17032 W MOONCREST DR 91436
Certificate Information: 17032 W MOONCREST DR 91436
- Application / Permit
- 24014-20000-01071
- Plan Check / Job No.
- B24VN03588
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 23'-6" x 8'-4" ADDITION TO (E) SFD AND REMOVE THE (E) ATTACHED GARAGE AND BUILD A NEW 23'-6" x 19' ATTACHED GARAGE AND INTERIOR REMODEL OF (E) SFD. WORK DONE PER ENGINEER DESIGN.
- Permit Issued
- Issued on 5/2/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 12/16/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/18/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 3/22/2024 | JESSE ARELLANO |
| Corrections Issued | 3/28/2024 | JESSE ARELLANO |
| Building Plans Picked Up | 3/28/2024 | APPLICANT |
| Issued | 5/2/2024 | APPLICANT |
| CofO in Progress | 11/15/2024 | MORRIS JACKSON |
| Permit Finaled | 12/16/2024 | JOHN JANSON |
| CofO Issued | 12/16/2024 | JOHN JANSON |
| Permit Finaled | 12/16/2024 | JOHN JANSON |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 4/3/2024 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 4/10/2024 | BIAINA HARITUNIAN |
| GPI Written Notices | Cleared | 5/2/2024 | JESSE ARELLANO |
| Grading Pre-Inspection | Cleared | 5/2/2024 | JESSE ARELLANO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Sheppard,, Kayse Rose; Lic. No.: C95444 | 1835 OLD CANYON DR HACIENDA HEIGHTS, CA 91745 |
Inspector Information
| THOMAS FINNILA, (818) 774-4324 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 5/21/2024 | Partial Approval | JOHN KIDWELL |
| Footing/Foundation/Slab | 5/24/2024 | Corrections Issued | THOMAS FINNILA |
| Footing/Foundation/Slab | 6/4/2024 | Approved | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 6/13/2024 | Partial Approval | THOMAS FINNILA |
| BUILDING-Rough-Frame | 7/19/2024 | Corrections Issued | HENRY KIM |
| ELECTRICAL-Rough | 7/19/2024 | Corrections Issued | HENRY KIM |
| Floor/Roof Diaphrgm/Shear Wall | 7/19/2024 | Corrections Issued | HENRY KIM |
| Green Building Rough | 7/19/2024 | Not Ready for Inspection | HENRY KIM |
| HVAC-Rough | 7/19/2024 | Corrections Issued | HENRY KIM |
| PLUMBING-Rough | 7/19/2024 | Corrections Issued | HENRY KIM |
| BUILDING-Rough-Frame | 7/29/2024 | Partial Inspection | THOMAS FINNILA |
| ELECTRICAL-Rough | 7/29/2024 | Not Ready for Inspection | THOMAS FINNILA |
| Green Building Rough | 7/29/2024 | Not Ready for Inspection | THOMAS FINNILA |
| HVAC-Rough | 7/29/2024 | Not Ready for Inspection | THOMAS FINNILA |
| PLUMBING-Rough | 7/29/2024 | Partial Inspection | THOMAS FINNILA |
| Underground Mechanical | 7/29/2024 | Not Ready for Inspection | THOMAS FINNILA |
| Deputy Drilled-In Anchors | 7/31/2024 | Conditional Approval | THOMAS FINNILA |
| ELECTRICAL-Rough | 7/31/2024 | Not Ready for Inspection | THOMAS FINNILA |
| PLUMBING-Rough | 7/31/2024 | Corrections Issued | THOMAS FINNILA |
| Underground Mechanical | 7/31/2024 | Not Ready for Inspection | THOMAS FINNILA |
| BUILDING-Rough-Frame | 8/6/2024 | No Access for Inspection | THOMAS FINNILA |
| ELECTRICAL-Rough | 8/6/2024 | No Access for Inspection | THOMAS FINNILA |
| PLUMBING-Rough | 8/6/2024 | No Access for Inspection | THOMAS FINNILA |
| BUILDING-Rough-Frame | 8/9/2024 | Corrections Issued | THOMAS FINNILA |
| HVAC-Rough | 8/9/2024 | Approved | THOMAS FINNILA |
| PLUMBING-Rough | 8/9/2024 | Corrections Issued | THOMAS FINNILA |
| ELECTRICAL-Rough | 8/13/2024 | Corrections Issued | THOMAS FINNILA |
| Interior/Exterior Lathing | 8/13/2024 | Not Ready for Inspection | THOMAS FINNILA |
| BUILDING-Rough-Frame | 8/15/2024 | Approved | THOMAS FINNILA |
| Green Building Rough | 8/15/2024 | Approved | THOMAS FINNILA |
| Insulation | 8/20/2024 | Approved | THOMAS FINNILA |
| Interior/Exterior Lathing | 8/20/2024 | Partial Approval | THOMAS FINNILA |
| Shower Pan | 8/20/2024 | Approved | THOMAS FINNILA |
| Drywall Nailing | 8/26/2024 | Approved | SCOTT SOBEL |
| Interior/Exterior Lathing | 8/26/2024 | Partial Approval | SCOTT SOBEL |
| Interior/Exterior Lathing | 8/30/2024 | Approved | SCOTT SOBEL |
| ELECTRICAL-Final | 10/21/2024 | Corrections Issued | THOMAS FINNILA |
| ELECTRICAL-Final | 10/30/2024 | Corrections Issued | THOMAS FINNILA |
| HVAC-Final | 10/31/2024 | Not Ready for Inspection | MORRIS JACKSON |
| PLUMBING-Final | 10/31/2024 | Not Ready for Inspection | MORRIS JACKSON |
| ELECTRICAL-Final | 11/1/2024 | Corrections Issued | THOMAS FINNILA |
| HVAC-Final | 11/1/2024 | Corrections Issued | THOMAS FINNILA |
| PLUMBING-Final | 11/1/2024 | Corrections Issued | THOMAS FINNILA |
| ELECTRICAL-Final | 11/5/2024 | Corrections Issued | THOMAS FINNILA |
| HVAC-Final | 11/6/2024 | Corrections Issued | MORRIS JACKSON |
| PLUMBING-Final | 11/6/2024 | Not Ready for Inspection | MORRIS JACKSON |
| ELECTRICAL-Final | 11/8/2024 | Approved | MORRIS JACKSON |
| HVAC-Final | 11/8/2024 | Approved | MORRIS JACKSON |
| PLUMBING-Final | 11/8/2024 | Approved | MORRIS JACKSON |
| Final | 11/14/2024 | OK to Issue CofO | MORRIS JACKSON |
| Green Building Final | 11/14/2024 | Approved | MORRIS JACKSON |
| SGSOV-Seismic Gas S/O Valve | 11/14/2024 | SGSOV Approved | MORRIS JACKSON |
| Smoke Detectors | 11/14/2024 | Approved | MORRIS JACKSON |