4432 N TALOFA AVE 91602
Certificate Information: 4432 N TALOFA AVE 91602
- Application / Permit
- 24014-20000-01010
- Plan Check / Job No.
- B24VN03350
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN: MAJOR REMODEL, ADDITION AT REAR AND FRONT PORCH ADDITION TO (E) SFD. NFPA 13D FIRE SPRINKLERS TO BE PROVIDED THROUGHOUT
- Permit Issued
- Issued on 7/18/2024
- Issuing Office
- Current Status
- Issued on 7/18/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 3/14/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 3/19/2024 | LUISANGEL VALENZUELA |
| Corrections Issued | 3/20/2024 | LUISANGEL VALENZUELA |
| Applicant returned to address corrections | 5/8/2024 | SERGIO MUNIZ |
| Applicant returned to address corrections | 6/21/2024 | MOHAMMAD ESMAILI |
| Plan Check Approved | 7/17/2024 | GURUNATH NESARAJAH |
| Issued | 7/18/2024 | APPLICANT |
Permit Application Clearance Information
| ZI | Cleared | 3/27/2024 | DORIAN AGUILAR |
| Eng Process Fee Ord 176,300 | Cleared | 4/4/2024 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 4/4/2024 | BIAINA HARITUNIAN |
| Low Impact Development (LID) | Cleared | 4/25/2024 | MELINEH AGHAKHABIAN |
| Roof/Waste drainage to street | Cleared | 5/7/2024 | BIAINA HARITUNIAN |
| ZI | Cleared | 7/8/2024 | DORIAN AGUILAR |
Contact Information
| Contractor | J D R Construction; Lic. No.: 991165-B | , |
| Engineer | Castillo,, Margarito; Lic. No.: S4808 | 1205 PINE AVE SUITE 201 LONG BEACH, CA 90813 |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 7/23/2024 | Conditional Approval | JUAN VALENZUELA |
| Excavation/Setback/Form/Re-Bar | 7/26/2024 | Approved | CHRISTOPHER ROJAS |
| Footing/Foundation/Slab | 7/26/2024 | Approved | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 8/9/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| Deputy Reinf. Concrete | 8/27/2024 | Conditional Approval | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 8/28/2024 | Partial Approval | CHRISTOPHER ROJAS |
| Gas Test | 8/28/2024 | Approved | CHRISTOPHER ROJAS |
| Insulation | 8/28/2024 | Partial Approval | CHRISTOPHER ROJAS |
| PLUMBING-Rough | 8/28/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| Deputy Steel/Welding | 8/30/2024 | Conditional Approval | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 10/29/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| ELECTRICAL-Rough | 10/29/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Floor/Roof Diaphrgm/Shear Wall | 10/29/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Green Building Rough | 10/29/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| HVAC-Rough | 10/29/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| MERV13>=Rough | 10/29/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| PLUMBING-Rough | 10/29/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 10/30/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| ELECTRICAL-Rough | 10/30/2024 | Approved | CHRISTOPHER ROJAS |
| Floor/Roof Diaphrgm/Shear Wall | 10/30/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| HVAC-Rough | 10/30/2024 | Approved | CHRISTOPHER ROJAS |
| PLUMBING-Rough | 10/30/2024 | Approved | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 11/1/2024 | Approved | CHRISTOPHER ROJAS |
| Floor/Roof Diaphrgm/Shear Wall | 11/1/2024 | Approved | CHRISTOPHER ROJAS |
| Green Building Rough | 11/1/2024 | Approved | CHRISTOPHER ROJAS |
| MERV13>=Rough | 11/1/2024 | Approved | CHRISTOPHER ROJAS |
| Insulation | 11/21/2024 | Approved | CHRISTOPHER ROJAS |
| Interior/Exterior Lathing | 11/21/2024 | Partial Approval | CHRISTOPHER ROJAS |
| Interior/Exterior Lathing | 12/9/2024 | Approved | CHRISTOPHER ROJAS |
| Shower Pan | 12/9/2024 | Approved | CHRISTOPHER ROJAS |
| Drywall Nailing | 12/24/2024 | Corrections Issued | OGANES TARAKHCHYAN |
| Drywall Nailing | 12/27/2024 | Approved | CHRISTOPHE COCHRAN |
| ELECTRICAL-Final | 10/1/2025 | Corrections Issued | JAVIER RAMOS JR |
| Final | 10/1/2025 | Corrections Issued | JAVIER RAMOS JR |
| Green Building Final | 10/1/2025 | Approved | JAVIER RAMOS JR |
| MERV13>=Final | 10/1/2025 | Approved | JAVIER RAMOS JR |
| PLUMBING-Final | 10/1/2025 | Approved | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 10/1/2025 | SGSOV Approved | JAVIER RAMOS JR |
| Service/Power Release | 10/1/2025 | Approved | JAVIER RAMOS JR |
| Smoke Detectors | 10/1/2025 | Approved | JAVIER RAMOS JR |
| ELECTRICAL-Final | 10/3/2025 | Approved | CHRISTOPHE COCHRAN |
| HVAC-Final | 10/3/2025 | Approved | CHRISTOPHE COCHRAN |