11480 W KAMLOOPS PL 91342
Certificate Information: 11480 W KAMLOOPS PL 91342
- Application / Permit
- 24014-20000-01045
- Plan Check / Job No.
- B24VN03305
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADD NEW 26' x 30'-9" ONE-STORY ACCESSORY DWELLING UNIT TO (E) DET. GARAGE [PER CA Govt. Code 65852.2(e)(1)(B) and applicable part2 of LAMC 12.22 A.33 (c)-(d), (g)]
- Permit Issued
- Issued on 5/13/2024
- Issuing Office
- Current Status
- CofO Issued on 10/9/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/12/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 3/14/2024 | SEAN SHAHMIRI |
| Corrections Issued | 3/18/2024 | SEAN SHAHMIRI |
| Quality Review Completed | 3/20/2024 | STEVEN KIM |
| Applicant returned to address corrections | 4/19/2024 | SEAN SHAHMIRI |
| Plan Check Approved | 5/9/2024 | SEAN SHAHMIRI |
| Issued | 5/13/2024 | APPLICANT |
| CofO in Progress | 9/12/2024 | MICHEL ABAJAN |
| CofO Issued | 10/9/2024 | DANIEL ORRANTE |
| Permit Finaled | 10/9/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 3/19/2024 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 3/20/2024 | BIAINA HARITUNIAN |
| Low Impact Development (LID) | Cleared | 4/19/2024 | SAMUEL LINN |
| Grading Pre-Inspection | Cleared | 5/9/2024 | SEAN SHAHMIRI |
| Eng Process Fee Ord 176,300 | Cleared | 5/10/2024 | EDGAR ALCARAZ |
| Roof/Waste drainage to street | Cleared | 5/10/2024 | BIAINA HARITUNIAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Melchor,, Oscar Elias; Lic. No.: C76828 | 21243 VENTURA BLVD SUITE 119 WOODLAND HILLS, CA 91364 |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/15/2024 | Not Ready for Inspection | MICHEL ABAJAN |
| PLUMBING-Rough | 5/15/2024 | Partial Approval | MICHEL ABAJAN |
| Deputy Drilled-In Anchors | 5/16/2024 | Conditional Approval | ROBERT GOLD |
| Footing/Foundation/Slab | 5/17/2024 | Approved | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/4/2024 | Partial Approval | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 6/17/2024 | Approved | MATTHEW NELSON |
| ELECTRICAL-Rough | 6/17/2024 | Approved | MATTHEW NELSON |
| Green Building Rough | 6/17/2024 | Approved | MATTHEW NELSON |
| HVAC-Rough | 6/17/2024 | Approved | MATTHEW NELSON |
| MERV13>=Rough | 6/17/2024 | Approved | MATTHEW NELSON |
| PLUMBING-Rough | 6/17/2024 | Approved | MATTHEW NELSON |
| Drywall Nailing | 6/26/2024 | Approved | MICHEL ABAJAN |
| Final | 9/11/2024 | Not Ready for Inspection | RYAN SALAZAR |
| Green Building Final | 9/11/2024 | Not Ready for Inspection | RYAN SALAZAR |
| MERV13>=Final | 9/11/2024 | Not Ready for Inspection | RYAN SALAZAR |
| SGSOV-Seismic Gas S/O Valve | 9/11/2024 | SGSOV Not Ready | RYAN SALAZAR |
| Smoke Detectors | 9/11/2024 | Not Ready for Inspection | RYAN SALAZAR |
| ELECTRICAL-Final | 9/12/2024 | Approved | MICHEL ABAJAN |
| Final | 9/12/2024 | OK to Issue CofO | MICHEL ABAJAN |
| Green Building Final | 9/12/2024 | Approved | MICHEL ABAJAN |
| HVAC-Final | 9/12/2024 | Approved | MICHEL ABAJAN |
| MERV13>=Final | 9/12/2024 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 9/12/2024 | Approved | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 9/12/2024 | SGSOV Approved | MICHEL ABAJAN |
| Smoke Detectors | 9/12/2024 | Approved | MICHEL ABAJAN |