5213 N BEEMAN AVE 91607
Certificate Information: 5213 N BEEMAN AVE 91607
- Application / Permit
- 24014-20000-01021
- Plan Check / Job No.
- B24VN03406
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITIONS OF 7'-6" X 17'-7" AND 18'-10" X 17'-7" TO THE REAR OF THE (E) SFD AND REMOVE AND REPLACE WINDOWS AND REMOVE THE ATTACHED PORTE COCHERE - PER ENGINEER **"COMPLY WITH DEPARTMENT ORDER effective date 03/04/2024. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
- Permit Issued
- Issued on 4/5/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 6/6/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/13/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 3/13/2024 | DANIEL ABRAMYAN |
| Corrections Issued | 3/13/2024 | DANIEL ABRAMYAN |
| Plan Check Approved | 4/1/2024 | ANGELICA MARTINEZ |
| Issued | 4/5/2024 | APPLICANT |
| CofO in Progress | 5/13/2025 | SCOTT SHUSTER |
| Permit Finaled | 6/6/2025 | DAVID JAMES |
| CofO Issued | 6/6/2025 | DAVID JAMES |
| Permit Finaled | 6/6/2025 | DAVID JAMES |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 3/18/2024 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 3/21/2024 | CARLOS AGUILERA |
| Specific Plan | Cleared | 3/29/2024 | MAREN GAMBOA |
| Specific Plan | Cleared | 3/29/2024 | MAREN GAMBOA |
Contact Information
| Contractor | New Beginnning Construction Company The; Lic. No.: 848904-B | 3837 E COCHRAN STREET SIMI VALLEY, CA 93063 |
| Engineer | Khanlou,, Amir; Lic. No.: C87550 | 2603 BASIL LN LOS ANGELES, CA 90077 |
Inspector Information
| ARA SINANIAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| HASANTHA WEERASEKARA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| SCOTT SHUSTER, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOEL GUARDADO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARIYA MIHALEVA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOSE RUBIO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| DAVID JAMES, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| DAVID HICKMAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN HAMILTON, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN STEPHENS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| PIERRE VEGA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARK VAN SLOOTEN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MICKEY YAMASHITA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| KIM BEAUCHAMP, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARK DOVICO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| THOMAS WOODS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAUL VASQUEZ, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| AUGUSTUS ALBAS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| LEO MILBAUER, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARIO CUEVAS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/11/2024 | Partial Inspection | SCOTT SHUSTER |
| Deputy Drilled-In Anchors | 4/18/2024 | Conditional Approval | SCOTT SHUSTER |
| Footing/Foundation/Slab | 4/23/2024 | Partial Inspection | SCOTT SHUSTER |
| Wood Frame | 4/23/2024 | Not Ready for Inspection | SCOTT SHUSTER |
| Footing/Foundation/Slab | 5/29/2024 | Partial Inspection | SCOTT SHUSTER |
| Footing/Foundation/Slab | 6/11/2024 | Not Ready for Inspection | THOMAS WOODS |
| Footing/Foundation/Slab | 6/17/2024 | Partial Approval | THOMAS WOODS |
| Interior/Exterior Lathing | 6/17/2024 | Partial Approval | THOMAS WOODS |
| Deputy Steel/Welding | 7/5/2024 | Conditional Approval | SCOTT SHUSTER |
| Footing/Foundation/Slab | 7/5/2024 | Partial Inspection | SCOTT SHUSTER |
| Structural Steel Frame | 7/5/2024 | Partial Inspection | SCOTT SHUSTER |
| ELECTRICAL-Rough | 9/3/2024 | Partial Inspection | SCOTT SHUSTER |
| Deputy Reinf. Concrete | 1/24/2025 | Approved | SCOTT SHUSTER |
| Interior/Exterior Lathing | 1/24/2025 | Partial Approval | SCOTT SHUSTER |
| BUILDING-Rough-Frame | 3/18/2025 | Partial Inspection | SCOTT SHUSTER |
| Green Building Rough | 3/18/2025 | Approved | SCOTT SHUSTER |
| Wood Frame | 3/26/2025 | Partial Inspection | SCOTT SHUSTER |
| BUILDING-Rough-Frame | 5/12/2025 | Approved | SCOTT SHUSTER |
| Drywall Nailing | 5/12/2025 | Approved | SCOTT SHUSTER |
| Final | 5/12/2025 | Partial Approval | SCOTT SHUSTER |
| Footing/Foundation/Slab | 5/12/2025 | Approved | SCOTT SHUSTER |
| Green Building Final | 5/12/2025 | Approved | SCOTT SHUSTER |
| SGSOV-Seismic Gas S/O Valve | 5/12/2025 | SGSOV Approved | SCOTT SHUSTER |
| Smoke Detectors | 5/12/2025 | Approved | SCOTT SHUSTER |
| Final | 5/13/2025 | OK to Issue CofO | SCOTT SHUSTER |