12440 W ADDISON ST 91607
Certificate Information: 12440 W ADDISON ST 91607
- Application / Permit
- 24014-20000-01121
- Plan Check / Job No.
- B24VN03767
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION AND REMODEL TO ENLARGE KITCHEN AND ADD ONE NEW BATHROOM.
- Permit Issued
- Issued on 4/22/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 8/20/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/21/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 3/29/2024 | JEROME MAGAT PALMA |
| Corrections Issued | 3/30/2024 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 4/3/2024 | APPLICANT |
| Plan Check Approved | 4/5/2024 | KAMYAR EMAMI |
| Issued | 4/22/2024 | APPLICANT |
| CofO in Progress | 8/7/2024 | OGANES TARAKHCHYAN |
| Permit Finaled | 8/20/2024 | DANIEL ORRANTE |
| CofO Issued | 8/20/2024 | DANIEL ORRANTE |
| Permit Finaled | 8/20/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 4/2/2024 | LEE GUILBEAUX |
| Miscellaneous | Cleared | 4/2/2024 | ASHLEY RODARTE |
| Roof/Waste drainage to street | Cleared | 4/2/2024 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 4/2/2024 | LEE GUILBEAUX |
| Specific Plan | Cleared | 4/3/2024 | JOANNA MARROQUIN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Chahbaz,, Chris; Lic. No.: C95753 | 10937 COLLETT AVE GRANADA HILLS, CA 91344 |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/1/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Rough | 5/1/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Footing/Foundation/Slab | 5/3/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Rough | 5/3/2024 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| Sewer | 5/3/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 5/13/2024 | Corrections Issued | MATTHEW NELSON |
| ELECTRICAL-Rough | 5/13/2024 | Approved | MATTHEW NELSON |
| Green Building Rough | 5/13/2024 | Approved | MATTHEW NELSON |
| PLUMBING-Rough | 5/13/2024 | Corrections Issued | MATTHEW NELSON |
| PLUMBING-Rough | 5/14/2024 | Approved | OGANES TARAKHCHYAN |
| Wood Frame | 5/14/2024 | Partial Approval | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 5/20/2024 | Partial Approval | OGANES TARAKHCHYAN |
| Wood Frame | 5/20/2024 | Approved | OGANES TARAKHCHYAN |
| Insulation | 5/21/2024 | Approved | OGANES TARAKHCHYAN |
| Drywall Nailing | 5/24/2024 | Approved | LEONARD ROSS II |
| Shower Pan | 5/29/2024 | Corrections Issued | LEONARD ROSS II |
| Shower Pan | 6/1/2024 | Approved | MICHEL ABAJAN |
| Shower Pan | 6/1/2024 | Off-Hour Fees Due | |
| ELECTRICAL-Final | 7/11/2024 | Approved | OGANES TARAKHCHYAN |
| Final | 8/5/2024 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| PLUMBING-Final | 8/5/2024 | Approved | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 8/6/2024 | Approved | OGANES TARAKHCHYAN |
| Final | 8/6/2024 | OK to Issue CofO | OGANES TARAKHCHYAN |
| Green Building Final | 8/6/2024 | Approved | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 8/6/2024 | SGSOV Approved | OGANES TARAKHCHYAN |
| Smoke Detectors | 8/6/2024 | Approved | OGANES TARAKHCHYAN |