10942 W PENROSE ST 91352

Certificate Information: 10942 W PENROSE ST 91352

Application / Permit
24014-20000-01084
Plan Check / Job No.
B24VN03638
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan New Addition to Existing Single Family Dwelling per WFPP. NFPA 13D fire sprinkler system is required.
Permit Issued
Issued on 9/22/2024
Issuing Office
Current Status
CofO Issued on 2/18/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/4/2024 APPLICANT
Assigned to Plan Check Engineer 4/9/2024 JOSEPH RAFOLS
Corrections Issued 4/10/2024 JOSEPH RAFOLS
Applicant returned to address corrections 5/24/2024 NGHI SU
Plan Check Approved 5/30/2024 NGHI SU
Issued 9/22/2024 APPLICANT
CofO in Progress 1/29/2025 DAVID ANDERSON
Permit Finaled 2/18/2025 RUBEN SALAS
CofO Issued 2/18/2025 RUBEN SALAS
Permit Finaled 2/18/2025 RUBEN SALAS

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 4/13/2024 CARLOS AGUILERA
Sewer availability Cleared 4/13/2024 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 4/15/2024 CARLOS AGUILERA
ZA Case Cleared 4/16/2024 BRENNEN OBETO
ZI Cleared 4/16/2024 BRENNEN OBETO

Contact Information

Contractor Roof Replacement Inc; Lic. No.: 1063655-B       ,

Inspector Information

MATTHEW NELSON, (818) 374-1168 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 10/3/2024 Approved DAVID ANDERSON
Footing/Foundation/Slab 10/3/2024 Approved DAVID ANDERSON
Floor/Roof Diaphrgm/Shear Wall 10/9/2024 Partial Approval DAVID ANDERSON
PLUMBING-Rough 10/9/2024 Partial Approval DAVID ANDERSON
Floor/Roof Diaphrgm/Shear Wall 10/10/2024 Partial Approval DAVID ANDERSON
Insulation 10/10/2024 Partial Approval DAVID ANDERSON
BUILDING-Rough-Frame 10/30/2024 Corrections Issued DAVID ANDERSON
Floor/Roof Diaphrgm/Shear Wall 10/30/2024 Approved DAVID ANDERSON
Green Building Rough 10/30/2024 Approved DAVID ANDERSON
Rough-Elec/Plmb/HVAC 10/30/2024 Approved DAVID ANDERSON
Wood Frame 10/30/2024 Approved DAVID ANDERSON
BUILDING-Rough-Frame 11/12/2024 Corrections Issued VINCENT HANLEY
Interior/Exterior Lathing 11/12/2024 Not Ready for Inspection VINCENT HANLEY
Wood Frame 11/12/2024 Corrections Issued VINCENT HANLEY
BUILDING-Rough-Frame 11/15/2024 Approved DAVID ANDERSON
Interior/Exterior Lathing 11/15/2024 Partial Approval DAVID ANDERSON
Insulation 11/18/2024 Approved DAVID ANDERSON
Drywall Nailing 11/22/2024 Approved DAVID ANDERSON
ELECTRICAL-Final 1/2/2025 Not Ready for Inspection DAVID ANDERSON
PLUMBING-Final 1/2/2025 Not Ready for Inspection DAVID ANDERSON
ELECTRICAL-Final 1/9/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Final 1/9/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Green Building Final 1/9/2025 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
HVAC-Final 1/9/2025 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
PLUMBING-Final 1/9/2025 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
SGSOV-Seismic Gas S/O Valve 1/9/2025 SGSOV Not Ready ROBERTO PALACIOS-LOPEZ
Smoke Detectors 1/9/2025 Approved ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Final 1/15/2025 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Final 1/15/2025 Corrections Issued JENNIFER RABUCHIN
ELECTRICAL-Final 1/22/2025 Approved DAVID ANDERSON
Final 1/22/2025 Corrections Issued DAVID ANDERSON
Green Building Final 1/22/2025 Not Ready for Inspection DAVID ANDERSON
PLUMBING-Final 1/22/2025 Not Ready for Inspection DAVID ANDERSON
SGSOV-Seismic Gas S/O Valve 1/22/2025 SGSOV Approved DAVID ANDERSON
Final 1/28/2025 OK to Issue CofO DAVID ANDERSON
Gas Test 1/28/2025 Approved DAVID ANDERSON
Green Building Final 1/28/2025 Approved DAVID ANDERSON
PLUMBING-Final 1/28/2025 Approved DAVID ANDERSON