERSON |
| Green Building Rough | 2/28/2025 | Not Ready for Inspection | DAVID ANDERSON |
| Green Building Rough | 4/15/2025 | Approved | DAVID ANDERSON |
| Rough-Elec/Plmb/HVAC | 4/15/2025 | Corrections Issued | DAVID ANDERSON |
| Deputy Drilled-In Anchors | 4/30/2025 | Conditional Approval | DAVID MATSON |
| BUILDING-Rough-Frame | 6/5/2025 | Approved | DAVID ANDERSON |
| Floor/Roof Diaphrgm/Shear Wall | 6/5/2025 | Approved | DAVID ANDERSON |
| Rough-Elec/Plmb/HVAC | 6/5/2025 | Approved | DAVID ANDERSON |
| Interior/Exterior Lathing | 6/17/2025 | Partial Approval | LOUIS ESCOTO |
| Interior/Exterior Lathing | 6/24/2025 | Partial Approval | DAVID ANDERSON |
| Insulation | 6/30/2025 | Approved | DAVID ANDERSON |
| Drywall Nailing | 7/3/2025 | Approved | DAVID ANDERSON |
| Interior/Exterior Lathing | 7/30/2025 | Approved | DAVID ANDERSON |
| Shower Pan | 7/30/2025 | Approved | DAVID ANDERSON |
| ELECTRICAL-Final | 11/26/2025 | Approved | DAVID ANDERSON |
| Green Building Final | 11/26/2025 | Approved | DAVID ANDERSON |
| HVAC-Final | 11/26/2025 | Approved | DAVID ANDERSON |
| PLUMBING-Final | 11/26/2025 | Approved | DAVID ANDERSON |
| Smoke Detectors | 11/26/2025 | Approved | DAVID ANDERSON |