7317-7321 N DARBY PL 91335
Certificate Information: 7317-7321 N DARBY PL 91335
- Application / Permit
- 24014-20000-00983
- Plan Check / Job No.
- B24VN03259
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- EPLAN CONVERT GARAGE AND STORAGE AT 1ST FLOOR TO SFD per SB9 Two-Unit Development Ca Govt Code 65852.21 TO CREATE A DUPLEX. CONVERT 1ST AND 2ND FLOOR FOR NEW ACCESSORY DWELLING PER LAMC 12.22 A.33 (c) and (e). NFPA 13D FIRE SPRINKLERS THROUGHOUT.
- Permit Issued
- Issued on 4/11/2025
- Issuing Office
- Current Status
- CofO Issued on 1/28/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/20/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 4/4/2024 | RAPHAEL ROSAS |
| Corrections Issued | 4/9/2024 | RAPHAEL ROSAS |
| Quality Review Completed | 4/9/2024 | STEVEN KIM |
| Applicant returned to address corrections | 7/30/2024 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 8/23/2024 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 9/3/2024 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 4/2/2025 | RAPHAEL ROSAS |
| Plan Check Approved | 4/8/2025 | RAPHAEL ROSAS |
| Issued | 4/11/2025 | APPLICANT |
| CofO in Progress | 12/22/2025 | ARUTYUN MADATYAN |
| Permit Finaled | 1/28/2026 | JOHN JANSON |
| Permit Finaled | 1/28/2026 | JOHN JANSON |
| CofO Issued | 1/28/2026 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 5/14/2024 | BIAINA HARITUNIAN |
| Roof/Waste drainage to street | Cleared | 5/14/2024 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 5/15/2024 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 5/15/2024 | BIAINA HARITUNIAN |
| Senate Bill 9 | Cleared | 6/25/2024 | ROSALINDA MEZA |
| Trees in Parkway | Cleared | 7/11/2024 | MIGUEL ORNELAS |
| Permit | Cleared | 7/15/2024 | BIAINA HARITUNIAN |
Contact Information
| Contractor | Markarian Setrag; Lic. No.: 832632-B | , |
| Contractor | Pampa Investment Inc; Lic. No.: 832632-B | , |
| Engineer | Moser,, Bradley Charles; Lic. No.: C68803 | 116 OAKSIDE LN BUELLTON, CA 93427 |
| Engineer | Moser,, Bradley Charles; Lic. No.: NA68803 | , |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 5/1/2025 | Conditional Approval | ROBERT GOLD |
| Footing/Foundation/Slab | 5/14/2025 | Corrections Issued | ARUTYUN MADATYAN |
| PLUMBING-Rough | 5/14/2025 | Partial Approval | ARUTYUN MADATYAN |
| Deputy Wood Construction | 7/9/2025 | Conditional Approval | ROBERT GOLD |
| BUILDING-Rough-Frame | 7/16/2025 | Approved | ARUTYUN MADATYAN |
| ELECTRICAL-Rough | 7/16/2025 | Approved | ARUTYUN MADATYAN |
| Green Building Rough | 7/16/2025 | Approved | ARUTYUN MADATYAN |
| HVAC-Rough | 7/16/2025 | Approved | ARUTYUN MADATYAN |
| PLUMBING-Rough | 7/16/2025 | Approved | ARUTYUN MADATYAN |
| Insulation | 7/23/2025 | Approved | ARUTYUN MADATYAN |
| Interior/Exterior Lathing | 7/23/2025 | Partial Approval | ARUTYUN MADATYAN |
| Shower Pan | 7/23/2025 | Approved | ARUTYUN MADATYAN |
| Drywall Nailing | 7/30/2025 | Approved | JUAN ALVARADO |
| Interior/Exterior Lathing | 7/30/2025 | Approved | JUAN ALVARADO |
| ELECTRICAL-Final | 12/10/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Final | 12/10/2025 | Corrections Issued | ARUTYUN MADATYAN |
| Footing/Foundation/Slab | 12/10/2025 | Approved | ARUTYUN MADATYAN |
| Green Building Final | 12/10/2025 | Approved | ARUTYUN MADATYAN |
| HVAC-Final | 12/10/2025 | Approved | ARUTYUN MADATYAN |
| PLUMBING-Final | 12/10/2025 | Approved | ARUTYUN MADATYAN |
| SGSOV-Seismic Gas S/O Valve | 12/10/2025 | SGSOV Approved | ARUTYUN MADATYAN |
| Service/Power Release | 12/10/2025 | Approved | ARUTYUN MADATYAN |
| Smoke Detectors | 12/10/2025 | Approved | ARUTYUN MADATYAN |
| ELECTRICAL-Final | 12/22/2025 | Approved | ARUTYUN MADATYAN |
| Final | 12/22/2025 | OK to Issue CofO | ARUTYUN MADATYAN |
| HVAC-Final | 12/22/2025 | Approved | ARUTYUN MADATYAN |
| PLUMBING-Final | 12/22/2025 | Approved | ARUTYUN MADATYAN |