7431-7433 N SATSUMA AVE 91352

Certificate Information: 7431-7433 N SATSUMA AVE 91352

Application / Permit
24014-20000-01027
Plan Check / Job No.
B24VN03419
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION OF ATTACHED ACCESSORY DWELLING UNIT TO (E) S.F.D. TO COMPLY WITH LAMC 12.22 A.33(c) AND (e) PER ENGINEERING.
Permit Issued
Issued on 6/27/2024
Issuing Office
Current Status
CofO Issued on 1/17/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/15/2024 APPLICANT
Assigned to Plan Check Engineer 3/20/2024 ALFRED RAMIREZ
Corrections Issued 3/20/2024 ALFRED RAMIREZ
Applicant returned to address corrections 6/20/2024 MOHAMMAD ESMAILI
Plan Check Approved 6/25/2024 ROSENDO MEDINA
Issued 6/27/2024 APPLICANT
CofO in Progress 12/2/2024 ROBERTO PALACIOS-LOPEZ
Permit Finaled 1/17/2025 RUBEN SALAS
CofO Issued 1/17/2025 RUBEN SALAS
Permit Finaled 1/17/2025 RUBEN SALAS

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 3/29/2024 BIAINA HARITUNIAN
Address approval Cleared 5/6/2024 BIAINA HARITUNIAN
Sewer availability Cleared 5/6/2024 BIAINA HARITUNIAN
Low Impact Development (LID) Cleared 6/10/2024 MITESH PATEL
Roof/Waste drainage to street Cleared 6/12/2024 BIAINA HARITUNIAN

Contact Information

Contractor Owner-Builder       ,
Engineer Melchor,, Oscar Elias; Lic. No.: C76828 21243 VENTURA BLVD SUITE 119      WOODLAND HILLS, CA 91364

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 7/15/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Sewer 7/15/2024 Approved ROBERTO PALACIOS-LOPEZ
Underground Mechanical 7/15/2024 Partial Approval ROBERTO PALACIOS-LOPEZ
Deputy Drilled-In Anchors 7/24/2024 Conditional Approval JOSE AVILA
Footing/Foundation/Slab 7/24/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Footing/Foundation/Slab 7/29/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 8/26/2024 Corrections Issued JOSE AVILA
BUILDING-Rough-Frame 8/30/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Rough 8/30/2024 Approved ROBERTO PALACIOS-LOPEZ
Footing/Foundation/Slab 8/30/2024 Approved ROBERTO PALACIOS-LOPEZ
Green Building Rough 8/30/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
PLUMBING-Rough 8/30/2024 Approved ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 9/9/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Green Building Rough 9/9/2024 Approved ROBERTO PALACIOS-LOPEZ
HVAC-Rough 9/9/2024 Approved ROBERTO PALACIOS-LOPEZ
Interior/Exterior Lathing 9/9/2024 Partial Approval ROBERTO PALACIOS-LOPEZ
Shower Pan 9/9/2024 Approved ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 9/12/2024 Approved ROBERTO PALACIOS-LOPEZ
Insulation 9/12/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Drywall Nailing 9/18/2024 Approved ROBERTO PALACIOS-LOPEZ
Insulation 9/18/2024 Approved ROBERTO PALACIOS-LOPEZ
Interior/Exterior Lathing 9/18/2024 Approved ROBERTO PALACIOS-LOPEZ
Underground Mechanical 10/22/2024 Partial Approval ROBERTO PALACIOS-LOPEZ
Final 10/31/2024 No Access for Inspection ROBERTO PALACIOS-LOPEZ
Green Building Final 10/31/2024 No Access for Inspection ROBERTO PALACIOS-LOPEZ
SGSOV-Seismic Gas S/O Valve 10/31/2024 SGSOV Not Ready ROBERTO PALACIOS-LOPEZ
Smoke Detectors 10/31/2024 No Access for Inspection ROBERTO PALACIOS-LOPEZ
Final 11/7/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Green Building Final 11/7/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
SGSOV-Seismic Gas S/O Valve 11/7/2024 SGSOV Not Ready ROBERTO PALACIOS-LOPEZ
Smoke Detectors 11/7/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Final 11/12/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Green Building Final 11/12/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
SGSOV-Seismic Gas S/O Valve 11/12/2024 SGSOV Not Ready ROBERTO PALACIOS-LOPEZ
Smoke Detectors 11/12/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Final 11/18/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Green Building Final 11/18/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
SGSOV-Seismic Gas S/O Valve 11/18/2024 SGSOV Not Ready ROBERTO PALACIOS-LOPEZ
Smoke Detectors 11/18/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Final 11/22/2024 Corrections Issued JOSE AVILA
Green Building Final 11/22/2024 Approved JOSE AVILA
SGSOV-Seismic Gas S/O Valve 11/22/2024 SGSOV Approved JOSE AVILA
Smoke Detectors 11/22/2024 Approved JOSE AVILA
Final 11/27/2024 OK to Issue CofO ROBERTO PALACIOS-LOPEZ
Service/Power Release 11/27/2024 Approved ROBERTO PALACIOS-LOPEZ