9329 N LOUISE AVE 91325
Certificate Information: 9329 N LOUISE AVE 91325
- Application / Permit
- 24014-20000-01080
- Plan Check / Job No.
- B24VN03635
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) 8'-3" X 17'-0" ADDITION TO (E) ATT GARAGE AND 10'-17'-0" OVERHANG, SEE COMMENTS
- Permit Issued
- Issued on 4/19/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 10/12/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/18/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 3/28/2024 | ARAMIK SHAHMIRZAIAN |
| Corrections Issued | 3/28/2024 | ARAMIK SHAHMIRZAIAN |
| Building Plans Picked Up | 3/29/2024 | APPLICANT |
| Applicant returned to address corrections | 4/9/2024 | HAYATO TSUCHIYA |
| Issued | 4/19/2024 | APPLICANT |
| CofO in Progress | 8/14/2024 | JAVIER RAMOS JR |
| Permit Finaled | 10/12/2024 | DANIEL ORRANTE |
| CofO Issued | 10/12/2024 | DANIEL ORRANTE |
| Permit Finaled | 10/12/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 4/3/2024 | BIAINA HARITUNIAN |
| Roof/Waste drainage to street | Cleared | 4/3/2024 | BIAINA HARITUNIAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 3625 BEVERLY RIDGE DRIVE SHERMAN OAKS, CA 91423 |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/3/2024 | Approved | JAVIER RAMOS JR |
| Deputy Drilled-In Anchors | 6/17/2024 | Conditional Approval | ROBERT GOLD |
| Footing/Foundation/Slab | 6/24/2024 | Approved | JAVIER RAMOS JR |
| PLUMBING-Rough | 6/24/2024 | Partial Approval | JAVIER RAMOS JR |
| Deputy Wood Construction | 7/23/2024 | Conditional Approval | ROBERT GOLD |
| BUILDING-Rough-Frame | 7/24/2024 | Partial Approval | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 7/24/2024 | Approved | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 7/29/2024 | Approved | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 8/12/2024 | Approved | JAVIER RAMOS JR |
| ELECTRICAL-Final | 8/12/2024 | Approved | JAVIER RAMOS JR |
| Final | 8/12/2024 | OK to Issue CofO | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 8/12/2024 | SGSOV Approved | JAVIER RAMOS JR |
| Smoke Detectors | 8/12/2024 | Approved | JAVIER RAMOS JR |