12317 W HATTERAS ST 91607

Certificate Information: 12317 W HATTERAS ST 91607

Application / Permit
24014-20000-01050
Plan Check / Job No.
B24VN03503
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMOVE ENTIRE 1-STORY SINGLE FAMILY DWELLING EXCEPT FOR 5'-8" WALL AND BUILD NEW 2898 SQFT 2-STORY SINGLE FAMILY DWELLING W/ATTACHED 2-CAR GARAGE (338 SQFT) AND ATTACHED OPEN TRELLIS. W/NFPA 13D SPRINKLERS THROUGHOUT
Permit Issued
Issued on 5/21/2024
Issuing Office
Current Status
CofO Issued on 3/3/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/15/2024 APPLICANT
Assigned to Plan Check Engineer 3/21/2024 PETER MOSESIAN
Corrections Issued 3/28/2024 PETER MOSESIAN
Quality Review Completed 3/29/2024 OMID HEDAYAT
Building Plans Picked Up 4/2/2024 APPLICANT
Plan Check Approved 5/21/2024 PETER MOSESIAN
Issued 5/21/2024 APPLICANT
CofO in Progress 1/17/2025 OGANES TARAKHCHYAN
CofO Issued 3/3/2025 RUBEN SALAS
Permit Finaled 3/3/2025 RUBEN SALAS

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 4/10/2024 EDGAR ALCARAZ
Sewer availability Cleared 4/10/2024 EDGAR ALCARAZ
Trees in Parkway Cleared 4/18/2024 ADALBERTO VERA
Low Impact Development (LID) Cleared 4/26/2024 MELINEH AGHAKHABIAN
Hydrant and Access approval Cleared 5/7/2024 KURT CORRAL
Permit Cleared 5/8/2024 EDGAR ALCARAZ
Roof/Waste drainage to street Cleared 5/8/2024 EDGAR ALCARAZ

Contact Information

Contractor Owner-Builder       ,
Engineer Yuzon,, Benigno Sari; Lic. No.: S3454 2511 PEACHWOOD PLACE      WESTLAKE VILLAGE, CA 91361

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 6/6/2024 Partial Approval OGANES TARAKHCHYAN
Excavation/Setback/Form/Re-Bar 6/7/2024 Corrections Issued OGANES TARAKHCHYAN
Deputy Reinf. Concrete 6/10/2024 Conditional Approval DAVID MATSON
Excavation/Setback/Form/Re-Bar 6/11/2024 Approved OGANES TARAKHCHYAN
Footing/Foundation/Slab 6/14/2024 Not Ready for Inspection JOHN COLEMAN
Deputy Steel/Welding 6/20/2024 Conditional Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 6/25/2024 Partial Approval OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 7/8/2024 Not Ready for Inspection OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 7/15/2024 Partial Approval KEVIN BERBERYAN
HVAC-Rough 7/26/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
PLUMBING-Rough 7/26/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
PLUMBING-Rough 7/30/2024 Approved OGANES TARAKHCHYAN
ELECTRICAL-Rough 8/1/2024 Corrections Issued KEVIN BERBERYAN
HVAC-Rough 8/1/2024 Approved KEVIN BERBERYAN
Deputy Wood Construction 8/2/2024 Partial Approval OGANES TARAKHCHYAN
ELECTRICAL-Rough 8/2/2024 Corrections Issued SALVADOR MARTINEZ
HVAC-Rough 8/2/2024 Approved SALVADOR MARTINEZ
ELECTRICAL-Rough 8/5/2024 Approved OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 8/5/2024 Approved OGANES TARAKHCHYAN
Shower Pan 8/7/2024 Approved OGANES TARAKHCHYAN
Interior/Exterior Lathing 8/9/2024 Not Ready for Inspection OGANES TARAKHCHYAN
Wood Frame 8/9/2024 Not Ready for Inspection OGANES TARAKHCHYAN
BUILDING-Rough-Frame 8/12/2024 Approved OGANES TARAKHCHYAN
Green Building Rough 8/12/2024 Approved OGANES TARAKHCHYAN
Interior/Exterior Lathing 8/13/2024 Partial Approval OGANES TARAKHCHYAN
Insulation 8/15/2024 Approved MISAEL ESPARZA
Interior/Exterior Lathing 8/16/2024 Corrections Issued SALVADOR MARTINEZ
Drywall Nailing 8/19/2024 Approved JACK KARGODORIAN
Underground Mechanical 11/5/2024 Approved GAREN HAYRAPETYAN
Pre-Inspection 12/12/2024 Not Ready for Inspection OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 12/12/2024 SGSOV Not Ready OGANES TARAKHCHYAN
ELECTRICAL-Final 12/18/2024 Not Ready for Inspection OGANES TARAKHCHYAN
HVAC-Final 12/18/2024 Not Ready for Inspection OGANES TARAKHCHYAN
PLUMBING-Final 12/18/2024 Not Ready for Inspection OGANES TARAKHCHYAN
Footing/Foundation/Slab 12/19/2024 Approved OGANES TARAKHCHYAN
PLUMBING-Final 12/19/2024 Approved OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 12/19/2024 SGSOV Not Ready OGANES TARAKHCHYAN
ELECTRICAL-Final 12/20/2024 Not Ready for Inspection OGANES TARAKHCHYAN
ELECTRICAL-Final 12/23/2024 Approved OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 12/26/2024 SGSOV Not Ready OGANES TARAKHCHYAN
HVAC-Final 12/27/2024 Not Ready for Inspection OGANES TARAKHCHYAN
HVAC-Final 12/30/2024 Not Ready for Inspection OGANES TARAKHCHYAN
Green Building Final 12/31/2024 Not Ready for Inspection OGANES TARAKHCHYAN
HVAC-Final 12/31/2024 Not Ready for Inspection OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 12/31/2024 SGSOV Approved OGANES TARAKHCHYAN
Smoke Detectors 12/31/2024 Approved OGANES TARAKHCHYAN
HVAC-Final 1/3/2025 Approved OGANES TARAKHCHYAN
Final 1/8/2025 Corrections Issued GAREN HAYRAPETYAN
Green Building Final 1/8/2025 Approved GAREN HAYRAPETYAN
Final 1/16/2025 OK to Issue CofO OGANES TARAKHCHYAN
Service/Power Release 1/16/2025 Approved OGANES TARAKHCHYAN