5113 E TEMPLETON ST 90032
Certificate Information: 5113 E TEMPLETON ST 90032
- Application / Permit
- 24014-20000-01120
- Plan Check / Job No.
- B24VN03766
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADDITION TO AND CONVERT DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
- Permit Issued
- Issued on 5/7/2024
- Issuing Office
- Current Status
- CofO Issued on 6/12/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/21/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 3/29/2024 | JEROME MAGAT PALMA |
| Corrections Issued | 3/30/2024 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 4/2/2024 | APPLICANT |
| Issued | 5/7/2024 | APPLICANT |
| CofO in Progress | 5/16/2025 | LILIANA PORTILLO |
| No Progress | 5/18/2025 | DEROLD HAUFF |
| CofO in Progress | 5/18/2025 | DEROLD HAUFF |
| CofO in Progress | 6/9/2025 | LILIANA PORTILLO |
| Permit Finaled | 6/12/2025 | DEROLD HAUFF |
| CofO Issued | 6/12/2025 | DEROLD HAUFF |
| Permit Finaled | 6/12/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 4/3/2024 | JESSICA OPINION |
| Roof/Waste drainage to street | Cleared | 4/3/2024 | JESSICA OPINION |
| Grading Pre-Inspection | Cleared | 4/4/2024 | MICHAEL TEMPLE |
| Eng Process Fee Ord 176,300 | Cleared | 4/8/2024 | JESSICA OPINION |
| Sewer availability | Cleared | 4/8/2024 | JESSICA OPINION |
| "D" conditions | Cleared | 5/2/2024 | DAVID URITA |
| "Q" conditions | Cleared | 5/2/2024 | DAVID URITA |
| ZI | Cleared | 5/2/2024 | DAVID URITA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/14/2024 | Corrections Issued | LILIANA PORTILLO |
| PLUMBING-Rough | 6/14/2024 | Corrections Issued | LILIANA PORTILLO |
| Underground Mechanical | 6/14/2024 | Partial Approval | LILIANA PORTILLO |
| PLUMBING-Rough | 7/12/2024 | Partial Approval | OSVALDO PARAMO |
| PLUMBING-Rough | 8/14/2024 | Corrections Issued | LILIANA PORTILLO |
| Sewer | 8/14/2024 | Approved | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 10/10/2024 | Not Ready for Inspection | LUIS CASTRO |
| ELECTRICAL-Rough | 10/10/2024 | Approved | LUIS CASTRO |
| Green Building Rough | 10/10/2024 | Not Ready for Inspection | LUIS CASTRO |
| HVAC-Rough | 10/10/2024 | Partial Approval | LUIS CASTRO |
| PLUMBING-Rough | 10/10/2024 | Partial Approval | LUIS CASTRO |
| Wood Frame | 10/10/2024 | Not Ready for Inspection | LUIS CASTRO |
| BUILDING-Rough-Frame | 4/7/2025 | Approved | ALIZAH MAYAGOITIA |
| Final | 4/7/2025 | Corrections Issued | ALIZAH MAYAGOITIA |
| Footing/Foundation/Slab | 4/7/2025 | Approved | ALIZAH MAYAGOITIA |
| Green Building Final | 4/7/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Green Building Rough | 4/7/2025 | Approved | ALIZAH MAYAGOITIA |
| SGSOV-Seismic Gas S/O Valve | 4/7/2025 | SGSOV Approved | ALIZAH MAYAGOITIA |
| Smoke Detectors | 4/7/2025 | Approved | ALIZAH MAYAGOITIA |
| Final | 5/12/2025 | OK to Issue CofO | LILIANA PORTILLO |
| Green Building Final | 5/12/2025 | Approved | LILIANA PORTILLO |
| Final | 5/15/2025 | OK to Issue CofO | LILIANA PORTILLO |