12041 N JEANETTE PL 91344
Certificate Information: 12041 N JEANETTE PL 91344
- Application / Permit
- 24014-20000-01168
- Plan Check / Job No.
- B24VN03949
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION TO EX. SFD FOR KITCHEN/ DINING ROOM EXPANSION AND REMODEL.
- Permit Issued
- Issued on 4/9/2024
- Issuing Office
- Current Status
- CofO Issued on 3/27/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/26/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 3/29/2024 | ROSENDO MEDINA |
| Corrections Issued | 3/30/2024 | ROSENDO MEDINA |
| Plan Check Approved | 4/8/2024 | ROSENDO MEDINA |
| Issued | 4/9/2024 | APPLICANT |
| CofO in Progress | 3/19/2025 | STEVEN BACK |
| Permit Finaled | 3/27/2025 | JOHN JANSON |
| CofO Issued | 3/27/2025 | JOHN JANSON |
| Permit Finaled | 3/27/2025 | JOHN JANSON |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 4/3/2024 | CARLOS RAMIREZ |
| Roof/Waste drainage to street | Cleared | 4/3/2024 | CARLOS RAMIREZ |
| Grading Pre-Inspection | Cleared | 4/3/2024 | CHARLES POWELL |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 3625 BEVERLY RIDGE DRIVE SHERMAN OAKS, CA 91423 |
Inspector Information
| JEFFREY PARD, (818) 774-4312 | Office Hours: 7:00-8:00 AM MON-FRI |
| STEVEN BACK, (818) 774-4312 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 5/29/2024 | Partial Approval | HENRY KIM |
| Deputy Drilled-In Anchors | 5/30/2024 | Conditional Approval | STEVEN BACK |
| Excavation/Setback/Form/Re-Bar | 6/4/2024 | Approved | STEVEN BACK |
| Footing/Foundation/Slab | 6/4/2024 | Approved | STEVEN BACK |
| ELECTRICAL-Rough | 6/24/2024 | Partial Approval | DAVID SCANTLIN |
| Deputy Wood Construction | 7/8/2024 | Approved | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 7/8/2024 | Approved | STEVEN BACK |
| Green Building Rough | 7/8/2024 | Not Ready for Inspection | STEVEN BACK |
| Interior/Exterior Lathing | 8/22/2024 | Partial Approval | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 8/29/2024 | Approved | STEVEN BACK |
| ELECTRICAL-Rough | 8/29/2024 | Approved | STEVEN BACK |
| Green Building Rough | 8/29/2024 | Approved | STEVEN BACK |
| HVAC-Rough | 8/29/2024 | Approved | STEVEN BACK |
| PLUMBING-Rough | 8/29/2024 | Approved | STEVEN BACK |
| Drywall Nailing | 9/12/2024 | Approved | STEVEN BACK |
| Insulation | 9/12/2024 | Approved | STEVEN BACK |
| Final | 3/13/2025 | No Access for Inspection | STEVEN BACK |
| Green Building Final | 3/13/2025 | No Access for Inspection | STEVEN BACK |
| SGSOV-Seismic Gas S/O Valve | 3/13/2025 | SGSOV Not Ready | STEVEN BACK |
| Smoke Detectors | 3/13/2025 | No Access for Inspection | STEVEN BACK |
| ELECTRICAL-Final | 3/19/2025 | Approved | STEVEN BACK |
| Final | 3/19/2025 | OK to Issue CofO | STEVEN BACK |
| Green Building Final | 3/19/2025 | Approved | STEVEN BACK |
| HVAC-Final | 3/19/2025 | Approved | STEVEN BACK |
| PLUMBING-Final | 3/19/2025 | Approved | STEVEN BACK |
| SGSOV-Seismic Gas S/O Valve | 3/19/2025 | SGSOV Approved | STEVEN BACK |
| Smoke Detectors | 3/19/2025 | Approved | STEVEN BACK |