12317 W HATTERAS ST 91607
Certificate Information: 12317 W HATTERAS ST 91607
- Application / Permit
- 24014-20000-01050
- Plan Check / Job No.
- B24VN03503
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMOVE ENTIRE 1-STORY SINGLE FAMILY DWELLING EXCEPT FOR 5'-8" WALL AND BUILD NEW 2898 SQFT 2-STORY SINGLE FAMILY DWELLING W/ATTACHED 2-CAR GARAGE (338 SQFT) AND ATTACHED OPEN TRELLIS. W/NFPA 13D SPRINKLERS THROUGHOUT
- Permit Issued
- Issued on 5/21/2024
- Issuing Office
- Current Status
- CofO Issued on 3/3/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/15/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 3/21/2024 | PETER MOSESIAN |
| Corrections Issued | 3/28/2024 | PETER MOSESIAN |
| Quality Review Completed | 3/29/2024 | OMID HEDAYAT |
| Building Plans Picked Up | 4/2/2024 | APPLICANT |
| Plan Check Approved | 5/21/2024 | PETER MOSESIAN |
| Issued | 5/21/2024 | APPLICANT |
| CofO in Progress | 1/17/2025 | OGANES TARAKHCHYAN |
| CofO Issued | 3/3/2025 | RUBEN SALAS |
| Permit Finaled | 3/3/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 4/10/2024 | EDGAR ALCARAZ |
| Sewer availability | Cleared | 4/10/2024 | EDGAR ALCARAZ |
| Trees in Parkway | Cleared | 4/18/2024 | ADALBERTO VERA |
| Low Impact Development (LID) | Cleared | 4/26/2024 | MELINEH AGHAKHABIAN |
| Hydrant and Access approval | Cleared | 5/7/2024 | KURT CORRAL |
| Permit | Cleared | 5/8/2024 | EDGAR ALCARAZ |
| Roof/Waste drainage to street | Cleared | 5/8/2024 | EDGAR ALCARAZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Yuzon,, Benigno Sari; Lic. No.: S3454 | 2511 PEACHWOOD PLACE WESTLAKE VILLAGE, CA 91361 |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 6/6/2024 | Partial Approval | OGANES TARAKHCHYAN |
| Excavation/Setback/Form/Re-Bar | 6/7/2024 | Corrections Issued | OGANES TARAKHCHYAN |
| Deputy Reinf. Concrete | 6/10/2024 | Conditional Approval | DAVID MATSON |
| Excavation/Setback/Form/Re-Bar | 6/11/2024 | Approved | OGANES TARAKHCHYAN |
| Footing/Foundation/Slab | 6/14/2024 | Not Ready for Inspection | JOHN COLEMAN |
| Deputy Steel/Welding | 6/20/2024 | Conditional Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 6/25/2024 | Partial Approval | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/8/2024 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/15/2024 | Partial Approval | KEVIN BERBERYAN |
| HVAC-Rough | 7/26/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Rough | 7/26/2024 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Rough | 7/30/2024 | Approved | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 8/1/2024 | Corrections Issued | KEVIN BERBERYAN |
| HVAC-Rough | 8/1/2024 | Approved | KEVIN BERBERYAN |
| Deputy Wood Construction | 8/2/2024 | Partial Approval | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 8/2/2024 | Corrections Issued | SALVADOR MARTINEZ |
| HVAC-Rough | 8/2/2024 | Approved | SALVADOR MARTINEZ |
| ELECTRICAL-Rough | 8/5/2024 | Approved | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/5/2024 | Approved | OGANES TARAKHCHYAN |
| Shower Pan | 8/7/2024 | Approved | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 8/9/2024 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Wood Frame | 8/9/2024 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 8/12/2024 | Approved | OGANES TARAKHCHYAN |
| Green Building Rough | 8/12/2024 | Approved | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 8/13/2024 | Partial Approval | OGANES TARAKHCHYAN |
| Insulation | 8/15/2024 | Approved | MISAEL ESPARZA |
| Interior/Exterior Lathing | 8/16/2024 | Corrections Issued | SALVADOR MARTINEZ |
| Drywall Nailing | 8/19/2024 | Approved | JACK KARGODORIAN |
| Underground Mechanical | 11/5/2024 | Approved | GAREN HAYRAPETYAN |
| Pre-Inspection | 12/12/2024 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 12/12/2024 | SGSOV Not Ready | OGANES TARAKHCHYAN |
| ELECTRICAL-Final | 12/18/2024 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| HVAC-Final | 12/18/2024 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| PLUMBING-Final | 12/18/2024 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Footing/Foundation/Slab | 12/19/2024 | Approved | OGANES TARAKHCHYAN |
| PLUMBING-Final | 12/19/2024 | Approved | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 12/19/2024 | SGSOV Not Ready | OGANES TARAKHCHYAN |
| ELECTRICAL-Final | 12/20/2024 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| ELECTRICAL-Final | 12/23/2024 | Approved | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 12/26/2024 | SGSOV Not Ready | OGANES TARAKHCHYAN |
| HVAC-Final | 12/27/2024 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| HVAC-Final | 12/30/2024 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Green Building Final | 12/31/2024 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| HVAC-Final | 12/31/2024 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 12/31/2024 | SGSOV Approved | OGANES TARAKHCHYAN |
| Smoke Detectors | 12/31/2024 | Approved | OGANES TARAKHCHYAN |
| HVAC-Final | 1/3/2025 | Approved | OGANES TARAKHCHYAN |
| Final | 1/8/2025 | Corrections Issued | GAREN HAYRAPETYAN |
| Green Building Final | 1/8/2025 | Approved | GAREN HAYRAPETYAN |
| Final | 1/16/2025 | OK to Issue CofO | OGANES TARAKHCHYAN |
| Service/Power Release | 1/16/2025 | Approved | OGANES TARAKHCHYAN |