1587 N BUNDY DR 90049
Certificate Information: 1587 N BUNDY DR 90049
- Application / Permit
- 24014-20000-01124
- Plan Check / Job No.
- B24VN03781
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSE (N) 2ND FLOOR ADDITION TO (E) TWO STORY SFD AND REDESIGN PORTION OF (E) GROUND FLOOR TO ACCOMODATE (N) STAIR ACCESS (PER ZA-2022-6869-ZAA-HCA)_ BUILDING SHALL BE FULLY SPRINKLER THROUGH OUT WITH NFPA 13D [SEE COMMENTS].
- Permit Issued
- Issued on 3/10/2025
- Issuing Office
- Valley
- Current Status
- Issued on 3/10/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 3/21/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 4/4/2024 | DAWN MC NULTY |
| Corrections Issued | 4/23/2024 | DAWN MC NULTY |
| Quality Review Completed | 4/24/2024 | OMID HEDAYAT |
| Building Plans Picked Up | 5/6/2024 | APPLICANT |
| Applicant returned to address corrections | 5/28/2024 | DAWN MC NULTY |
| Applicant returned to address corrections | 2/11/2025 | DAWN MC NULTY |
| Applicant returned to address corrections | 2/20/2025 | DAWN MC NULTY |
| Plan Check Approved | 3/6/2025 | DAWN MC NULTY |
| Plan Check Approved | 3/6/2025 | DAWN MC NULTY |
| Issued | 3/10/2025 | APPLICANT |
Permit Application Clearance Information
| GPI Written Notices | Cleared | 4/19/2024 | DAWN MC NULTY |
| Grading Pre-Inspection | Cleared | 4/19/2024 | DAWN MC NULTY |
| Address approval | Cleared | 6/11/2024 | DIANA RENTERIA |
| BHO/Hillside ordinance | Cleared | 6/11/2024 | DIANA RENTERIA |
| BHO/Hillside ordinance | Cleared | 6/11/2024 | DIANA RENTERIA |
| BHO/Hillside ordinance | Cleared | 6/11/2024 | DIANA RENTERIA |
| BHO/Hillside ordinance | Cleared | 6/11/2024 | DIANA RENTERIA |
| BHO/Hillside ordinance | Cleared | 6/11/2024 | DIANA RENTERIA |
| Roof/Waste drainage to street | Cleared | 6/11/2024 | DIANA RENTERIA |
| Sewer availability | Cleared | 6/11/2024 | DIANA RENTERIA |
| Watercourse | Cleared | 6/11/2024 | HISASHI KOBAYAKAWA |
| Miscellaneous | Cleared | 10/11/2024 | DAVID URITA |
| Eng Process Fee Ord 176,300 | Cleared | 10/22/2024 | LIAM ODONOVAN |
| Miscellaneous | Cleared | 1/7/2025 | JOHN CONNEALLY |
| Low Impact Development (LID) | Cleared | 2/4/2025 | LUIS LUVANO |
| ZA Case | Cleared | 2/26/2025 | YINGSHI HUANG |
Contact Information
| Architect | Hoffman,, Fred; Lic. No.: C8128 | 11558 KLING STREET NORTH HOLLYWOOD, CA 91602 |
| Contractor | Addition Building & Design Inc; Lic. No.: 925471-B | 4335 VAN NUYS BLVD STE 354 SHERMAN OAKS, CA 91403 |
| Engineer | Mourad,, Daniel; Lic. No.: C83387 | 542 N FULLER AVE LOS ANGELES, CA 90036 |
| Engineer | Plouff,, Kacie; Lic. No.: L9013 | 25570 RYE CANYON RD A VALENCIA, CA 91355 |
Inspector Information
| EVAN COOPER, (310) 914-3861 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 3/11/2025 | Conditional Approval | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 3/11/2025 | Corrections Issued | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 3/18/2025 | Approved | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 4/24/2025 | Approved | CARLOS MATAMOROS |
| ELECTRICAL-Rough | 6/18/2025 | Corrections Issued | ARAM AVEDISIAN |
| HVAC-Rough | 6/18/2025 | Corrections Issued | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 6/20/2025 | Corrections Issued | ARAM AVEDISIAN |
| ELECTRICAL-Rough | 6/20/2025 | Approved | ARAM AVEDISIAN |
| HVAC-Rough | 6/20/2025 | Not Ready for Inspection | ARAM AVEDISIAN |
| PLUMBING-Rough | 6/20/2025 | Partial Approval | ARAM AVEDISIAN |
| PLUMBING-Rough | 6/25/2025 | Partial Approval | MEL KHACHATOURIAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/27/2025 | No Access for Inspection | TEMISTOCLES CAAL |
| Floor/Roof Diaphrgm/Shear Wall | 7/1/2025 | Corrections Issued | MEL KHACHATOURIAN |
| HVAC-Rough | 7/1/2025 | Corrections Issued | MEL KHACHATOURIAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/7/2025 | Approved | ARAM AVEDISIAN |
| HVAC-Rough | 7/7/2025 | Approved | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 7/7/2025 | Partial Approval | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 7/10/2025 | Conditional Approval | MEL KHACHATOURIAN |
| Green Building Rough | 7/10/2025 | Approved | MEL KHACHATOURIAN |
| Shower Pan | 7/10/2025 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Verify Sprinkler Sign Off | 7/10/2025 | Approved | MEL KHACHATOURIAN |
| Insulation | 7/14/2025 | Approved | KEVIN SARGSYAN |
| Shower Pan | 7/15/2025 | Corrections Issued | JESUS PINEDA |
| Shower Pan | 7/17/2025 | Corrections Issued | JAYLIN GRAVITTE |
| Interior/Exterior Lathing | 7/22/2025 | Approved | MEL KHACHATOURIAN |
| Shower Pan | 7/22/2025 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Drywall Nailing | 7/25/2025 | Conditional Approval | TEMISTOCLES CAAL |
| Shower Pan | 7/25/2025 | Approved | TEMISTOCLES CAAL |
| Interior/Exterior Lathing | 8/5/2025 | Corrections Issued | CARLOS MATAMOROS |
| Interior/Exterior Lathing | 8/7/2025 | Corrections Issued | CARLOS MATAMOROS |
| Interior/Exterior Lathing | 8/8/2025 | Approved | CARLOS MATAMOROS |
| Underground Mechanical | 10/1/2025 | Approved | CARLOS MATAMOROS |
| SGSOV-Seismic Gas S/O Valve | 1/30/2026 | SGSOV Not Ready | CARLOS MATAMOROS |
| BUILDING-Rough-Frame | 6/1/2026 | Approved | EVAN COOPER |
| Drywall Nailing | 6/1/2026 | Approved | EVAN COOPER |
| ELECTRICAL-Final | 6/1/2026 | Corrections Issued | EVAN COOPER |
| Final | 6/1/2026 | Corrections Issued | EVAN COOPER |
| Green Building Final | 6/1/2026 | Approved | EVAN COOPER |
| HVAC-Final | 6/1/2026 | Corrections Issued | EVAN COOPER |
| PLUMBING-Final | 6/1/2026 | Approved | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 6/1/2026 | SGSOV Approved | EVAN COOPER |
| Smoke Detectors | 6/1/2026 | Approved | EVAN COOPER |