9523 N ARLETA AVE 1-3 91331

Certificate Information: 9523 N ARLETA AVE 1-3 91331

Application / Permit
24014-20000-01047
Plan Check / Job No.
B24VN03495
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(n) 41'7" x 14' 2nd floor Accesory dweling unit addition to (e) sfd as per LAMC 12.22.A.33 (c) and (d) and convert (e) 20'2" x 17'11" attached garage and 14'7" x 10'6" irregular shaped portion of the sfd to Junior Accessory dwelling unit as per CA Govt. Code 65852.2(e)(1)(A) and 65852.229 , All work per engineering
Permit Issued
Issued on 7/25/2024
Issuing Office
Valley
Current Status
Issued on 7/25/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 3/15/2024 APPLICANT
Assigned to Plan Check Engineer 3/28/2024 RARES BODEA
Corrections Issued 4/2/2024 RARES BODEA
Quality Review Completed 4/3/2024 STEVEN KIM
Building Plans Picked Up 4/3/2024 APPLICANT
Plan Check Approved 5/13/2024 RARES BODEA
Issued 7/25/2024 APPLICANT

Permit Application Clearance Information

Address approval Cleared 4/16/2024 CARLOS AGUILERA
Certificate of Compliance Cleared 4/17/2024 BRENNEN OBETO
Tract Map conditions Cleared 4/17/2024 BRENNEN OBETO
ZA Case Cleared 4/17/2024 BRENNEN OBETO
Eng Process Fee Ord 176,300 Cleared 4/26/2024 CARLOS AGUILERA
Sewer availability Cleared 4/26/2024 CARLOS AGUILERA
Low Impact Development (LID) Cleared 5/6/2024 ERNEST TSE
Miscellaneous Cleared 5/10/2024 NELSON RODRIGUEZ
Roof/Waste drainage to street Cleared 5/10/2024 EDGAR ALCARAZ

Contact Information

Contractor Owner-Builder       ,
Engineer Mroczka,, Peter J; Lic. No.: C42648 9301 DARBY AVE APT 1      NORTHRIDGE, CA 91325

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 7/29/2024 Conditional Approval ROBERT GOLD
Footing/Foundation/Slab 7/30/2024 Corrections Issued MICHEL ABAJAN
BUILDING-Rough-Frame 8/8/2024 Partial Approval MICHEL ABAJAN
Footing/Foundation/Slab 8/8/2024 Approved MICHEL ABAJAN
PLUMBING-Rough 8/8/2024 Partial Approval MICHEL ABAJAN
Drywall Nailing 8/16/2024 Partial Approval KEVIN BERBERYAN
Floor/Roof Diaphrgm/Shear Wall 8/16/2024 Conditional Approval KEVIN BERBERYAN
Green Building Rough 8/16/2024 Not Ready for Inspection KEVIN BERBERYAN
Floor/Roof Diaphrgm/Shear Wall 9/26/2024 Corrections Issued MATTHEW NELSON
Floor/Roof Diaphrgm/Shear Wall 9/27/2024 Not Ready for Inspection MICHEL ABAJAN
Interior/Exterior Lathing 11/14/2024 Approved MICHEL ABAJAN
ELECTRICAL-Rough 3/10/2025 Not Ready for Inspection MICHEL ABAJAN
BUILDING-Rough-Frame 3/11/2025 Approved MICHEL ABAJAN
ELECTRICAL-Rough 3/11/2025 Approved MICHEL ABAJAN
Green Building Rough 3/11/2025 Approved MICHEL ABAJAN
HVAC-Rough 3/11/2025 Approved MICHEL ABAJAN
PLUMBING-Rough 3/11/2025 Approved MICHEL ABAJAN
Insulation 3/20/2025 Approved MICHEL ABAJAN
Drywall Nailing 4/17/2025 Approved MICHEL ABAJAN
ELECTRICAL-Final 4/23/2025 Not Ready for Inspection MICHEL ABAJAN
Final 4/23/2025 Corrections Issued MICHEL ABAJAN
Green Building Final 4/23/2025 Not Ready for Inspection MICHEL ABAJAN
HVAC-Final 4/23/2025 Not Ready for Inspection MICHEL ABAJAN
PLUMBING-Final 4/23/2025 Not Ready for Inspection MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 4/23/2025 SGSOV Not Ready MICHEL ABAJAN
Service/Power Release 4/23/2025 Not Ready for Inspection MICHEL ABAJAN
Smoke Detectors 4/23/2025 Not Ready for Inspection MICHEL ABAJAN