19343 W COHASSET ST 91335
Certificate Information: 19343 W COHASSET ST 91335
- Application / Permit
- 24014-20000-01073
- Plan Check / Job No.
- B24VN03591
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION TO EX. SFD. EXPAND BEDROOM AND BATHROOM. REMODEL KITCHEN, LIVING ROOM AND BATHROOM. WORK PER ENGINEER.
- Permit Issued
- Issued on 4/23/2024
- Issuing Office
- Current Status
- CofO Issued on 3/6/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/20/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 3/27/2024 | ROSENDO MEDINA |
| Corrections Issued | 4/16/2024 | ROSENDO MEDINA |
| Plan Check Approved | 4/18/2024 | PINANK PATEL |
| Issued | 4/23/2024 | APPLICANT |
| CofO in Progress | 2/24/2025 | ARUTYUN MADATYAN |
| Permit Finaled | 3/6/2025 | JOHN JANSON |
| CofO Issued | 3/6/2025 | JOHN JANSON |
| Permit Finaled | 3/6/2025 | JOHN JANSON |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 4/1/2024 | CARLOS RAMIREZ |
| Eng Process Fee Ord 176,300 | Cleared | 4/2/2024 | CARLOS RAMIREZ |
| "T" removal | Cleared | 4/15/2024 | MATHEW QUAN |
| Tract Map conditions | Cleared | 4/15/2024 | MATHEW QUAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Helou,, Dawn Renee; Lic. No.: C52361 | 22701 ERWIN ST WOODLAND HILLS, CA 91367 |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 5/28/2024 | Approved | JEFFREY BULL |
| Footing/Foundation/Slab | 5/28/2024 | Approved | JEFFREY BULL |
| BUILDING-Rough-Frame | 7/3/2024 | Partial Approval | ARUTYUN MADATYAN |
| PLUMBING-Rough | 7/3/2024 | Partial Approval | ARUTYUN MADATYAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/15/2024 | Partial Approval | JEFFREY BULL |
| Insulation | 7/15/2024 | Partial Approval | JEFFREY BULL |
| Floor/Roof Diaphrgm/Shear Wall | 8/9/2024 | Approved | JEFFREY BULL |
| ELECTRICAL-Rough | 8/23/2024 | Approved | JEFFREY BULL |
| Interior/Exterior Lathing | 8/23/2024 | Partial Approval | JEFFREY BULL |
| PLUMBING-Rough | 8/23/2024 | Approved | JEFFREY BULL |
| BUILDING-Rough-Frame | 9/11/2024 | Approved | CHRIS CHRISTENSEN |
| Green Building Rough | 9/11/2024 | Approved | CHRIS CHRISTENSEN |
| HVAC-Rough | 9/11/2024 | Approved | CHRIS CHRISTENSEN |
| Insulation | 9/11/2024 | Approved | CHRIS CHRISTENSEN |
| Interior/Exterior Lathing | 9/11/2024 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Shower Pan | 9/11/2024 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Drywall Nailing | 9/25/2024 | Approved | KRISTEN CAUSEY |
| ELECTRICAL-Rough | 10/25/2024 | Partial Approval | JEFFREY BULL |
| Final | 12/18/2024 | Corrections Issued | ARUTYUN MADATYAN |
| Green Building Final | 12/18/2024 | Not Ready for Inspection | ARUTYUN MADATYAN |
| SGSOV-Seismic Gas S/O Valve | 12/18/2024 | SGSOV Approved | ARUTYUN MADATYAN |
| Smoke Detectors | 12/18/2024 | Approved | ARUTYUN MADATYAN |
| Final | 12/30/2024 | Not Ready for Inspection | JOHN COLEMAN |
| Green Building Final | 12/30/2024 | Corrections Issued | JOHN COLEMAN |
| Final | 1/28/2025 | Corrections Issued | ARUTYUN MADATYAN |
| Green Building Final | 1/28/2025 | Approved | ARUTYUN MADATYAN |
| Final | 2/14/2025 | Not Ready for Inspection | TROY SANDERS |
| ELECTRICAL-Final | 2/21/2025 | Approved | ARUTYUN MADATYAN |
| Final | 2/21/2025 | OK to Issue CofO | ARUTYUN MADATYAN |
| HVAC-Final | 2/21/2025 | Approved | ARUTYUN MADATYAN |
| PLUMBING-Final | 2/21/2025 | Approved | ARUTYUN MADATYAN |