19136 W CASTLEBAY LANE 91326
Certificate Information: 19136 W CASTLEBAY LANE 91326
- Application / Permit
- 24014-20000-00969
- Plan Check / Job No.
- B24VN03213
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN (E) HOUSE REMODELING AND 2-STORY ADDITION
- Permit Issued
- Issued on 12/4/2024
- Issuing Office
- Current Status
- Issued on 12/4/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 3/11/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 3/21/2024 | ARSALAN SHABESTARI |
| Corrections Issued | 3/23/2024 | ARSALAN SHABESTARI |
| Quality Review Completed | 4/4/2024 | YOUNG KIM |
| Applicant returned to address corrections | 10/9/2024 | ARSALAN SHABESTARI |
| Plan Check Approved | 12/4/2024 | ARSALAN SHABESTARI |
| Issued | 12/4/2024 | APPLICANT |
Permit Application Clearance Information
| ZA Case | Cleared | 4/3/2024 | ASHLEY RODARTE |
| BHO/Hillside ordinance | Cleared | 4/8/2024 | CARLOS AGUILERA |
| BHO/Hillside ordinance | Cleared | 4/8/2024 | CARLOS AGUILERA |
| BHO/Hillside ordinance | Cleared | 4/8/2024 | CARLOS AGUILERA |
| BHO/Hillside ordinance | Cleared | 4/8/2024 | CARLOS AGUILERA |
| BHO/Hillside ordinance | Cleared | 4/8/2024 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 4/8/2024 | CARLOS AGUILERA |
| Sewer availability | Cleared | 4/8/2024 | CARLOS AGUILERA |
| Miscellaneous | Cleared | 4/10/2024 | ASHLEY RODARTE |
| Hydrant and Access approval | Cleared | 5/11/2024 | KURT CORRAL |
| Low Impact Development (LID) | Cleared | 9/24/2024 | MARCO SANCHEZ |
| Roof/Waste drainage to street | Cleared | 10/10/2024 | RYAN CASTRO |
| GPI Written Notices | Cleared | 12/4/2024 | ARSALAN SHABESTARI |
| Grading Pre-Inspection | Cleared | 12/4/2024 | ARSALAN SHABESTARI |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JEFFREY PARD, (818) 774-4312 | Office Hours: 7:00-8:00 AM MON-FRI |
| STEVEN BACK, (818) 774-4312 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 2/5/2025 | Not Ready for Inspection | SCOTT SOBEL |
| Sewer | 2/5/2025 | Not Ready for Inspection | SCOTT SOBEL |
| Footing/Foundation/Slab | 2/12/2025 | Corrections Issued | SCOTT SOBEL |
| PLUMBING-Rough | 2/19/2025 | Partial Approval | HENRY KIM |
| Sewer | 2/19/2025 | Not Ready for Inspection | HENRY KIM |
| Deputy Other (see comments) | 3/6/2025 | Conditional Approval | STEVEN BACK |
| METHANE-Rough | 3/7/2025 | Not Ready for Inspection | STEVEN BACK |
| METHANE-Barrier | 3/27/2025 | Not Ready for Inspection | STEVEN BACK |
| Deputy Drilled-In Anchors | 6/6/2025 | Conditional Approval | HENRY KIM |
| Footing/Foundation/Slab | 6/10/2025 | Corrections Issued | STEVEN BACK |
| METHANE-Barrier | 6/10/2025 | Approved | STEVEN BACK |
| METHANE-Subgrade | 6/10/2025 | Approved | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 7/21/2025 | Corrections Issued | STEVEN BACK |
| Footing/Foundation/Slab | 7/21/2025 | Corrections Issued | STEVEN BACK |
| Deputy Wood Construction | 8/21/2025 | Conditional Approval | HENRY KIM |
| Floor/Roof Diaphrgm/Shear Wall | 11/6/2025 | Approved | STEVEN BACK |
| BUILDING-Rough-Frame | 12/16/2025 | Approved | STEVEN BACK |
| ELECTRICAL-Rough | 12/16/2025 | Approved | STEVEN BACK |
| Footing/Foundation/Slab | 12/16/2025 | Approved | STEVEN BACK |
| Green Building Rough | 12/16/2025 | Approved | STEVEN BACK |
| HVAC-Rough | 12/16/2025 | Approved | STEVEN BACK |
| METHANE-Rough | 12/16/2025 | Approved | STEVEN BACK |
| PLUMBING-Rough | 12/16/2025 | Approved | STEVEN BACK |
| Verify Sprinkler Sign Off | 12/16/2025 | Approved | STEVEN BACK |
| Insulation | 1/6/2026 | Approved | STEVEN BACK |
| Drywall Nailing | 1/15/2026 | Approved | JEFFREY PARD |
| Interior/Exterior Lathing | 1/26/2026 | Approved | STEVEN BACK |
| Shower Pan | 1/26/2026 | Approved | STEVEN BACK |
| Sewer | 7/1/2026 | Approved | STEVEN BACK |